2033 S BUTLER AVE 90025
Certificate Information: 2033 S BUTLER AVE 90025
- Application / Permit
- 19010-30000-02529
- Plan Check / Job No.
- B19WL03326
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New three story s.f.d. with attached garage. Bld'g A (Per AA-2019-3917-PMLA-CN)
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- CofO Issued on 10/3/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/24/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 7/30/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 8/5/2019 | FELIX FIGUEROA |
| Green Plans Picked Up | 8/14/2020 | APPLICANT |
| Applicant returned to address corrections | 9/17/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/20/2021 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/15/2021 | VLADIMIR ARUTYUNYAN |
| Applicant returned to address corrections | 11/9/2021 | FELIPE HERNANDEZ |
| Plan Check Approved | 12/1/2021 | VLADIMIR ARUTYUNYAN |
| Issued | 1/25/2022 | APPLICANT |
| Building Plans Picked Up | 1/27/2022 | APPLICANT |
| CofO in Progress | 10/1/2024 | KIRK SANDERS |
| Permit Finaled | 10/3/2024 | RICHARD STEINBACH |
| CofO Issued | 10/3/2024 | RICHARD STEINBACH |
| Permit Finaled | 10/3/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 7/31/2020 | DINAH GARIN |
| Permit | Cleared | 7/31/2020 | DINAH GARIN |
| Green Code | Cleared | 8/10/2020 | RICHARD GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 8/25/2020 | DINAH GARIN |
| Sewer availability | Cleared | 8/25/2020 | DINAH GARIN |
| Trees in Parkway | Cleared | 9/14/2020 | JOHN KIM |
| Hydrant and Access approval | Cleared | 10/15/2020 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/14/2020 | JORGE MEJIA LEMUS |
| Miscellaneous | Cleared | 9/30/2021 | LOUIS ORTEGA |
| Highway dedication | Cleared | 10/18/2021 | KATHLEEN LEE |
| Roof/Waste drainage to street | Cleared | 10/18/2021 | KATHLEEN LEE |
Contact Information
| Architect | Bernstein,, William Marlon; Lic. No.: C12137 | 1725 C ABBOT KINNEY BLVD VENICE, CA 90241 |
| Contractor | Mr Build Home Improvement Company; Lic. No.: 439166-B | 12444 VICTORY BLVD UNIT 404 NORTH HOLLYWOOD, CA 91606 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2022 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 6/13/2022 | Partial Approval | KENNETH NAGLE |
| PLUMBING-Rough | 6/14/2022 | Partial Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/15/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Reinf. Concrete | 6/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 7/12/2022 | Approved | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 7/20/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Steel/Welding | 7/21/2022 | Conditional Approval | MICHAEL PELHAM |
| Deputy Steel/Welding | 7/22/2022 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Conditional Approval | JOHN KIDWELL |
| Deputy Wood Construction | 8/2/2022 | Partial Approval | JOHN KIDWELL |
| Deputy Wood Construction | 8/23/2022 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 8/23/2022 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/12/2022 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Rough | 10/12/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Verify Sprinkler Sign Off | 10/12/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Special/Order Compliance | 11/2/2022 | Corrections Issued | MICHAEL PELHAM |
| Special/Order Compliance | 11/2/2022 | Partial Approval | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Partial Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 11/23/2022 | Approved | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/23/2022 | Approved | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 12/28/2022 | Corrections Issued | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/24/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Green Building Rough | 1/24/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| Interior/Exterior Lathing | 1/24/2023 | Corrections Issued | ASHLEY THOMPSON |
| Special/Order Compliance | 1/24/2023 | Partial Inspection | CLAYTON GRAHAM |
| Special/Order Compliance | 1/24/2023 | Partial Inspection | DAVID FEILER |
| Verify Sprinkler Sign Off | 1/24/2023 | Approved | ASHLEY THOMPSON |
| HVAC-Rough | 1/25/2023 | Approved | JULIAN AMAYA |
| BUILDING-Rough-Frame | 1/27/2023 | Corrections Issued | JULIAN AMAYA |
