4642 W ST ELMO DR 90019
Certificate Information: 4642 W ST ELMO DR 90019
- Application / Permit
- 19010-30000-02304
- Plan Check / Job No.
- B19WL03055
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 3 STORY SFD WITH ATTACHED CAR GARAGE (FRONT)
- Permit Issued
- Issued on 3/16/2020
- Issuing Office
- Metro
- Current Status
- CofO Issued on 6/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/31/2019 | APPLICANT |
| Green Plans Picked Up | 6/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/21/2019 | TARIK SAOUD |
| Corrections Issued | 6/24/2019 | TARIK SAOUD |
| Quality Review Completed | 7/1/2019 | FELIX FIGUEROA |
| Building Plans Picked Up | 7/2/2019 | APPLICANT |
| Plan Check Approved | 9/5/2019 | TARIK SAOUD |
| Issued | 3/16/2020 | LADBS |
| CofO in Progress | 6/5/2023 | STUART CHAPMAN |
| Permit Finaled | 6/21/2023 | RONALD MYRICK |
| CofO Issued | 6/21/2023 | RONALD MYRICK |
| Permit Finaled | 6/21/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 7/5/2019 | ERIK BEASLEY |
| Permit | Cleared | 7/5/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 7/9/2019 | DENNIS BRAGIN |
| Sewer availability | Cleared | 7/9/2019 | DENNIS BRAGIN |
| Hydrant and Access approval | Cleared | 7/12/2019 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 7/12/2019 | HECTOR BANUELOS |
| Green Code | Cleared | 8/14/2019 | DONALD CRICHLOW |
| Green Code | Cleared | 8/14/2019 | DONALD CRICHLOW |
| Low Impact Development | Cleared | 9/13/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/13/2019 | JAMES MORALEZ |
Contact Information
| Contractor | Investors Design And Builders Inc; Lic. No.: 1003930-B | 4019 WEIK AVENUE BELL, CA 90201 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 7366 W MANCHESTER AVE #B LOS ANGELES, CA 90045 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/30/2020 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/5/2020 | Partial Approval | STUART CHAPMAN |
| METHANE-Barrier | 5/5/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Subgrade | 5/5/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/8/2020 | Partial Approval | STUART CHAPMAN |
| METHANE-Rough | 5/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 5/13/2020 | Partial Approval | STUART CHAPMAN |
| METHANE-Barrier | 5/13/2020 | Approved | STUART CHAPMAN |
| METHANE-Subgrade | 5/13/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 5/19/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 5/22/2020 | Partial Approval | STUART CHAPMAN |
| Wood Frame | 5/22/2020 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/29/2020 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 5/29/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 5/29/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 5/29/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Special/Order Compliance | 6/4/2020 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/8/2020 | Partial Approval | STUART CHAPMAN |
| Green Building Rough | 6/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 6/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/8/2020 | Not Ready for Inspection | STUART CHAPMAN |
| Special/Order Compliance | 6/19/2020 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 6/24/2020 | Approved | ELMER BLAND |
| ELECTRICAL-Rough | 7/24/2020 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2020 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 7/24/2020 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 7/24/2020 | Approved | STUART CHAPMAN |
| Wood Frame | 7/24/2020 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 8/24/2020 | Partial Approval | SABAS ALONSO |
| Insulation | 9/4/2020 | Approved | STUART CHAPMAN |
| Drywall Nailing | 9/18/2020 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 4/30/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/30/2021 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/30/2021 | Approved | STUART CHAPMAN |
| Green Building Final | 4/30/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 4/30/2021 | Approved | STUART CHAPMAN |
| METHANE-Final | 4/30/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 4/30/2021 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/30/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 4/30/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 4/30/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 4/30/2021 | Approved | STUART CHAPMAN |
| Special/Order Compliance | 6/3/2021 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/22/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 6/22/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 6/22/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Final | 6/22/2021 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 6/22/2021 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/22/2021 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 6/22/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 6/22/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Special/Order Compliance | 9/24/2021 | Approved | ALAN MORELOS |
| ELECTRICAL-Final | 11/8/2021 | Not Ready for Inspection | STUART CHAPMAN |
| Sewer | 5/20/2022 | Approved | JOSE AVILA |
| Gas Test | 6/6/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 6/6/2022 | Partial Approval | STUART CHAPMAN |
| HVAC-Final | 6/30/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Final | 7/15/2022 | Approved | STUART CHAPMAN |
| HVAC-Final | 9/20/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 11/3/2022 | Corrections Issued | STUART CHAPMAN |
| BUILDING-Rough-Frame | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| Final | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Final | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Rough | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 12/27/2022 | SGSOV Not Ready | CALEB MEISTER |
| Service/Power Release | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 12/27/2022 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 1/20/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 2/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 2/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Final | 2/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Final | 2/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| METHANE-Rough | 2/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Not Ready | CALEB MEISTER |
| Service/Power Release | 2/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| Smoke Detectors | 2/3/2023 | Not Ready for Inspection | CALEB MEISTER |
| BUILDING-Rough-Frame | 4/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 4/17/2023 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 4/17/2023 | Approved | STUART CHAPMAN |
| METHANE-Final | 4/17/2023 | Approved | STUART CHAPMAN |
| METHANE-Rough | 4/17/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 4/17/2023 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 4/17/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 4/17/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/2/2023 | Approved | STUART CHAPMAN |
| Final | 6/2/2023 | OK to Issue CofO | STUART CHAPMAN |
| Service/Power Release | 6/2/2023 | Approved | STUART CHAPMAN |