4925 S BERRYMAN AVE 90230
Certificate Information: 4925 S BERRYMAN AVE 90230
- Application / Permit
- 19010-30000-02434
- Plan Check / Job No.
- B19WL03199
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2 STORY SFD WITH ATTACHED GARAGE
- Permit Issued
- Issued on 12/18/2019
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/29/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/7/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 7/18/2019 | SERGIO GUTIERREZ |
| Corrections Issued | 8/26/2019 | SERGIO GUTIERREZ |
| Quality Review Completed | 9/3/2019 | KESETE HAREGOT |
| Green Plans Picked Up | 9/5/2019 | APPLICANT |
| Building Plans Picked Up | 9/10/2019 | APPLICANT |
| Plan Check Approved | 12/13/2019 | SERGIO GUTIERREZ |
| Issued | 12/18/2019 | LADBS |
| CofO in Progress | 4/7/2021 | ENRIQUE MIRELES |
| CofO Issued | 4/29/2021 | VINCENT COTTON |
| Permit Finaled | 4/29/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Permit | Cleared | 10/23/2019 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 10/29/2019 | THOMAS LANG |
| Hydrant and Access approval | Cleared | 10/29/2019 | JOHN CONNEALLY |
| Roof/Waste drainage to street | Cleared | 10/29/2019 | THOMAS LANG |
| Sewer availability | Cleared | 10/29/2019 | THOMAS LANG |
| Stormwater Pollution Mitigatn | Cleared | 10/29/2019 | ORVAL HERNANDEZ-MARCI |
| Low Impact Development | Cleared | 12/10/2019 | JORGE MEJIA LEMUS |
| Green Code | Cleared | 12/11/2019 | RICHARD GARCIA |
Contact Information
| Contractor | Escobar Construction; Lic. No.: 917824-B | 5651 W PICO BLVD #203 LOS ANGELES, CA 90019 |
| Engineer | Heydar,, Ahmad; Lic. No.: S3679 | 28025 DOROTHY DR STE 104 AGOURA HILLS, CA 91301 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/5/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 2/5/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 2/5/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Special/Order Compliance | 2/6/2020 | Corrections Issued | KENNETH NAGLE |
| Underground Mechanical | 2/6/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 2/10/2020 | Corrections Issued | JOHNNY MIRANDA |
| Underground Mechanical | 2/10/2020 | Partial Approval | CRAIG DAVIS |
| Underground Mechanical | 2/12/2020 | Partial Approval | CRAIG DAVIS |
| Footing/Foundation/Slab | 2/18/2020 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 2/26/2020 | Partial Approval | DAVID HEINE |
| Floor/Roof Diaphrgm/Shear Wall | 2/26/2020 | Partial Approval | KENNETH NAGLE |
| Deputy Wood Construction | 3/16/2020 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2020 | Not Ready for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 3/18/2020 | Conditional Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/19/2020 | Partial Approval | CRAIG DAVIS |
| ELECTRICAL-Rough | 3/20/2020 | Not Ready for Inspection | DAVID FEILER |
| PLUMBING-Rough | 3/20/2020 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 3/23/2020 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2020 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 3/24/2020 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Rough | 3/26/2020 | Approved | JUAN VALENZUELA |
| PLUMBING-Rough | 3/26/2020 | Approved | JUAN VALENZUELA |
| Interior/Exterior Lathing | 3/31/2020 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 4/2/2020 | Partial Approval | CRAIG DAVIS |
| HVAC-Rough | 4/6/2020 | Approved | DAVID HEINE |
| Interior/Exterior Lathing | 4/8/2020 | Partial Approval | DAVID FEILER |
| BUILDING-Rough-Frame | 4/29/2020 | Partial Inspection | DAVID FEILER |
| Green Building Rough | 4/29/2020 | Corrections Issued | DAVID FEILER |
| MERV13>=Rough | 4/29/2020 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 4/29/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 5/1/2020 | Approved | DAVID FEILER |
| Green Building Rough | 5/1/2020 | Approved | DAVID FEILER |
| Insulation | 5/5/2020 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 5/11/2020 | Approved | JOHNNY MIRANDA |
| Shower Pan | 5/29/2020 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 6/2/2020 | Approved | DAVID FEILER |
| ELECTRICAL-Rough | 7/14/2020 | Approved | DAVID HEINE |
| Sewer | 7/15/2020 | Corrections Issued | JOHNNY MIRANDA |
| Sewer | 7/16/2020 | Not Ready for Inspection | JOHNNY MIRANDA |
| Underground Mechanical | 7/16/2020 | Approved | JOHNNY MIRANDA |
| Sewer | 7/18/2020 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Final | 7/30/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Final | 7/30/2020 | Not Ready for Inspection | CRAIG DAVIS |
| Footing/Foundation/Slab | 7/30/2020 | Approved | CRAIG DAVIS |
| Green Building Final | 7/30/2020 | Not Ready for Inspection | CRAIG DAVIS |
| HVAC-Final | 7/30/2020 | Not Ready for Inspection | CRAIG DAVIS |
| MERV13>=Final | 7/30/2020 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Final | 7/30/2020 | Not Ready for Inspection | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 7/30/2020 | SGSOV Not Ready | CRAIG DAVIS |
| Service/Power Release | 7/30/2020 | Partial Inspection | CRAIG DAVIS |
| Smoke Detectors | 7/30/2020 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 8/3/2020 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Final | 8/3/2020 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 8/3/2020 | Corrections Issued | JUAN VALENZUELA |
| Service/Power Release | 8/7/2020 | Approved | JUAN VALENZUELA |
| Final | 10/13/2020 | Corrections Issued | ENRIQUE MIRELES |
| Green Building Final | 10/13/2020 | Approved | ENRIQUE MIRELES |
| MERV13>=Final | 10/13/2020 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 10/13/2020 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 10/13/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 10/15/2020 | Approved | ENRIQUE MIRELES |
| Final | 10/15/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Final | 10/15/2020 | Approved | ENRIQUE MIRELES |
| PLUMBING-Final | 10/15/2020 | Approved | ENRIQUE MIRELES |
| Service/Power Release | 10/15/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 11/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| Final | 11/6/2020 | Corrections Issued | ENRIQUE MIRELES |
| Final | 3/30/2021 | Corrections Issued | ENRIQUE MIRELES |
| Final | 4/7/2021 | OK to Issue CofO | ENRIQUE MIRELES |