6454 W 85TH ST 90045
Certificate Information: 6454 W 85TH ST 90045
- Application / Permit
- 19010-30000-01799
- Plan Check / Job No.
- B19WL02348
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 2-STORY TYPE VB IRREGULAR SHAPE ACCESSORY DWELLING UNIT (ADU) PER AB 494 AND SB 229.
- Permit Issued
- Issued on 3/10/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 5/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 6/6/2019 | SERGIO SILVA |
| Corrections Issued | 6/11/2019 | SERGIO SILVA |
| Quality Review Completed | 6/21/2019 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 12/10/2020 | SERGIO SILVA |
| Applicant returned to address corrections | 2/22/2021 | SERGIO SILVA |
| Green Plans Picked Up | 3/2/2021 | APPLICANT |
| Applicant returned to address corrections | 10/3/2022 | SERGIO SILVA |
| Building Plans Picked Up | 10/4/2022 | APPLICANT |
| Applicant returned to address corrections | 2/24/2023 | SERGIO SILVA |
| Plan Check Approved | 3/6/2023 | SERGIO SILVA |
| Issued | 3/10/2023 | APPLICANT |
| CofO in Progress | 5/10/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
| CofO Issued | 5/10/2024 | DANIEL ORRANTE |
| Permit Finaled | 5/10/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 11/8/2021 | ANTHONY MAINEZ |
| Permit | Cleared | 11/8/2021 | ANTHONY MAINEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | STEVEN JIN |
| Sewer availability | Cleared | 1/14/2022 | STEVEN JIN |
| CPC | Cleared | 4/22/2022 | DALIA MOKAYED |
| CPC | Cleared | 4/22/2022 | DALIA MOKAYED |
| CPC | Cleared | 4/22/2022 | DALIA MOKAYED |
| Hydrant and Access approval | Cleared | 4/22/2022 | KURT CORRAL |
| Low Impact Development | Cleared | 6/8/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 9/1/2022 | JEANETTE VONG |
| Trees in Parkway | Cleared | 9/6/2022 | ADALBERTO VERA |
| Green Code | Cleared | 3/6/2023 | RICHARD GARCIA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Bustillos, Portillo, Alejandro; Lic. No.: C87257 | 4749 W 169TH STREET LAWNDALE, CA 90260 |
| Engineer | Mani,, Dev; Lic. No.: C62778 | P O BOX 1451 DUARTE, CA 91009 |
| Engineer | Vreeland,, Regan; Lic. No.: L8503 | PO BOX 482 SANTA MONICA, CA 90406 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/31/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 4/4/2023 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 4/7/2023 | Approved | HERBERT GIRON |
| Special/Order Compliance | 4/7/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 4/19/2023 | Corrections Issued | HERBERT GIRON |
| Sewer | 4/19/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 4/25/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 4/25/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 4/25/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 4/28/2023 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 4/28/2023 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 6/12/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Rough | 7/28/2023 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 7/28/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 8/1/2023 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 8/1/2023 | Approved | HERBERT GIRON |
| Green Building Rough | 8/14/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 8/14/2023 | Partial Approval | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 9/12/2023 | Approved | HERBERT GIRON |
| Final | 9/12/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 9/12/2023 | Corrections Issued | HERBERT GIRON |
| Insulation | 9/12/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 9/19/2023 | Approved | RICHARD STEINBACH |
| Insulation | 9/19/2023 | Approved | RICHARD STEINBACH |
| Shower Pan | 9/19/2023 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 9/21/2023 | Approved | KENNETH NAGLE |
| Interior/Exterior Lathing | 9/21/2023 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 2/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 2/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Special/Order Compliance | 2/7/2024 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 2/21/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Final | 2/21/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 2/21/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 2/21/2024 | Corrections Issued | TEMISTOCLES CAAL |
| HVAC-Final | 2/21/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 2/21/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 2/21/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 2/21/2024 | Not Required | TEMISTOCLES CAAL |
| Smoke Detectors | 2/21/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 2/21/2024 | Partial Inspection | HERBERT GIRON |
| ELECTRICAL-Final | 4/25/2024 | Approved | TEMISTOCLES CAAL |
| Gas Test | 4/25/2024 | Corrections Issued | TEMISTOCLES CAAL |
| PLUMBING-Final | 4/25/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Gas Test | 5/8/2024 | Approved | BOBBY KEY |
| Final | 5/9/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| Gas Test | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| Green Building Final | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| PLUMBING-Final | 5/9/2024 | Approved | TEMISTOCLES CAAL |
| Special/Order Compliance | 5/9/2024 | Partial Inspection | HERBERT GIRON |