301 N CAROLWOOD DR 90077
Certificate Information: 301 N CAROLWOOD DR 90077
- Application / Permit
- 19010-30000-01715
- Plan Check / Job No.
- B19WL02279
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (23) Accessory Living Quarters
- Work Description
- ADDITION TO (E) DETACHED A.L.Q WITH ROOF DECK ABOVE & WATER FEATURES.
- Permit Issued
- Issued on 9/20/2019
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 9/20/2019
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/24/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/3/2019 | REZA HAGHIGHAT |
| Corrections Issued | 5/6/2019 | REZA HAGHIGHAT |
| Green Plans Picked Up | 5/7/2019 | APPLICANT |
| Quality Review Completed | 5/15/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 5/16/2019 | APPLICANT |
| Applicant returned to address corrections | 6/10/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 8/6/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 8/20/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 8/27/2019 | REZA HAGHIGHAT |
| Applicant returned to address corrections | 9/18/2019 | REZA HAGHIGHAT |
| Plan Check Approved | 9/20/2019 | REZA HAGHIGHAT |
| Issued | 9/20/2019 | LADBS |
Permit Application Clearance Information
| GPI Written Notices | Cleared | 8/6/2019 | REZA HAGHIGHAT |
| Grading Pre-Inspection | Cleared | 8/6/2019 | REZA HAGHIGHAT |
| Eng Process Fee Ord 176,300 | Cleared | 8/22/2019 | JENNY CEA |
| BHO/Hillside ordinance | Cleared | 8/26/2019 | JOSE CRUZ RODRIGUEZ |
| BHO/Hillside ordinance | Cleared | 8/26/2019 | JOSE CRUZ RODRIGUEZ |
| BHO/Hillside ordinance | Cleared | 8/26/2019 | JOSE CRUZ RODRIGUEZ |
| Grading in hillside | Cleared | 8/26/2019 | NOAH MCCOY |
| Miscellaneous | Cleared | 8/26/2019 | NOAH MCCOY |
| Sewer availability | Cleared | 8/26/2019 | JOSE CRUZ RODRIGUEZ |
| ZA Case | Cleared | 8/26/2019 | NOAH MCCOY |
| Flood clearance | Cleared | 8/28/2019 | HISASHI KOBAYAKAWA |
| Green Code | Cleared | 8/28/2019 | RICHARD GARCIA |
| Low Impact Development | Cleared | 9/11/2019 | JORGE MEJIA LEMUS |
| Hydrant and Access approval | Cleared | 9/18/2019 | JOHN CONNEALLY |
| Miscellaneous | Cleared | 9/18/2019 | MAHELET GEBEYHU |
| Roof/Waste drainage to street | Cleared | 9/18/2019 | MAHELET GEBEYHU |
| Watercourse | Cleared | 9/18/2019 | MAHELET GEBEYHU |
| Excavation more than 5-ft deep | Cleared | 9/20/2019 | CALOSHA APPROVED |
Contact Information
| Architect | Landry,, Richard; Lic. No.: C21848 | 1818 S.SEPULVEDA BLVD LOS ANGELES, CA 90025 |
| Contractor | Albino Construction Inc; Lic. No.: 477121-B | 12568 W WASHINGTON BLVD SUITE 200 LOS ANGELES, CA 90066 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Oruncakciel,, Sayat; Lic. No.: C77182 | 15445 VENTURA BLVD 25 SHERMAN OAKS, CA 91403 |
| Geologist | Hollingsworth,, Robert Alan; Lic. No.: EG1265 | 31129 VIA COLINAS SUITE 707 WESTLAKE VILLAGE, CA 91362 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 1/23/2020 | Partial Approval | MATT KELLERMAN |
| FLOOD-Elevation Certificate | 4/3/2020 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/3/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/16/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/20/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 6/10/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 6/11/2020 | Not Ready for Inspection | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 6/30/2020 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 6/30/2020 | Partial Approval | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 7/23/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/23/2020 | Corrections Issued | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 7/27/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/20/2020 | Partial Approval | MATT KELLERMAN |
| Excavation/Setback/Form/Re-Bar | 8/25/2020 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 8/25/2020 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 8/26/2020 | Partial Approval | CHRISTOPHER WILSON |
| Excavation/Setback/Form/Re-Bar | 9/10/2020 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 9/10/2020 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 9/22/2020 | Partial Approval | CHRISTOPHER WILSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2021 | Conditional Approval | MATT KELLERMAN |
| FLOOD-Proofing Certificate | 5/25/2021 | Approved | CHRISTOPHER WILSON |
| Green Building Rough | 5/25/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Structural Steel Frame | 5/25/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Verify Sprinkler Sign Off | 5/25/2021 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Green Building Rough | 6/2/2021 | Not Ready for Inspection | MATT KELLERMAN |
| Structural Steel Frame | 6/2/2021 | Partial Approval | MATT KELLERMAN |
| Verify Sprinkler Sign Off | 6/2/2021 | Not Ready for Inspection | MATT KELLERMAN |