3296 N HUTTON DR 90210
Certificate Information: 3296 N HUTTON DR 90210
- Application / Permit
- 19010-30000-01900
- Plan Check / Job No.
- B19WL02505
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SFD, BASEMENT, AND ATTACHED GARAGE
- Permit Issued
- Issued on 1/8/2020
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 10/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2019 | APPLICANT |
| Green Plans Picked Up | 5/17/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/23/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 5/28/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 5/31/2019 | CORA JOHNSON |
| Building Plans Picked Up | 6/4/2019 | APPLICANT |
| Applicant returned to address corrections | 9/24/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 10/1/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/12/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 11/26/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/16/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/24/2019 | KAMRAN GHOTBI RAVANDI |
| Plan Check Approved | 1/8/2020 | KAMRAN GHOTBI RAVANDI |
| Issued | 1/8/2020 | LADBS |
| CofO in Progress | 10/13/2022 | GERMAN RODRIGUEZ MENDOZA |
| Permit Finaled | 10/20/2022 | DANIEL ORRANTE |
| CofO Issued | 10/20/2022 | DANIEL ORRANTE |
| Permit Finaled | 10/20/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 8/27/2019 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 8/27/2019 | ERIK BEASLEY |
| Hydrant and Access approval | Cleared | 8/27/2019 | GEORGE SUCHAND |
| Permit | Cleared | 8/27/2019 | ERIK BEASLEY |
| Sewer availability | Cleared | 8/27/2019 | ERIK BEASLEY |
| BHO/Hillside ordinance | Cleared | 8/30/2019 | OSCAR GUTIERREZ |
| BHO/Hillside ordinance | Cleared | 8/30/2019 | OSCAR GUTIERREZ |
| Low Impact Development | Cleared | 9/18/2019 | ANDRES COVARRUBIAS |
| Miscellaneous | Cleared | 9/18/2019 | ANNA VAN |
| Miscellaneous | Cleared | 9/18/2019 | ANNA VAN |
| Roof/Waste drainage to street | Cleared | 9/18/2019 | JEANETTE VONG |
| ZI | Cleared | 9/18/2019 | ANNA VAN |
| Green Code | Cleared | 9/26/2019 | DONALD CRICHLOW |
| Miscellaneous | Cleared | 10/18/2019 | ANNA VAN |
| Miscellaneous | Cleared | 10/18/2019 | ANNA VAN |
| Trees in Parkway | Cleared | 10/22/2019 | JOHN KIM |
| Excavation more than 5-ft deep | Cleared | 1/7/2020 | CALOSHA APPROVED |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Salehipour,, Sassan A; Lic. No.: GE2579 | 1290 N LAKE AVENUE #204 PASADENA, CA 91104 |
| Engineer | Yamini,, Soly; Lic. No.: C33719 | 540 WARNER AVE LOS ANGELES, CA 90024 |
Inspector Information
| CARLOS MATAMOROS, (310) 914-3878 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/16/2020 | Partial Inspection | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 2/3/2020 | Partial Inspection | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 2/5/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 2/6/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Footing/Foundation/Slab | 2/18/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Shotcrete | 2/20/2020 | Conditional Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 3/6/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 4/1/2020 | Partial Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 5/22/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 5/28/2020 | Corrections Issued | ANTHONY MCDOWALL |
| PLUMBING-Rough | 5/28/2020 | Partial Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 6/3/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Reinf. Concrete | 6/4/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Excavation/Setback/Form/Re-Bar | 6/18/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Steel/Welding | 7/1/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2020 | Partial Approval | ANTHONY MCDOWALL |
| Green Building Rough | 7/22/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Verify Sprinkler Sign Off | 7/22/2020 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Deputy Steel/Welding | 9/1/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Deputy Steel/Welding | 9/3/2020 | Conditional Approval | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2020 | Partial Approval | ANTHONY MCDOWALL |
| PLUMBING-Rough | 10/15/2020 | Partial Approval | ANTHONY MCDOWALL |
| Deputy Wood Construction | 12/16/2020 | Conditional Approval | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 12/16/2020 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 1/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| ELECTRICAL-Rough | 1/21/2021 | Approved | ANTHONY MCDOWALL |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2021 | Partial Approval | ANTHONY MCDOWALL |
| Green Building Rough | 1/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 1/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Verify Sprinkler Sign Off | 1/21/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| HVAC-Rough | 2/2/2021 | Approved | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 2/4/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Green Building Rough | 2/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| PLUMBING-Rough | 2/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Verify Sprinkler Sign Off | 2/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| BUILDING-Rough-Frame | 2/10/2021 | Approved | ANTHONY MCDOWALL |
| Green Building Rough | 2/10/2021 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 2/10/2021 | Approved | ANTHONY MCDOWALL |
| Verify Sprinkler Sign Off | 2/10/2021 | Approved | ANTHONY MCDOWALL |
| PLUMBING-Rough | 2/18/2021 | Partial Approval | ANTHONY MCDOWALL |
| Sewer | 2/18/2021 | Partial Approval | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 3/23/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 3/24/2021 | Corrections Issued | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 4/1/2021 | Partial Approval | ANTHONY MCDOWALL |
| Insulation | 4/6/2021 | Approved | ANTHONY MCDOWALL |
| Drywall Nailing | 5/4/2021 | Approved | ANTHONY MCDOWALL |
| Shower Pan | 5/4/2021 | Not Ready for Inspection | ANTHONY MCDOWALL |
| Shower Pan | 6/15/2021 | Approved | ANTHONY MCDOWALL |
| Interior/Exterior Lathing | 6/23/2021 | Partial Approval | ANTHONY MCDOWALL |
| HVAC-Rough | 8/12/2021 | Approved | ANTHONY MCDOWALL |
| Pre-Inspection | 4/22/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 4/22/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 5/5/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/6/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 5/12/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Service/Power Release | 5/25/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Final | 6/1/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 6/13/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/7/2022 | Not Ready for Inspection | GERMAN RODRIGUEZ MENDOZA |
| Green Building Final | 7/20/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/20/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 7/28/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 8/22/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Footing/Foundation/Slab | 8/22/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Reinforced Concrete Frame | 8/22/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| SGSOV-Seismic Gas S/O Valve | 8/22/2022 | SGSOV Approved | GERMAN RODRIGUEZ MENDOZA |
| Smoke Detectors | 8/22/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Final | 10/12/2022 | OK to Issue CofO | GERMAN RODRIGUEZ MENDOZA |