1219 W R ST 90744
Certificate Information: 1219 W R ST 90744
- Application / Permit
- 19010-30000-01842
- Plan Check / Job No.
- B19WL02415
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- New 2-car garage
- Permit Issued
- Issued on 5/20/2021
- Issuing Office
- Current Status
- CofO Issued on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/1/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | TARIK SAOUD |
| Corrections Issued | 6/10/2019 | TARIK SAOUD |
| Quality Review Completed | 6/21/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 8/25/2020 | TARIK SAOUD |
| Green Plans Picked Up | 9/1/2020 | APPLICANT |
| Applicant returned to address corrections | 9/21/2020 | TARIK SAOUD |
| Building Plans Picked Up | 9/24/2020 | APPLICANT |
| Plan Check Approved | 4/22/2021 | TARIK SAOUD |
| Issued | 5/20/2021 | APPLICANT |
| CofO in Progress | 6/3/2024 | EUGENE CASSIDY |
| Permit Finaled | 6/4/2024 | DONALD CRICHLOW |
| CofO Issued | 6/4/2024 | DONALD CRICHLOW |
| Permit Finaled | 6/4/2024 | DONALD CRICHLOW |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 7/27/2020 | CHINH DINH |
| Eng Process Fee Ord 176,300 | Cleared | 8/12/2020 | CHINH DINH |
| Green Code | Cleared | 8/25/2020 | RICHARD GARCIA |
| Low Impact Development | Cleared | 2/10/2021 | SARAH YOUSSEF |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Cooke,, Conway Cecil; Lic. No.: S5524 | 34658 LINDA ROSEA RD TEMECULA, CA 92592 |
Inspector Information
| EUGENE CASSIDY, (310) 548-2508 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/28/2021 | Approved | JOHN KLARIN |
| METHANE-Barrier | 5/28/2021 | Approved | JOHN KLARIN |
| METHANE-Subgrade | 5/28/2021 | Approved | JOHN KLARIN |
| Deputy Wood Construction | 6/2/2021 | No Access for Inspection | ELMER BLAND |
| Deputy Wood Construction | 6/22/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 6/28/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/6/2021 | Corrections Issued | JOHN KLARIN |
| ELECTRICAL-Rough | 7/6/2021 | Approved | JOHN KLARIN |
| Green Building Rough | 7/6/2021 | Approved | JOHN KLARIN |
| METHANE-Rough | 7/6/2021 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 7/15/2021 | Not Ready for Inspection | JOHN KLARIN |
| BUILDING-Rough-Frame | 11/4/2021 | Approved | JOHN KLARIN |
| Insulation | 11/4/2021 | Approved | JOHN KLARIN |
| Insulation | 11/10/2021 | Approved | JOHN KLARIN |
| Drywall Nailing | 11/15/2021 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 11/15/2021 | Approved | JOHN KLARIN |
| Final | 5/9/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 5/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 5/9/2022 | SGSOV Not Ready | EUGENE CASSIDY |
| Service/Power Release | 5/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Smoke Detectors | 5/9/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| Final | 12/30/2022 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 12/30/2022 | Not Ready for Inspection | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 12/30/2022 | SGSOV Approved | EUGENE CASSIDY |
| Service/Power Release | 12/30/2022 | Not Required | EUGENE CASSIDY |
| Smoke Detectors | 12/30/2022 | Approved | EUGENE CASSIDY |
| Final | 9/13/2023 | Corrections Issued | EUGENE CASSIDY |
| Green Building Final | 9/13/2023 | Approved | EUGENE CASSIDY |
| ELECTRICAL-Final | 5/31/2024 | Approved | EUGENE CASSIDY |
| Final | 5/31/2024 | OK to Issue CofO | EUGENE CASSIDY |
| HVAC-Final | 5/31/2024 | Approved | EUGENE CASSIDY |
| PLUMBING-Final | 5/31/2024 | Approved | EUGENE CASSIDY |