6704 N BLUCHER AVE 91406

Certificate Information: 6704 N BLUCHER AVE 91406

Application / Permit
19010-30000-02544
Plan Check / Job No.
B19WL03337
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(E)GARAGE CONVERSION TO ACCESSORY DWELLING UNIT AND ADDITION TO ACCESSORY DWELLING UNIT AT REAR OF THE LOT. PER AB494&SB229. EQUIPPED WITH FIRE SPRINKLER SYSTEM NFPA 13D.
Permit Issued
Issued on 10/5/2020
Issuing Office
Current Status
CofO Issued on 8/23/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Green Plans Picked Up 7/2/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 ALFREDO JARA
Corrections Issued 7/10/2019 ALFREDO JARA
Quality Review Completed 7/12/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 7/15/2019 APPLICANT
Plan Check Approved 10/1/2020 ALFREDO JARA
Issued 10/5/2020 APPLICANT
CofO in Progress 11/16/2021 RICHARD DOCKUS
CofO Issued 8/23/2022 MICHAEL SMITH
Permit Finaled 8/23/2022 MICHAEL SMITH

Permit Application Clearance Information

Construction near power lines Cleared 9/21/2019 RIDWAN HARDY
Low Impact Development Cleared 10/23/2019 MITESH PATEL
Address approval Cleared 10/28/2019 ERIK BEASLEY
Roof/Waste drainage to street Cleared 10/28/2019 ERIK BEASLEY
Eng Process Fee Ord 176,300 Cleared 10/29/2019 EMIL KYUPELYAN
Sewer availability Cleared 10/29/2019 EMIL KYUPELYAN
CPC Cleared 11/5/2019 TERRI OSBORNE
CPC Cleared 11/5/2019 TERRI OSBORNE
ZI Cleared 11/5/2019 TERRI OSBORNE
Green Code Cleared 11/6/2019 DONALD CRICHLOW

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/14/2020 Corrections Issued JOHN HAYES
Footing/Foundation/Slab 12/17/2020 Partial Approval MISAEL ESPARZA
PLUMBING-Rough 12/17/2020 Partial Approval MISAEL ESPARZA
Pre-Inspection 12/17/2020 Corrections Issued MISAEL ESPARZA
Footing/Foundation/Slab 1/5/2021 Corrections Issued JENNIFER RABUCHIN
Footing/Foundation/Slab 1/11/2021 Approved JOHN HAYES
Floor/Roof Diaphrgm/Shear Wall 2/25/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 3/5/2021 Approved JENNIFER RABUCHIN
HVAC-Rough 3/5/2021 Corrections Issued JENNIFER RABUCHIN
PLUMBING-Rough 3/10/2021 Approved JOHN STEPHENS
BUILDING-Rough-Frame 3/19/2021 Not Ready for Inspection JOHN HAYES
Green Building Rough 3/19/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Rough 3/19/2021 Not Ready for Inspection JOHN HAYES
Rough-Elec/Plmb/HVAC 3/19/2021 Not Ready for Inspection JOHN HAYES
HVAC-Rough 3/23/2021 Approved RONALD COWAN
BUILDING-Rough-Frame 3/30/2021 Approved DANIEL ORRANTE
Green Building Rough 3/30/2021 Approved DANIEL ORRANTE
MERV13>=Rough 3/30/2021 Approved DANIEL ORRANTE
Gas Test 4/14/2021 Partial Approval JENNIFER RABUCHIN
Insulation 4/14/2021 Approved JENNIFER RABUCHIN
Sewer 4/14/2021 Approved JENNIFER RABUCHIN
Underground Mechanical 4/14/2021 Partial Approval JENNIFER RABUCHIN
Drywall Nailing 4/26/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 4/26/2021 Corrections Issued JENNIFER RABUCHIN
Interior/Exterior Lathing 4/26/2021 Approved JENNIFER RABUCHIN
Shower Pan 4/26/2021 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 7/28/2021 Not Ready for Inspection JOHN HAYES
Final 7/28/2021 Corrections Issued JOHN HAYES
Green Building Final 7/28/2021 Not Ready for Inspection JOHN HAYES
HVAC-Final 7/28/2021 Not Ready for Inspection JOHN HAYES
MERV13>=Final 7/28/2021 Not Ready for Inspection JOHN HAYES
PLUMBING-Final 7/28/2021 Not Ready for Inspection JOHN HAYES
SGSOV-Seismic Gas S/O Valve 7/28/2021 SGSOV Not Ready JOHN HAYES
Service/Power Release 7/28/2021 Not Ready for Inspection JOHN HAYES
Smoke Detectors 7/28/2021 Not Ready for Inspection JOHN HAYES
ELECTRICAL-Final 9/16/2021 Approved RICHARD DOCKUS
Final 9/16/2021 Corrections Issued RICHARD DOCKUS
Green Building Final 9/16/2021 Approved RICHARD DOCKUS
HVAC-Final 9/16/2021 Corrections Issued RICHARD DOCKUS
MERV13>=Final 9/16/2021 Approved RICHARD DOCKUS
PLUMBING-Final 9/16/2021 Approved RICHARD DOCKUS
SGSOV-Seismic Gas S/O Valve 9/16/2021 SGSOV Approved RICHARD DOCKUS
Service/Power Release 9/16/2021 Not Ready for Inspection RICHARD DOCKUS
Smoke Detectors 9/16/2021 Approved RICHARD DOCKUS
ELECTRICAL-Final 9/20/2021 Approved RICHARD DOCKUS
HVAC-Final 9/20/2021 Approved RICHARD DOCKUS
PLUMBING-Final 9/20/2021 Approved RICHARD DOCKUS
Service/Power Release 9/20/2021 Approved RICHARD DOCKUS
Final 9/23/2021 Corrections Issued RICHARD DOCKUS
Final 9/29/2021 Corrections Issued MICHAEL TEMPLE
Final 10/8/2021 OK to Issue CofO RICHARD DOCKUS