1370-1370 1/2 W 35TH PL 90007

Certificate Information: 1370-1370 1/2 W 35TH PL 90007

Application / Permit
19010-30000-02541
Plan Check / Job No.
B19WL03336
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX (FRONT BUILDING)
Permit Issued
Issued on 11/10/2020
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 TARIK SAOUD
Corrections Issued 7/15/2019 TARIK SAOUD
Quality Review Completed 7/17/2019 FELIX FIGUEROA
Green Plans Picked Up 8/6/2019 APPLICANT
Plan Check Approved 2/27/2020 TARIK SAOUD
Issued 11/10/2020 APPLICANT
Building Plans Picked Up 11/13/2020 APPLICANT
CofO in Progress 2/24/2022 SABAS ALONSO
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Green Code Cleared 1/29/2020 DONALD CRICHLOW
Hydrant and Access approval Cleared 2/13/2020 JEREMY CARTER
Miscellaneous Cleared 2/13/2020 TERRI OSBORNE
Trees in Parkway Cleared 2/18/2020 ADRIAN SANCHEZ
Address approval Cleared 2/20/2020 EMIL KYUPELYAN
Eng Process Fee Ord 176,300 Cleared 2/20/2020 EMIL KYUPELYAN
Low Impact Development Cleared 2/20/2020 AMMAR ELTAWIL
Permit Cleared 2/20/2020 EMIL KYUPELYAN
Roof/Waste drainage to street Cleared 2/20/2020 EMIL KYUPELYAN
Sewer availability Cleared 2/20/2020 EMIL KYUPELYAN

Contact Information

Architect Baek,, Sunpil; Lic. No.: C35323 3923 W 6TH ST SUITE 410      LOS ANGELES, CA 90020
Contractor Sunway Construction Inc; Lic. No.: 697180-B 3028 AVIANO COURT      CHINO HILLS, CA 91709
Engineer Hwang,, Junho; Lic. No.: S5592 815 FAIRVIEW AVE #205      SOUTH PASADENA, CA 91030

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/9/2021 Corrections Issued ROBERT MCDOWELL
Underground Mechanical 3/12/2021 Approved ROBERT MCDOWELL
Excavation/Setback/Form/Re-Bar 3/15/2021 Approved ROBERT MCDOWELL
Insulation 3/31/2021 Partial Approval ROBERT MCDOWELL
Sewer 3/31/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/1/2021 Partial Approval ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Approved ROBERT MCDOWELL
Floor/Roof Diaphrgm/Shear Wall 4/27/2021 Partial Approval ROBERT MCDOWELL
ELECTRICAL-Rough 5/24/2021 Not Ready for Inspection ROBERT MCDOWELL
Insulation 5/25/2021 Partial Approval ROBERT MCDOWELL
Rough-Elec/Plmb/HVAC 6/22/2021 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 7/2/2021 Partial Approval JOAQUIN GREENOUGH
Deputy Wood Construction 8/17/2021 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/18/2021 Partial Approval SABAS ALONSO
Deputy Wood Construction 8/23/2021 Conditional Approval WILLIAM WREN
BUILDING-Rough-Frame 8/25/2021 Approved SABAS ALONSO
Green Building Rough 8/25/2021 Approved SABAS ALONSO
METHANE-Rough 8/25/2021 Approved SABAS ALONSO
Verify Sprinkler Sign Off 8/25/2021 Approved SABAS ALONSO
Insulation 8/30/2021 Approved JESUS PINEDA
Drywall Nailing 9/15/2021 Approved WILLIAM WREN
Interior/Exterior Lathing 9/15/2021 Approved WILLIAM WREN
Gas Test 1/28/2022 Approved SHAVONNE ESPINOZA
ELECTRICAL-Final 2/2/2022 Approved SABAS ALONSO
HVAC-Final 2/2/2022 Approved SABAS ALONSO
PLUMBING-Final 2/2/2022 Approved SABAS ALONSO
Final 2/7/2022 Not Ready for Inspection SABAS ALONSO
Service/Power Release 2/7/2022 Not Required SABAS ALONSO
Final 2/18/2022 Corrections Issued SABAS ALONSO
Footing/Foundation/Slab 2/18/2022 Approved SABAS ALONSO
Green Building Final 2/18/2022 Approved SABAS ALONSO
METHANE-Barrier 2/18/2022 Approved SABAS ALONSO
METHANE-Subgrade 2/18/2022 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 2/18/2022 SGSOV Approved SABAS ALONSO
Smoke Detectors 2/18/2022 Approved SABAS ALONSO
Final 2/24/2022 OK to Issue CofO SABAS ALONSO