14153 W ARCHWOOD ST 91405
Certificate Information: 14153 W ARCHWOOD ST 91405
- Application / Permit
- 19010-30000-02999
- Plan Check / Job No.
- B19WL03936
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- NEW 1-STORY TYPE VB 2-CAR GARAGE.
- Permit Issued
- Issued on 2/10/2021
- Issuing Office
- Valley
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/15/2019 | APPLICANT |
| Green Plans Picked Up | 8/14/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 8/15/2019 | SERGIO SILVA |
| Corrections Issued | 8/21/2019 | SERGIO SILVA |
| Quality Review Completed | 8/22/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/31/2020 | SERGIO SILVA |
| Plan Check Approved | 1/7/2021 | SERGIO SILVA |
| Building Plans Picked Up | 1/15/2021 | APPLICANT |
| Issued | 2/10/2021 | APPLICANT |
| CofO in Progress | 12/14/2022 | RYAN SALAZAR |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
| CofO Issued | 12/17/2022 | MICHAEL SMITH |
| Permit Finaled | 12/17/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Permit | Cleared | 6/25/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 6/25/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 8/4/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 8/20/2020 | ROBIN YAMADA |
| Green Code | Cleared | 9/4/2020 | SERGIO SILVA |
| CPC | Cleared | 1/5/2021 | SUKI GERSHENHORN |
| CPC | Cleared | 1/5/2021 | SUKI GERSHENHORN |
| CPC | Cleared | 1/5/2021 | SUKI GERSHENHORN |
| HPOZ | Cleared | 1/5/2021 | SUKI GERSHENHORN |
| ZA Case | Cleared | 1/5/2021 | SUKI GERSHENHORN |
| ZI | Cleared | 1/5/2021 | SUKI GERSHENHORN |
| Address approval | Cleared | 1/6/2021 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2021 | GUILLERMO PETRA |
| Roof/Waste drainage to street | Cleared | 1/6/2021 | GUILLERMO PETRA |
| Trees in Parkway | Cleared | 1/11/2021 | JOHN KIM |
Contact Information
| Contractor | Munoz Carlos Enrique; Lic. No.: 908224-B | 2027 PHILLIPPI STREET SAN FERNANDO, CA 91340 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/17/2021 | Partial Inspection | MARK JOHNSON |
| Footing/Foundation/Slab | 3/25/2021 | Partial Inspection | MICHAEL TEMPLE |
| Footing/Foundation/Slab | 3/26/2021 | Corrections Issued | MICHAEL TEMPLE |
| Excavation/Setback/Form/Re-Bar | 5/5/2021 | Approved | DAVID SCANTLIN |
| Footing/Foundation/Slab | 5/5/2021 | Approved | DAVID SCANTLIN |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Not Ready for Inspection | JOHN HAYES |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2021 | Partial Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/9/2021 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/15/2021 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 3/22/2022 | Approved | RICHARD DOCKUS |
| Interior/Exterior Lathing | 4/6/2022 | Partial Approval | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 10/5/2022 | Approved | RICHARD DOCKUS |
| Drywall Nailing | 10/5/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Final | 10/5/2022 | Approved | RICHARD DOCKUS |
| Green Building Final | 10/5/2022 | Approved | RICHARD DOCKUS |
| Green Building Rough | 10/5/2022 | Approved | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Approved | RICHARD DOCKUS |
| Smoke Detectors | 10/5/2022 | Approved | RICHARD DOCKUS |
| Final | 11/10/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Service/Power Release | 11/10/2022 | Not Required | RICHARD DOCKUS |
| Final | 12/13/2022 | OK to Issue CofO | RYAN SALAZAR |
| HVAC-Final | 12/13/2022 | Approved | RYAN SALAZAR |
| PLUMBING-Final | 12/13/2022 | Approved | RYAN SALAZAR |