286 N QUADRO VECCHIO DR 90272
Certificate Information: 286 N QUADRO VECCHIO DR 90272
- Application / Permit
- 19010-30000-02523
- Plan Check / Job No.
- B19WL03317
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New one-story single familey dwelling with basement & attached garage.
- Permit Issued
- Issued on 12/10/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/13/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/11/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 7/16/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 7/17/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 7/18/2019 | APPLICANT |
| Green Plans Picked Up | 7/18/2019 | APPLICANT |
| Applicant returned to address corrections | 8/20/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/12/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 9/26/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/15/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/21/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 12/10/2019 | KAMRAN GHOTBI RAVANDI |
| Issued | 12/10/2019 | LADBS |
| CofO in Progress | 11/7/2022 | BRENDAN LOONEY |
| Permit Finaled | 2/2/2023 | DANIEL ORRANTE |
| CofO Issued | 2/2/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/2/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Trees in Parkway | Cleared | 8/1/2019 | JOHN KIM |
| BHO/Hillside ordinance | Cleared | 9/24/2019 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 9/24/2019 | JEANIE LAM |
| BHO/Hillside ordinance | Cleared | 9/24/2019 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 9/24/2019 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 9/24/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 9/24/2019 | ANDRES COVARRUBIAS |
| Permit | Cleared | 9/24/2019 | JEANIE LAM |
| Roof/Waste drainage to street | Cleared | 9/24/2019 | JEANIE LAM |
| Sewer availability | Cleared | 9/24/2019 | JEANIE LAM |
| Coastal Zone | Cleared | 11/13/2019 | SARAH GOLDMAN |
| Green Code | Cleared | 11/13/2019 | DONALD CRICHLOW |
| Miscellaneous | Cleared | 11/13/2019 | SARAH GOLDMAN |
| ZA Case | Cleared | 11/13/2019 | SARAH GOLDMAN |
| ZI | Cleared | 11/13/2019 | SARAH GOLDMAN |
| Excavation more than 5-ft deep | Cleared | 11/21/2019 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hollingsworth,, Robert Alan; Lic. No.: GE2022 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
| Engineer | Shah,, Kamal Rajendra; Lic. No.: C46200 | 28039 SMYTH DR STE 200 VALENCIA, CA 91355 |
| Geologist | Byrne,, Gregory S.; Lic. No.: EG1933 | 5449 RUTHWOOD DRIVE CALABASAS, CA 91302 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/17/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/3/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 8/27/2020 | Partial Approval | ANDREW NAVE |
| Structural Steel Frame | 8/27/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 9/2/2020 | Conditional Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 9/15/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 10/9/2020 | Partial Approval | ANDREW NAVE |
| Reinforced Concrete Frame | 10/9/2020 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 11/10/2020 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 11/13/2020 | Conditional Approval | ANDREW NAVE |
| Grading Pre-Inspection | 12/14/2020 | Approved | ANDREW NAVE |
| Footing/Foundation/Slab | 2/11/2021 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 2/23/2021 | Conditional Approval | ANDREW NAVE |
| Deputy Steel/Welding | 2/24/2021 | Approved | ROBERT SHELLY |
| Footing/Foundation/Slab | 2/26/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 2/26/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/2/2021 | Partial Approval | ANDREW NAVE |
| Footing/Foundation/Slab | 3/10/2021 | Approved | ANDREW NAVE |
| Deputy Steel/Welding | 3/23/2021 | Approved | ROBERT SHELLY |
| Deputy Steel/Welding | 3/24/2021 | Approved | ROBERT SHELLY |
| Deputy Steel/Welding | 3/31/2021 | Approved | ROBERT SHELLY |
| Sewer | 4/1/2021 | Approved | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2021 | Partial Approval | ANDREW NAVE |
| Deputy Steel/Welding | 4/13/2021 | Approved | ROBERT SHELLY |
| Deputy Steel/Welding | 4/20/2021 | Approved | ROBERT SHELLY |
| Deputy Wood Construction | 5/27/2021 | Conditional Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2021 | Partial Approval | ANDREW NAVE |
| Deputy Reinf. Concrete | 7/15/2021 | Approved | ANDREW NAVE |
| ELECTRICAL-Rough | 9/30/2021 | Partial Approval | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2021 | Partial Approval | ANDREW NAVE |
| HVAC-Rough | 9/30/2021 | Not Ready for Inspection | ANDREW NAVE |
| PLUMBING-Rough | 9/30/2021 | Not Ready for Inspection | ANDREW NAVE |
| HVAC-Rough | 11/19/2021 | Conditional Approval | ANDREW NAVE |
| PLUMBING-Rough | 11/19/2021 | Approved | ANDREW NAVE |
| BUILDING-Rough-Frame | 1/6/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 1/6/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 1/6/2022 | Approved | JUAN VALENZUELA |
| HVAC-Rough | 1/6/2022 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 1/6/2022 | Partial Approval | JUAN VALENZUELA |
| Light Gage Steel Frame | 1/6/2022 | Approved | JUAN VALENZUELA |
| Shower Pan | 1/6/2022 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 1/6/2022 | Approved | JUAN VALENZUELA |
| Insulation | 1/20/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 2/3/2022 | Approved | RYAN SALAZAR |
| Interior/Exterior Lathing | 2/3/2022 | Partial Approval | RYAN SALAZAR |
| Underground Mechanical | 4/29/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 7/13/2022 | Partial Approval | ANDREW NAVE |
| HVAC-Final | 8/5/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 8/8/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 8/8/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Final | 8/9/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Final | 8/9/2022 | Approved | BRENDAN LOONEY |
| HVAC-Final | 8/12/2022 | Approved | BRENDAN LOONEY |
| Service/Power Release | 9/13/2022 | Approved | BRENDAN LOONEY |
| Final | 9/28/2022 | Corrections Issued | BRENDAN LOONEY |
| Green Building Final | 9/28/2022 | Approved | BRENDAN LOONEY |
| Reinforced Concrete Frame | 9/28/2022 | Approved | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 9/28/2022 | SGSOV Not Ready | BRENDAN LOONEY |
| Smoke Detectors | 9/28/2022 | Corrections Issued | BRENDAN LOONEY |
| Final | 11/4/2022 | OK to Issue CofO | BRENDAN LOONEY |
| SGSOV-Seismic Gas S/O Valve | 11/4/2022 | SGSOV Approved | BRENDAN LOONEY |
| Service/Power Release | 11/4/2022 | Approved | BRENDAN LOONEY |
| Smoke Detectors | 11/4/2022 | Approved | BRENDAN LOONEY |