| Interior/Exterior Lathing | 2/8/2023 | Partial Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 2/10/2023 | Partial Approval | CLAYTON GRAHAM |
| Green Building Rough | 2/10/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 2/10/2023 | Partial Approval | CLAYTON GRAHAM |
| Insulation | 2/15/2023 | Corrections Issued | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 2/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Insulation | 2/17/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 2/23/2023 | Approved | CLAYTON GRAHAM |
| Drywall Nailing | 2/24/2023 | Approved | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 4/17/2023 | Partial Approval | CLAYTON GRAHAM |
| Shower Pan | 4/17/2023 | Corrections Issued | CLAYTON GRAHAM |
| Shower Pan | 5/8/2023 | Approved | HERBERT GIRON |
| Shower Pan | 5/9/2023 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 8/23/2023 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 10/24/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Sewer | 10/26/2023 | Approved | KENNETH NAGLE |
| Sewer | 11/17/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Underground Mechanical | 12/5/2023 | Approved | BEN MOLSTAD |
| ELECTRICAL-Final | 12/11/2023 | Corrections Issued | BEN MOLSTAD |
| ELECTRICAL-Final | 12/18/2023 | Not Ready for Inspection | BEN MOLSTAD |
| Gas Test | 12/18/2023 | Partial Approval | BEN MOLSTAD |
| PLUMBING-Final | 12/20/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 1/18/2024 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 1/24/2024 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 5/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 5/22/2024 | Corrections Issued | KIRK SANDERS |
| Green Building Final | 5/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 5/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| PLUMBING-Final | 5/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Not Ready | KIRK SANDERS |
| Service/Power Release | 5/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 5/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| Structural Steel Frame | 5/22/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 5/29/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 5/29/2024 | Corrections Issued | KIRK SANDERS |
| PLUMBING-Final | 5/29/2024 | Corrections Issued | KIRK SANDERS |
| Structural Steel Frame | 5/29/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 6/25/2024 | Conditional Approval | KIRK SANDERS |
| Final | 6/25/2024 | Not Ready for Inspection | KIRK SANDERS |
| Green Building Final | 6/25/2024 | Approved | KIRK SANDERS |
| HVAC-Final | 6/25/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 6/25/2024 | Corrections Issued | KIRK SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/25/2024 | SGSOV Approved | KIRK SANDERS |
| Service/Power Release | 6/25/2024 | Approved | KIRK SANDERS |
| Smoke Detectors | 6/25/2024 | Not Ready for Inspection | KIRK SANDERS |
| Structural Steel Frame | 6/25/2024 | Not Ready for Inspection | KIRK SANDERS |
| Gas Test | 6/28/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 7/11/2024 | Approved | KIRK SANDERS |
| Final | 7/11/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 7/11/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 7/11/2024 | Not Ready for Inspection | KIRK SANDERS |
| Smoke Detectors | 7/11/2024 | Approved | KIRK SANDERS |
| Structural Steel Frame | 7/11/2024 | Not Ready for Inspection | KIRK SANDERS |
| ELECTRICAL-Final | 8/26/2024 | Not Ready for Inspection | KIRK SANDERS |
| Final | 8/26/2024 | Corrections Issued | KIRK SANDERS |
| HVAC-Final | 8/26/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 8/26/2024 | Not Ready for Inspection | KIRK SANDERS |
| Structural Steel Frame | 8/26/2024 | Approved | KIRK SANDERS |
| ELECTRICAL-Final | 9/12/2024 | Corrections Issued | KIRK SANDERS |
| Final | 9/12/2024 | Not Ready for Inspection | KIRK SANDERS |
| HVAC-Final | 9/12/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 9/12/2024 | Corrections Issued | KIRK SANDERS |
| ELECTRICAL-Final | 9/19/2024 | Approved | KIRK SANDERS |
| Final | 9/19/2024 | Partial Approval | KIRK SANDERS |
| HVAC-Final | 9/19/2024 | Approved | KIRK SANDERS |
| PLUMBING-Final | 9/19/2024 | Approved | KIRK SANDERS |
| Final | 10/1/2024 | OK to Issue CofO | KIRK SANDERS |