2423 N BRIARCREST ROAD 90210
Certificate Information: 2423 N BRIARCREST ROAD 90210
- Application / Permit
- 19010-30000-02100
- Plan Check / Job No.
- B19WL02802
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New 2-story SFD with basement and attached garge.
- Permit Issued
- Issued on 12/23/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/20/2019 | APPLICANT |
| Green Plans Picked Up | 6/4/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/13/2019 | MANUEL GARCIA |
| Corrections Issued | 6/21/2019 | MANUEL GARCIA |
| Quality Review Completed | 6/25/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/1/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/10/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 9/24/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 10/3/2019 | MANUEL GARCIA |
| Applicant returned to address corrections | 12/10/2019 | MANUEL GARCIA |
| Plan Check Approved | 12/19/2019 | MANUEL GARCIA |
| Issued | 12/23/2019 | LADBS |
| Building Plans Picked Up | 5/6/2020 | APPLICANT |
| CofO in Progress | 4/13/2024 | RAUL BARAJAS |
| Permit Finaled | 4/16/2024 | RONALD MYRICK |
| CofO Issued | 4/16/2024 | RONALD MYRICK |
| Permit Finaled | 4/16/2024 | RONALD MYRICK |
Permit Application Clearance Information
| Private street | Cleared | 8/5/2019 | NOAH MCCOY |
| ZA Case | Cleared | 8/5/2019 | NOAH MCCOY |
| ZI | Cleared | 8/5/2019 | NOAH MCCOY |
| Address approval | Cleared | 8/22/2019 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 8/22/2019 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 8/22/2019 | HISASHI KOBAYAKAWA |
| BHO/Hillside ordinance | Cleared | 8/22/2019 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2019 | HISASHI KOBAYAKAWA |
| Hydrant and Access approval | Cleared | 9/12/2019 | JEREMY CARTER |
| Low Impact Development | Cleared | 9/12/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/12/2019 | EMIL KYUPELYAN |
| Sewer availability | Cleared | 9/12/2019 | EMIL KYUPELYAN |
| Green Code | Cleared | 9/18/2019 | RICHARD GARCIA |
| Grading Pre-Inspection | Cleared | 9/24/2019 | MANUEL GARCIA |
| Landscape for retaining wall | Cleared | 11/19/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 11/19/2019 | SARAH GOLDMAN |
| Miscellaneous | Cleared | 11/19/2019 | SARAH GOLDMAN |
| Specific Plan | Cleared | 11/19/2019 | SARAH GOLDMAN |
| ZI | Cleared | 11/19/2019 | SARAH GOLDMAN |
| Excavation more than 5-ft deep | Cleared | 12/10/2019 | CALOSHA APPROVED |
Contact Information
| Contractor | Saad Maher; Lic. No.: 627177-B | 7641 TEXHOMA AVENUE NORTHRIDGE, CA 91325 |
Inspector Information
| BRENDAN MORELLI, (213) 202-3412 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/22/2020 | Partial Approval | RICHARD STEINBACH |
| Deputy Reinf. Concrete | 8/17/2020 | No Access for Inspection | RAUL BARAJAS |
| Piling/Pier/Caisson | 8/18/2020 | Partial Approval | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 8/19/2020 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 8/20/2020 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 9/23/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 9/24/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 9/28/2020 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 10/1/2020 | No Access for Inspection | ELMER BLAND |
| Underground Mechanical | 10/27/2020 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 11/5/2020 | Partial Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 12/3/2020 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 12/4/2020 | No Access for Inspection | ELMER BLAND |
| Excavation/Setback/Form/Re-Bar | 12/11/2020 | Partial Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 12/21/2020 | Approved | BRAD BESCOS |
| Deputy Steel/Welding | 12/22/2020 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 12/29/2020 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 1/7/2021 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 1/7/2021 | Partial Approval | RAUL BARAJAS |
| Structural Steel Frame | 1/7/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Shotcrete | 1/8/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 1/13/2021 | Partial Approval | RAUL BARAJAS |
| Underground Mechanical | 1/19/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 2/2/2021 | No Access for Inspection | ELMER BLAND |
| Footing/Foundation/Slab | 2/2/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 2/3/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 2/24/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 3/15/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/5/2021 | Corrections Issued | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/6/2021 | Approved | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/6/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 4/7/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 4/15/2021 | Conditional Approval | THOMAS LOGRASSO |
| Deputy Reinf. Concrete | 4/19/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 4/19/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 4/26/2021 | Partial Approval | JOSEPH MCGARRY |
| Deputy Reinf. Concrete | 4/27/2021 | Conditional Approval | THOMAS LOGRASSO |
| Underground Mechanical | 4/27/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 5/4/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Drilled-In Anchors | 5/6/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Reinf. Concrete | 5/6/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 5/6/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 5/17/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 5/19/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Underground Mechanical | 5/19/2021 | Approved | RAUL BARAJAS |
