1327 N FULLER AVE 90046
Certificate Information: 1327 N FULLER AVE 90046
- Application / Permit
- 19010-30000-01533
- Plan Check / Job No.
- B19WL02052
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New single family dwelling w/attached garage per VTT-82217-SL. (Lot #4)
- Permit Issued
- Issued on 12/15/2021
- Issuing Office
- Current Status
- CofO Issued on 8/27/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/12/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 5/2/2019 | KAMRAN GHOTBI RAVANDI |
| Plans on Hold | 5/3/2019 | KAMRAN GHOTBI RAVANDI |
| Hold Released | 11/26/2019 | KAMRAN GHOTBI RAVANDI |
| Corrections Issued | 12/3/2019 | KAMRAN GHOTBI RAVANDI |
| Quality Review Completed | 12/17/2019 | FELIX FIGUEROA |
| Applicant returned to address corrections | 3/27/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 4/9/2020 | KAMRAN GHOTBI RAVANDI |
| Applicant returned to address corrections | 7/23/2020 | KAMRAN GHOTBI RAVANDI |
| Green Plans Picked Up | 7/27/2020 | APPLICANT |
| Plan Check Approved | 3/12/2021 | KAMRAN GHOTBI RAVANDI |
| Issued | 12/15/2021 | APPLICANT |
| Building Plans Picked Up | 12/20/2021 | APPLICANT |
| CofO in Progress | 8/19/2024 | BRENDAN MORELLI |
| CofO Issued | 8/27/2024 | RUBEN SALAS |
| Permit Finaled | 8/27/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 4/10/2020 | GEORGE SUCHAND |
| Address approval | Cleared | 4/24/2020 | THOMAS LANG |
| Permit | Cleared | 4/24/2020 | THOMAS LANG |
| Low Impact Development | Cleared | 6/15/2020 | JORGE MEJIA LEMUS |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2020 | RENZ SORIANO |
| Roof/Waste drainage to street | Cleared | 7/20/2020 | RENZ SORIANO |
| Green Code | Cleared | 7/24/2020 | KAMRAN GHOTBI RAVANDI |
| Tract Map conditions | Cleared | 8/14/2020 | DENZEL HENDERSON |
| Sewer availability | Cleared | 8/27/2020 | RENZ SORIANO |
| Miscellaneous | Cleared | 9/18/2020 | NGOC KIEM |
| Trees in Parkway | Cleared | 2/25/2021 | JOHN KIM |
| Building over 3-story or 36-ft | Cleared | 3/12/2021 | CALOSHA APPROVED |
Contact Information
| Architect | Daham,, Ramsey Walid; Lic. No.: C34257 | 109 EUCALYPTUS DRIVE EL SEGUNDO, CA 90245 |
| Contractor | Custom Design Construction; Lic. No.: 737436-B | 19528 VENTURA BLVD #687 TARZANA, CA 91356 |
| Engineer | Kim,, Seung Su; Lic. No.: S5909 | 15808 APOLLO PLACE GARDENA, CA 90249 |
| Engineer | Noori,, Abdul Wahab; Lic. No.: C81696 | 6 BIENVENIDO ALISO VIEJO, CA 92656 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Excavation/Setback/Form/Re-Bar | 12/7/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/7/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 12/8/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 12/16/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 12/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Footing/Foundation/Slab | 12/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 12/21/2022 | Conditional Approval | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 12/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 12/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 12/28/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 1/23/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 1/27/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 1/31/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Gas Test | 2/1/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 2/1/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 2/22/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 2/23/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 3/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 4/14/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 4/14/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/19/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 4/21/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 5/1/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/18/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 5/19/2023 | Conditional Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 5/26/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Steel/Welding | 5/30/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/30/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 6/8/2023 | Conditional Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 6/26/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Drywall Nailing | 6/28/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Deputy Wood Construction | 7/11/2023 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 7/13/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/25/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/25/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 9/11/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 9/15/2023 | Corrections Issued | BRENDAN MORELLI |
| Shower Pan | 9/15/2023 | Approved | BRENDAN MORELLI |
| Interior/Exterior Lathing | 9/21/2023 | Partial Approval | BRENDAN MORELLI |
| PLUMBING-Rough | 9/21/2023 | Conditional Approval | BRENDAN MORELLI |
| Floor/Roof Diaphrgm/Shear Wall | 9/26/2023 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Rough | 10/11/2023 | Approved | BRENDAN MORELLI |
| HVAC-Rough | 10/11/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | BRENDAN MORELLI |
| Green Building Rough | 10/17/2023 | Not Ready for Inspection | BRENDAN MORELLI |
| Verify Sprinkler Sign Off | 10/17/2023 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 11/13/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 11/13/2023 | Approved | ALIZAH MAYAGOITIA |
| Interior/Exterior Lathing | 11/13/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 11/27/2023 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 3/22/2024 | Partial Approval | JOSEPH MCGARRY |
| ELECTRICAL-Final | 7/26/2024 | Corrections Issued | BRENDAN MORELLI |
| Final | 7/26/2024 | Corrections Issued | BRENDAN MORELLI |
| HVAC-Final | 7/26/2024 | Corrections Issued | BRENDAN MORELLI |
| PLUMBING-Final | 7/26/2024 | Corrections Issued | BRENDAN MORELLI |
| Service/Power Release | 7/26/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 8/7/2024 | Approved | BRENDAN MORELLI |
| Final | 8/7/2024 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Final | 8/7/2024 | Approved | BRENDAN MORELLI |
| HVAC-Final | 8/7/2024 | Approved | BRENDAN MORELLI |
| PLUMBING-Final | 8/7/2024 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 8/7/2024 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 8/7/2024 | Approved | BRENDAN MORELLI |
| Smoke Detectors | 8/7/2024 | Approved | BRENDAN MORELLI |
| Final | 8/19/2024 | OK to Issue CofO | BRENDAN MORELLI |