Permit Issued
Issued on 1/16/2020
Issuing Office
Valley
Current Status
CofO Issued on 4/29/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/21/2019 APPLICANT
Assigned to Plan Check Engineer 7/18/2019 MICHAEL PEREZ
Corrections Issued 7/26/2019 MICHAEL PEREZ
Quality Review Completed 8/8/2019 JOSE RODRIGUEZ
Building Plans Picked Up 8/12/2019 APPLICANT
Plan Check Approved 1/14/2020 MICHAEL PEREZ
Issued 1/16/2020 LADBS
CofO in Progress 4/29/2021 KENNETH NAGLE
Permit Finaled 4/29/2021 KENNETH NAGLE
CofO Issued 4/29/2021 KENNETH NAGLE
Permit Finaled 4/29/2021 KENNETH NAGLE

Permit Application Clearance Information

CPC Cleared 9/25/2019 NOAH MCCOY
CPC Cleared 9/25/2019 NOAH MCCOY
CPC Cleared 9/25/2019 NOAH MCCOY
CPC Cleared 9/25/2019 NOAH MCCOY
Eng Process Fee Ord 176,300 Cleared 9/25/2019 OSCAR GUTIERREZ
Sewer availability Cleared 9/25/2019 OSCAR GUTIERREZ
Address approval Cleared 9/26/2019 DINAH GARIN
Hydrant and Access approval Cleared 9/30/2019 GILBERT URREA
Low Impact Development Cleared 11/6/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 11/12/2019 GUILLERMO PETRA
Green Code Cleared 11/26/2019 RICHARD GARCIA
GPI Written Notices Cleared 12/23/2019 JOSE RODRIGUEZ
Grading Pre-Inspection Cleared 12/23/2019 MICHAEL PEREZ
Construction near power lines Cleared 1/14/2020 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/2/2020 Corrections Issued JUAN VALENZUELA
Underground Mechanical 4/2/2020 Corrections Issued JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 4/7/2020 Approved JUAN VALENZUELA
Underground Mechanical 4/7/2020 Approved JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 4/28/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 5/7/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 5/19/2020 Partial Approval DAVID HEINE
BUILDING-Rough-Frame 6/5/2020 Corrections Issued JUAN VALENZUELA
Green Building Rough 6/5/2020 Not Ready for Inspection JUAN VALENZUELA
MERV13>=Rough 6/5/2020 Not Ready for Inspection JUAN VALENZUELA
Verify Sprinkler Sign Off 6/5/2020 Not Ready for Inspection JUAN VALENZUELA
Deputy Wood Construction 6/15/2020 Conditional Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 6/17/2020 Partial Inspection JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 6/22/2020 Corrections Issued JUAN VALENZUELA
Special/Order Compliance 6/22/2020 Partial Inspection KENNETH NAGLE
ELECTRICAL-Rough 7/7/2020 Corrections Issued JUAN VALENZUELA
HVAC-Rough 7/7/2020 Corrections Issued JUAN VALENZUELA
PLUMBING-Rough 7/7/2020 Partial Approval JUAN VALENZUELA
Underground Mechanical 7/24/2020 Partial Approval JUAN VALENZUELA
BUILDING-Rough-Frame 8/26/2020 Partial Approval KENNETH NAGLE
ELECTRICAL-Rough 8/26/2020 Approved KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/26/2020 Partial Approval KENNETH NAGLE
HVAC-Rough 9/3/2020 Approved JUAN VALENZUELA
Interior/Exterior Lathing 9/3/2020 Partial Approval JUAN VALENZUELA
PLUMBING-Rough 9/3/2020 Corrections Issued JUAN VALENZUELA
BUILDING-Rough-Frame 9/14/2020 Approved JUAN VALENZUELA
Green Building Rough 9/14/2020 Approved JUAN VALENZUELA
MERV13>=Rough 9/14/2020 Approved JUAN VALENZUELA
PLUMBING-Rough 9/14/2020 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 9/14/2020 Approved JUAN VALENZUELA
Insulation 9/25/2020 Approved JUAN VALENZUELA
Drywall Nailing 9/29/2020 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 10/28/2020 Approved JUAN VALENZUELA
Shower Pan 10/28/2020 Approved JUAN VALENZUELA
Final 3/23/2021 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 3/23/2021 Approved BRENDAN LOONEY
Green Building Final 3/23/2021 Not Ready for Inspection BRENDAN LOONEY
MERV13>=Final 3/23/2021 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 3/23/2021 SGSOV Approved BRENDAN LOONEY
Service/Power Release 3/23/2021 Not Required BRENDAN LOONEY
Smoke Detectors 3/23/2021 Approved BRENDAN LOONEY
Final 3/31/2021 Not Ready for Inspection BRENDAN LOONEY
Green Building Final 3/31/2021 Not Ready for Inspection BRENDAN LOONEY
Final 4/29/2021 OK to Issue CofO KENNETH NAGLE
Green Building Final 4/29/2021 Approved KENNETH NAGLE