10768 W BELLAGIO ROAD 90077
Certificate Information: 10768 W BELLAGIO ROAD 90077
- Application / Permit
- 19010-30000-02818
- Plan Check / Job No.
- B19WL03698
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Commercial
- Primary Use
- (4) Golf Club
- Work Description
- NEW GUESTHOUSE (5-GUESTROOMS) ACCESSORY TO GOLF CLUB. PER ZA-2019-1078-PAD
- Permit Issued
- Issued on 9/3/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/11/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 7/2/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2019 | TARIK SAOUD |
| Corrections Issued | 7/29/2019 | TARIK SAOUD |
| Quality Review Completed | 8/15/2019 | FELIX FIGUEROA |
| Disabled Access Plans Picked Up | 8/20/2019 | APPLICANT |
| Green Plans Picked Up | 6/9/2020 | APPLICANT |
| Applicant returned to address corrections | 8/3/2020 | TARIK SAOUD |
| Plan Check Approved | 8/4/2020 | TARIK SAOUD |
| Building Plans Picked Up | 9/2/2020 | APPLICANT |
| Issued | 9/3/2020 | APPLICANT |
| Permit Finaled | 5/11/2026 | VASIL MIHALEV |
| CofO Issued | 5/11/2026 | VASIL MIHALEV |
| Permit Finaled | 5/11/2026 | VASIL MIHALEV |
Permit Application Clearance Information
| ZA Case | Cleared | 10/3/2019 | JOE LUCKEY |
| ZA Case | Cleared | 10/3/2019 | JOE LUCKEY |
| DAS Clearance | Cleared | 11/19/2019 | SOMKIAT SUPANYACHOTSKUL |
| Eng Process Fee Ord 176,300 | Cleared | 2/11/2020 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 2/11/2020 | EMIL KYUPELYAN |
| Internal circulation | Cleared | 2/19/2020 | COLLINS ALLAN |
| CPC | Cleared | 2/20/2020 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 2/20/2020 | DENZEL HENDERSON |
| Miscellaneous | Cleared | 2/20/2020 | DENZEL HENDERSON |
| Site Plan review | Cleared | 2/20/2020 | DENZEL HENDERSON |
| ZA Case | Cleared | 2/20/2020 | DENZEL HENDERSON |
| Fire Marshall Fire Life Safety | Cleared | 3/23/2020 | OSCAR SALGADO JR |
| Construction near power lines | Cleared | 4/13/2020 | WALTER RAMIREZ |
| Green Code | Cleared | 5/13/2020 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 5/22/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 7/6/2020 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 7/30/2020 | MAHELET GEBEYHU |
Contact Information
| Architect | Marsh,, Michael Steven; Lic. No.: C23523 | 15900 LA CANTERA PARKWAY SUITE 19205 SAN ANTONIO, TX 78256 |
| Contractor | Hayhoe Construction Corporation; Lic. No.: 519186-B | 17821 EAST 17TH STREET STE 150 TUSTIN, CA 92780 |
| Engineer | Leffler,, Russell David; Lic. No.: C65053 | 165 S UNION BLVD STE 360 LAKEWOOD, CO 80228 |
| Engineer | Liston,, Leonard Irvin; Lic. No.: C31902 | 889 PIERCE CT STE 101 THOUSAND OAKS, CA 91360 |
| Geologist | Holt,, Jacob William; Lic. No.: EG2282 | 5158 COCHRAN ST SIMI VALLEY, CA 93063 |
Inspector Information
| DERRICK SPENCER, (310) 914-3919 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2021 | Approved | DERRICK SPENCER |
| Piling/Pier/Caisson | 10/19/2022 | Partial Approval | DERRICK SPENCER |
| Footing/Foundation/Slab | 5/25/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/21/2023 | Approved | DERRICK SPENCER |
| Deputy Shotcrete | 6/21/2023 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 6/22/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/27/2023 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 6/27/2023 | Partial Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 6/28/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 8/3/2023 | Approved | DERRICK SPENCER |
| Footing/Foundation/Slab | 8/7/2023 | Partial Approval | DERRICK SPENCER |
| Structural Steel Frame | 8/7/2023 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 10/13/2023 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Concrete | 10/23/2023 | Approved | DERRICK SPENCER |
| Deputy Wood Construction | 10/26/2023 | Approved | DERRICK SPENCER |
| Floor/Roof Diaphrgm/Shear Wall | 10/26/2023 | Approved | DERRICK SPENCER |
| Deputy Wood Construction | 11/9/2023 | Conditional Approval | PAUL DAVIDSON |
| Light Gage Steel Frame | 11/14/2023 | Approved | DERRICK SPENCER |
| Wood Frame | 11/14/2023 | Approved | DERRICK SPENCER |
| Insulation | 12/14/2023 | Approved | DERRICK SPENCER |
| Interior/Exterior Lathing | 1/11/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 1/17/2024 | Conditional Approval | DERRICK SPENCER |
| Deputy Reinf. Masonry | 1/18/2024 | Approved | DERRICK SPENCER |
| Deputy Reinf. Masonry | 1/19/2024 | Approved | DERRICK SPENCER |
| Final | 1/30/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Footing/Foundation/Slab | 1/30/2024 | Approved | DERRICK SPENCER |
| Green Building Final | 1/30/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Rough | 1/30/2024 | Approved | DERRICK SPENCER |
| Interior/Exterior Lathing | 1/30/2024 | Approved | DERRICK SPENCER |
| Reinforced Masonry Frame | 1/30/2024 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 1/30/2024 | SGSOV Not Ready | DERRICK SPENCER |
| Smoke Detectors | 1/30/2024 | Approved | DERRICK SPENCER |
| Verify Sprinkler Sign Off | 1/30/2024 | Approved | DERRICK SPENCER |
| Reinforced Concrete Frame | 3/27/2024 | Partial Approval | DERRICK SPENCER |
| Insulation | 4/11/2024 | Approved | DERRICK SPENCER |
| Drywall Nailing | 4/17/2024 | Approved | DERRICK SPENCER |
| Insulation | 5/29/2024 | Approved | DERRICK SPENCER |
| Final | 9/6/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Green Building Final | 9/6/2024 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 9/6/2024 | SGSOV Approved | DERRICK SPENCER |
| Final | 9/11/2024 | Not Ready for Inspection | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 1/8/2026 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 1/9/2026 | Approved | DERRICK SPENCER |
| Deputy Reinf. Concrete | 1/9/2026 | Approved | DERRICK SPENCER |
| Final | 1/29/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Final | 2/27/2026 | Not Ready for Inspection | DERRICK SPENCER |
| Deputy Other (see comments) | 3/10/2026 | Approved | DERRICK SPENCER |
| Final | 3/10/2026 | Partial Approval | DERRICK SPENCER |
| Deputy Other (see comments) | 3/23/2026 | Approved | DERRICK SPENCER |