2434 S GLENCOE AVE 90291

Certificate Information: 2434 S GLENCOE AVE 90291

Application / Permit
19010-30000-02488
Plan Check / Job No.
B19WL03260
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 2-STORY TYPE VB ACCESSORY DWELLING UNIT PER AB 494 AND SB 229.
Permit Issued
Issued on 9/25/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/11/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 SERGIO SILVA
Corrections Issued 7/8/2019 SERGIO SILVA
Green Plans Picked Up 7/8/2019 APPLICANT
Quality Review Completed 7/19/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/10/2019 SERGIO SILVA
Plan Check Approved 9/25/2019 SERGIO SILVA
Issued 9/25/2019 LADBS
Building Plans Picked Up 4/24/2020 APPLICANT
CofO in Progress 6/24/2022 JESUS RODRIGUEZ
Permit Finaled 6/30/2022 DANIEL ORRANTE
CofO Issued 6/30/2022 DANIEL ORRANTE
Permit Finaled 6/30/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 8/29/2019 OSCAR GUTIERREZ
Eng Process Fee Ord 176,300 Cleared 8/29/2019 OSCAR GUTIERREZ
Permit Cleared 8/29/2019 OSCAR GUTIERREZ
Sewer availability Cleared 8/29/2019 OSCAR GUTIERREZ
CPC Cleared 9/10/2019 TREVOR MARTIN
CPC Cleared 9/10/2019 TREVOR MARTIN
Hydrant and Access approval Cleared 9/12/2019 JOHN CONNEALLY
Low Impact Development Cleared 9/12/2019 ORVAL HERNANDEZ-MARCI
Green Code Cleared 9/18/2019 DONALD CRICHLOW
Roof/Waste drainage to street Cleared 9/24/2019 DINAH GARIN

Contact Information

Contractor Owner-Builder       ,
Engineer Paniagua,, Cristobal; Lic. No.: C72894 1538 W 92ND ST      LOS ANGELES, CA 90047

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 1/13/2020 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 1/17/2020 Partial Inspection JOHNNY MIRANDA
PLUMBING-Rough 1/27/2020 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 2/4/2020 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 2/7/2020 Approved JOHNNY MIRANDA
Wood Frame 3/31/2020 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 5/6/2020 Partial Inspection DAVID FEILER
ELECTRICAL-Rough 5/6/2020 Corrections Issued DAVID FEILER
Green Building Rough 5/6/2020 Not Ready for Inspection DAVID FEILER
PLUMBING-Rough 5/6/2020 Corrections Issued DAVID FEILER
Verify Sprinkler Sign Off 5/6/2020 Not Ready for Inspection DAVID FEILER
Wood Frame 5/6/2020 Corrections Issued DAVID FEILER
BUILDING-Rough-Frame 5/22/2020 Partial Approval DAVID HEINE
ELECTRICAL-Rough 5/22/2020 Approved DAVID HEINE
Green Building Rough 5/22/2020 Approved DAVID HEINE
HVAC-Rough 5/22/2020 Approved DAVID HEINE
PLUMBING-Rough 5/22/2020 Approved DAVID HEINE
Verify Sprinkler Sign Off 5/22/2020 Approved DAVID HEINE
Wood Frame 5/22/2020 Partial Approval DAVID HEINE
Insulation 6/5/2020 Corrections Issued JUAN VALENZUELA
Interior/Exterior Lathing 6/30/2020 Partial Approval JUAN VALENZUELA
Insulation 7/30/2020 Approved EVAN COOPER
Drywall Nailing 8/11/2020 Approved DAVID HEINE
Shower Pan 8/26/2020 Approved DAVID HEINE
Interior/Exterior Lathing 9/4/2020 Approved DAVID HEINE
Gas Test 9/21/2020 Approved JOHNNY MIRANDA
ELECTRICAL-Final 2/10/2021 Corrections Issued ENRIQUE MIRELES
Service/Power Release 2/25/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 7/21/2021 Corrections Issued ENRIQUE MIRELES
ELECTRICAL-Final 8/18/2021 Approved ENRIQUE MIRELES
PLUMBING-Final 8/20/2021 Approved ENRIQUE MIRELES
BUILDING-Rough-Frame 5/23/2022 Approved PATRICK QUALEY
Final 5/23/2022 Corrections Issued PATRICK QUALEY
Green Building Final 5/23/2022 Approved PATRICK QUALEY
SGSOV-Seismic Gas S/O Valve 5/23/2022 SGSOV Approved PATRICK QUALEY
Smoke Detectors 5/23/2022 Approved PATRICK QUALEY
HVAC-Final 6/2/2022 Corrections Issued PATRICK QUALEY
Final 6/23/2022 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 6/23/2022 Approved JESUS RODRIGUEZ