2924 S BEVERWIL DR 90034

Certificate Information: 2924 S BEVERWIL DR 90034

Application / Permit
19010-30000-02396
Plan Check / Job No.
B19WL03162
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
(n) detached 2-car garage w/ attached accessory dwelling unit per AB494 and SB229
Permit Issued
Issued on 1/8/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 7/7/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/6/2019 APPLICANT
Green Plans Picked Up 6/25/2019 APPLICANT
Assigned to Plan Check Engineer 7/3/2019 KAMRAN GHOTBI RAVANDI
Corrections Issued 7/8/2019 KAMRAN GHOTBI RAVANDI
Quality Review Completed 7/10/2019 FELIX FIGUEROA
Building Plans Picked Up 7/15/2019 APPLICANT
Applicant returned to address corrections 10/15/2019 JAHANSHAH POURHASSAN
Applicant returned to address corrections 11/14/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/4/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 12/24/2019 KAMRAN GHOTBI RAVANDI
Plan Check Approved 1/7/2020 KAMRAN GHOTBI RAVANDI
Issued 1/8/2020 LADBS
CofO in Progress 7/6/2022 KEVIN SARGSYAN
Permit Finaled 7/7/2022 DANIEL ORRANTE
CofO Issued 7/7/2022 DANIEL ORRANTE
Permit Finaled 7/7/2022 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/30/2019 ELAINE LEI
Eng Process Fee Ord 176,300 Cleared 10/30/2019 ELAINE LEI
Hydrant and Access approval Cleared 10/30/2019 JEREMY CARTER
Low Impact Development Cleared 10/30/2019 MITESH PATEL
Roof/Waste drainage to street Cleared 10/30/2019 ELAINE LEI
Sewer availability Cleared 10/30/2019 ELAINE LEI
Trees in Parkway Cleared 10/31/2019 JOHN KIM
Green Code Cleared 11/13/2019 DONALD CRICHLOW
Permit Cleared 1/7/2020 OSCAR GUTIERREZ

Contact Information

Contractor R & O Chinchilla Inc; Lic. No.: 987184-B 42415 52ND STREET WEST      LANCASTER, CA 935364322
Engineer Sivushenka,, Mikita; Lic. No.: C87698 5525 CANOGA AVE APT 208      WOODLAND HILLS, CA 91367

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/17/2020 Corrections Issued KEVIN SARGSYAN
METHANE-Barrier 11/17/2020 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Subgrade 11/17/2020 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 11/19/2020 Approved KEVIN SARGSYAN
METHANE-Barrier 11/19/2020 Approved KEVIN SARGSYAN
METHANE-Subgrade 11/19/2020 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/3/2020 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2020 Partial Approval KEVIN SARGSYAN
ELECTRICAL-Rough 4/14/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/14/2021 Approved KEVIN SARGSYAN
Green Building Rough 4/14/2021 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 4/14/2021 Corrections Issued KEVIN SARGSYAN
METHANE-Rough 4/14/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 4/14/2021 Corrections Issued KEVIN SARGSYAN
Verify Sprinkler Sign Off 4/14/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/12/2021 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 5/12/2021 Approved KEVIN SARGSYAN
Green Building Rough 5/12/2021 Not Ready for Inspection KEVIN SARGSYAN
HVAC-Rough 5/12/2021 Not Ready for Inspection KEVIN SARGSYAN
PLUMBING-Rough 5/12/2021 Not Ready for Inspection KEVIN SARGSYAN
Shower Pan 5/12/2021 Approved KEVIN SARGSYAN
PLUMBING-Rough 5/26/2021 Approved KEVIN SARGSYAN
BUILDING-Rough-Frame 5/28/2021 Approved EVAN COOPER
Green Building Rough 5/28/2021 Approved EVAN COOPER
HVAC-Rough 5/28/2021 Approved EVAN COOPER
Interior/Exterior Lathing 6/2/2021 Partial Approval KEVIN SARGSYAN
Insulation 6/9/2021 Approved KEVIN SARGSYAN
Drywall Nailing 7/2/2021 Approved AMY COLIN
Interior/Exterior Lathing 7/8/2021 Approved JACK MATTILLO
ELECTRICAL-Final 3/15/2022 Corrections Issued KEVIN SARGSYAN
Service/Power Release 3/15/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Final 3/21/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 3/23/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Final 3/23/2022 Corrections Issued JOHNNY MIRANDA
HVAC-Final 4/13/2022 Approved KEVIN SARGSYAN
PLUMBING-Final 4/13/2022 Approved KEVIN SARGSYAN
Final 5/13/2022 Corrections Issued KEVIN SARGSYAN
Green Building Final 5/13/2022 Corrections Issued KEVIN SARGSYAN
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Approved KEVIN SARGSYAN
Service/Power Release 5/13/2022 Approved KEVIN SARGSYAN
Smoke Detectors 5/13/2022 Approved KEVIN SARGSYAN
Final 7/5/2022 OK to Issue CofO KEVIN SARGSYAN
Green Building Final 7/5/2022 Approved KEVIN SARGSYAN