286 N QUADRO VECCHIO DR 90272

Certificate Information: 286 N QUADRO VECCHIO DR 90272

Application / Permit
19010-30000-02523
Plan Check / Job No.
B19WL03317
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
New one-story single familey dwelling with basement & attached garage.
Permit Issued
Issued on 12/10/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/13/2019 APPLICANT
Assigned to Plan Check Engineer 7/11/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 7/16/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 7/17/2019 FELIX FIGUEROA
Building Plans Picked Up 7/18/2019 APPLICANT
Green Plans Picked Up 7/18/2019 APPLICANT
Applicant returned to address corrections 8/20/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/12/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/26/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 10/15/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 11/21/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 12/10/2019 KAMRAN GHOTBI RAVANDI
Issued 12/10/2019 LADBS
CofO in Progress 11/7/2022 BRENDAN LOONEY
Permit Finaled 2/2/2023 DANIEL ORRANTE
CofO Issued 2/2/2023 DANIEL ORRANTE
Permit Finaled 2/2/2023 DANIEL ORRANTE

Permit Application Clearance Information

Trees in Parkway Cleared 8/1/2019 JOHN KIM
BHO/Hillside ordinance Cleared 9/24/2019 JEANIE LAM
BHO/Hillside ordinance Cleared 9/24/2019 JEANIE LAM
BHO/Hillside ordinance Cleared 9/24/2019 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 9/24/2019 JEANIE LAM
Hydrant and Access approval Cleared 9/24/2019 JEREMY CARTER
Low Impact Development Cleared 9/24/2019 ANDRES COVARRUBIAS
Permit Cleared 9/24/2019 JEANIE LAM
Roof/Waste drainage to street Cleared 9/24/2019 JEANIE LAM
Sewer availability Cleared 9/24/2019 JEANIE LAM
Coastal Zone Cleared 11/13/2019 SARAH GOLDMAN
Green Code Cleared 11/13/2019 DONALD CRICHLOW
Miscellaneous Cleared 11/13/2019 SARAH GOLDMAN
ZA Case Cleared 11/13/2019 SARAH GOLDMAN
ZI Cleared 11/13/2019 SARAH GOLDMAN
Excavation more than 5-ft deep Cleared 11/21/2019 CALOSHA APPROVED

Contact Information

Contractor Owner-Builder       ,
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Shah,, Kamal Rajendra; Lic. No.: C46200 28039 SMYTH DR STE 200      VALENCIA, CA 91355
Geologist Byrne,, Gregory S.; Lic. No.: EG1933 5449 RUTHWOOD DRIVE      CALABASAS, CA 91302

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 7/17/2020 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 8/3/2020 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 8/27/2020 Partial Approval ANDREW NAVE
Structural Steel Frame 8/27/2020 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 9/2/2020 Conditional Approval ANDREW NAVE
Footing/Foundation/Slab 9/15/2020 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 10/9/2020 Partial Approval ANDREW NAVE
Reinforced Concrete Frame 10/9/2020 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 11/10/2020 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 11/13/2020 Conditional Approval ANDREW NAVE
Grading Pre-Inspection 12/14/2020 Approved ANDREW NAVE
Footing/Foundation/Slab 2/11/2021 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 2/23/2021 Conditional Approval ANDREW NAVE
Deputy Steel/Welding 2/24/2021 Approved ROBERT SHELLY
Footing/Foundation/Slab 2/26/2021 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 2/26/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 3/2/2021 Partial Approval ANDREW NAVE
Footing/Foundation/Slab 3/10/2021 Approved ANDREW NAVE
Deputy Steel/Welding 3/23/2021 Approved ROBERT SHELLY
Deputy Steel/Welding 3/24/2021 Approved ROBERT SHELLY
Deputy Steel/Welding 3/31/2021 Approved ROBERT SHELLY
Sewer 4/1/2021 Approved ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 4/8/2021 Partial Approval ANDREW NAVE
Deputy Steel/Welding 4/13/2021 Approved ROBERT SHELLY
Deputy Steel/Welding 4/20/2021 Approved ROBERT SHELLY
Deputy Wood Construction 5/27/2021 Conditional Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 6/14/2021 Partial Approval ANDREW NAVE
Deputy Reinf. Concrete 7/15/2021 Approved ANDREW NAVE
ELECTRICAL-Rough 9/30/2021 Partial Approval ANDREW NAVE
Floor/Roof Diaphrgm/Shear Wall 9/30/2021 Partial Approval ANDREW NAVE
HVAC-Rough 9/30/2021 Not Ready for Inspection ANDREW NAVE
PLUMBING-Rough 9/30/2021 Not Ready for Inspection ANDREW NAVE
HVAC-Rough 11/19/2021 Conditional Approval ANDREW NAVE
PLUMBING-Rough 11/19/2021 Approved ANDREW NAVE
BUILDING-Rough-Frame 1/6/2022 Approved JUAN VALENZUELA
ELECTRICAL-Rough 1/6/2022 Approved JUAN VALENZUELA
Green Building Rough 1/6/2022 Approved JUAN VALENZUELA
HVAC-Rough 1/6/2022 Approved JUAN VALENZUELA
Interior/Exterior Lathing 1/6/2022 Partial Approval JUAN VALENZUELA
Light Gage Steel Frame 1/6/2022 Approved JUAN VALENZUELA
Shower Pan 1/6/2022 Approved JUAN VALENZUELA
Verify Sprinkler Sign Off 1/6/2022 Approved JUAN VALENZUELA
Insulation 1/20/2022 Approved ANDREW NAVE
Drywall Nailing 2/3/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 2/3/2022 Partial Approval RYAN SALAZAR
Underground Mechanical 4/29/2022 Approved ANDREW NAVE
Underground Mechanical 7/13/2022 Partial Approval ANDREW NAVE
HVAC-Final 8/5/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 8/8/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Final 8/8/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Final 8/9/2022 Approved BRENDAN LOONEY
PLUMBING-Final 8/9/2022 Approved BRENDAN LOONEY
HVAC-Final 8/12/2022 Approved BRENDAN LOONEY
Service/Power Release 9/13/2022 Approved BRENDAN LOONEY
Final 9/28/2022 Corrections Issued BRENDAN LOONEY
Green Building Final 9/28/2022 Approved BRENDAN LOONEY
Reinforced Concrete Frame 9/28/2022 Approved BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 9/28/2022 SGSOV Not Ready BRENDAN LOONEY
Smoke Detectors 9/28/2022 Corrections Issued BRENDAN LOONEY
Final 11/4/2022 OK to Issue CofO BRENDAN LOONEY
SGSOV-Seismic Gas S/O Valve 11/4/2022 SGSOV Approved BRENDAN LOONEY
Service/Power Release 11/4/2022 Approved BRENDAN LOONEY
Smoke Detectors 11/4/2022 Approved BRENDAN LOONEY