| Underground Mechanical | 5/19/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 5/20/2021 | Conditional Approval | RAUL BARAJAS |
| Footing/Foundation/Slab | 5/20/2021 | Partial Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 5/21/2021 | Conditional Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 5/21/2021 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Steel/Welding | 5/24/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Reinf. Concrete | 5/27/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 5/27/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Steel/Welding | 6/1/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 6/7/2021 | No Access for Inspection | ELMER BLAND |
| Underground Mechanical | 6/7/2021 | Partial Approval | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 6/16/2021 | Approved | RAUL BARAJAS |
| Deputy Reinf. Concrete | 6/21/2021 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| Deputy Steel/Welding | 6/23/2021 | Conditional Approval | RAUL BARAJAS |
| Deputy Steel/Welding | 6/24/2021 | Conditional Approval | RAUL BARAJAS |
| Structural Steel Frame | 6/29/2021 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 7/9/2021 | Partial Approval | RAUL BARAJAS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2021 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 11/4/2021 | Partial Approval | RAUL BARAJAS |
| HVAC-Rough | 12/8/2021 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 12/9/2021 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 12/28/2021 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 4/19/2022 | Partial Inspection | RAUL BARAJAS |
| Green Building Rough | 4/19/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 4/19/2022 | Not Ready for Inspection | RAUL BARAJAS |
| Deputy Wood Construction | 5/26/2022 | Conditional Approval | RAUL BARAJAS |
| Underground Mechanical | 5/31/2022 | Approved | RAUL BARAJAS |
| Wood Frame | 5/31/2022 | Approved | RAUL BARAJAS |
| Wood Frame | 7/1/2022 | Partial Approval | RAUL BARAJAS |
| Insulation | 7/11/2022 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 7/27/2022 | Corrections Issued | RAUL BARAJAS |
| Rough-Elec/Plmb/HVAC | 7/27/2022 | Partial Approval | RAUL BARAJAS |
| Insulation | 8/15/2022 | Partial Approval | RYAN SALAZAR |
| Drywall Nailing | 8/31/2022 | Partial Approval | RAUL BARAJAS |
| Insulation | 9/20/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 10/7/2022 | Partial Approval | RAUL BARAJAS |
| Shower Pan | 10/21/2022 | Approved | RAUL BARAJAS |
| Drywall Nailing | 12/13/2022 | Approved | RICHARD DOCKUS |
| Shower Pan | 12/13/2022 | Approved | RICHARD DOCKUS |
| Shower Pan | 12/20/2022 | Corrections Issued | RAUL BARAJAS |
| Shower Pan | 12/23/2022 | Corrections Issued | RAUL BARAJAS |
| Interior/Exterior Lathing | 2/10/2023 | Approved | RAUL BARAJAS |
| Shower Pan | 2/10/2023 | Partial Approval | RAUL BARAJAS |
| Interior/Exterior Lathing | 3/30/2023 | Approved | RAUL BARAJAS |
| Interior/Exterior Lathing | 5/31/2023 | Approved | RAUL BARAJAS |
| ELECTRICAL-Rough | 7/25/2023 | Approved | RAUL BARAJAS |
| Gas Test | 7/25/2023 | Approved | RAUL BARAJAS |
| Underground Mechanical | 7/25/2023 | Approved | RAUL BARAJAS |
| Excavation/Setback/Form/Re-Bar | 8/17/2023 | Partial Inspection | RAUL BARAJAS |
| ELECTRICAL-Final | 12/29/2023 | Corrections Issued | RAUL BARAJAS |
| PLUMBING-Final | 1/22/2024 | Corrections Issued | RAUL BARAJAS |
| Service/Power Release | 1/24/2024 | Partial Inspection | RAUL BARAJAS |
| HVAC-Final | 2/1/2024 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 2/7/2024 | Partial Approval | RAUL BARAJAS |
| Service/Power Release | 2/8/2024 | Approved | RAUL BARAJAS |
| ELECTRICAL-Final | 2/14/2024 | Approved | RAUL BARAJAS |
| BUILDING-Rough-Frame | 3/4/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Final | 3/4/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Footing/Foundation/Slab | 3/4/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Final | 3/4/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Green Building Rough | 3/4/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 3/4/2024 | SGSOV Not Ready | RICHARD DOCKUS |
| Smoke Detectors | 3/4/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| Verify Sprinkler Sign Off | 3/4/2024 | Not Ready for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 3/7/2024 | Approved | RAUL BARAJAS |
| Final | 3/7/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Footing/Foundation/Slab | 3/7/2024 | Approved | RAUL BARAJAS |
| Green Building Final | 3/7/2024 | Not Ready for Inspection | RAUL BARAJAS |
| Green Building Rough | 3/7/2024 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 3/7/2024 | SGSOV Not Ready | RAUL BARAJAS |
| Smoke Detectors | 3/7/2024 | Approved | RAUL BARAJAS |
| Verify Sprinkler Sign Off | 3/7/2024 | Approved | RAUL BARAJAS |
| Final | 3/11/2024 | Partial Inspection | RAUL BARAJAS |
| Green Building Final | 3/11/2024 | Approved | RAUL BARAJAS |
| PLUMBING-Final | 3/11/2024 | Approved | RAUL BARAJAS |
| SGSOV-Seismic Gas S/O Valve | 3/11/2024 | SGSOV Approved | RAUL BARAJAS |
| Final | 4/10/2024 | Partial Inspection | RAUL BARAJAS |
| Final | 4/12/2024 | OK to Issue CofO | RAUL BARAJAS |