2337 W RIDGEVIEW AVE 90041

Certificate Information: 2337 W RIDGEVIEW AVE 90041

Application / Permit
19010-30000-01525
Plan Check / Job No.
B19WL02045
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SFD w/ attached garage built as a small lot subdivision (VTT No.: 77189-SL). ** 5 of 5 **
Permit Issued
Issued on 12/11/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 12/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 KAVIAN REFAHI
Corrections Issued 5/17/2019 KAVIAN REFAHI
Green Plans Picked Up 5/22/2019 APPLICANT
Quality Review Completed 5/24/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 5/24/2019 APPLICANT
Applicant returned to address corrections 8/28/2019 KAVIAN REFAHI
Applicant returned to address corrections 9/4/2019 KAVIAN REFAHI
Applicant returned to address corrections 10/8/2019 KAVIAN REFAHI
Applicant returned to address corrections 10/15/2019 KAVIAN REFAHI
Plan Check Approved 11/1/2019 KAVIAN REFAHI
Issued 12/11/2019 LADBS
CofO in Progress 12/2/2021 SCOTT FINNILA
Permit Finaled 12/4/2021 DEROLD HAUFF
CofO Issued 12/4/2021 DEROLD HAUFF
Permit Finaled 12/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/6/2019 ELENA LOPEZ
Highway dedication Cleared 6/6/2019 ELENA LOPEZ
Permit Cleared 6/6/2019 ELENA LOPEZ
Opn space landscape/Water mgmt Cleared 9/9/2019 ANNA VAN
Construction near power lines Cleared 9/10/2019 OSCAR CASTRO
Hydrant and Access approval Cleared 9/10/2019 ROBERT DUFF
Mechanical Car Lift Cleared 9/10/2019 ROBERT DUFF
Trees in Parkway Cleared 9/11/2019 ADRIAN SANCHEZ
Low Impact Development Cleared 9/19/2019 JORGE MEJIA LEMUS
Eng Process Fee Ord 176,300 Cleared 9/23/2019 EMIL KYUPELYAN
Sewer availability Cleared 9/23/2019 EMIL KYUPELYAN
Miscellaneous Cleared 9/25/2019 ANNA VAN
Roof/Waste drainage to street Cleared 9/25/2019 ELAINE LEI
GPI Written Notices Cleared 10/15/2019 KAVIAN REFAHI
Grading Pre-Inspection Cleared 10/15/2019 KAVIAN REFAHI
Miscellaneous Cleared 10/15/2019 KAVIAN REFAHI
Green Code Cleared 10/25/2019 RICHARD GARCIA

Contact Information

Architect Chong,, Abbey Kate; Lic. No.: C35532 17250 W SUNSET BLVD   # 316    PACIFIC PALISADES, CA 90272
Contractor Gillette Properties Inc; Lic. No.: 955663-B 29908 VIOLET HILLS DRIVE      CANYON COUNTRY, CA 91387
Engineer Lam,, Chsung Say; Lic. No.: C78287 6919 THELMA AVE      BUENA PARK, CA 90620
Engineer Salehipour,, Sassan A; Lic. No.: GE2579 1290 N LAKE AVENUE #204      PASADENA, CA 91104
Engineer Shen,, William Chuan; Lic. No.: C81681 5341 LA MADERA AVE      EL MONTE, CA 91732

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 2/7/2020 Corrections Issued BRAD BESCOS
Footing/Foundation/Slab 2/12/2020 Partial Approval SCOTT FINNILA
Underground Mechanical 2/20/2020 Partial Approval SCOTT FINNILA
PLUMBING-Rough 2/21/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/14/2020 Corrections Issued SCOTT FINNILA
Underground Mechanical 4/14/2020 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 4/17/2020 Approved SCOTT FINNILA
Underground Mechanical 4/17/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/4/2020 Conditional Approval SCOTT FINNILA
Deputy Wood Construction 5/6/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 5/7/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/11/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/21/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/21/2020 Conditional Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 5/27/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 5/28/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 6/5/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 6/9/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/9/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 6/16/2020 Partial Approval SCOTT FINNILA
Drywall Nailing 6/23/2020 Partial Approval SCOTT FINNILA
Deputy Wood Construction 7/9/2020 Corrections Issued SCOTT FINNILA
Deputy Wood Construction 7/22/2020 Conditional Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 7/23/2020 Corrections Issued ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 9/1/2020 Partial Approval ALEJANDRO DE ARTOLA
Deputy Wood Construction 9/16/2020 Approved DONALD CRICHLOW
Floor/Roof Diaphrgm/Shear Wall 9/16/2020 Partial Approval DONALD CRICHLOW
Wood Frame 9/16/2020 Partial Approval DONALD CRICHLOW
ELECTRICAL-Rough 10/6/2020 Corrections Issued SCOTT FINNILA
HVAC-Rough 10/6/2020 Corrections Issued SCOTT FINNILA
PLUMBING-Rough 10/13/2020 Approved SCOTT FINNILA
ELECTRICAL-Rough 10/30/2020 Corrections Issued SCOTT FINNILA
ELECTRICAL-Rough 11/10/2020 Approved SCOTT FINNILA
HVAC-Rough 11/10/2020 Partial Inspection SCOTT FINNILA
Wood Frame 11/10/2020 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 11/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Rough 11/30/2020 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/4/2020 Partial Approval SCOTT FINNILA
Green Building Rough 12/4/2020 Approved SCOTT FINNILA
Verify Sprinkler Sign Off 12/4/2020 Approved SCOTT FINNILA
HVAC-Rough 12/7/2020 Approved SCOTT FINNILA
BUILDING-Rough-Frame 12/10/2020 Partial Approval SCOTT FINNILA
Insulation 12/23/2020 Not Ready for Inspection SCOTT FINNILA
Insulation 12/30/2020 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/11/2021 Partial Inspection SCOTT FINNILA
Deputy Wood Construction 1/13/2021 Partial Approval SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 1/13/2021 Partial Approval SCOTT FINNILA
Drywall Nailing 1/21/2021 Partial Approval BRAD BESCOS
Interior/Exterior Lathing 1/22/2021 Approved SCOTT FINNILA
Shower Pan 2/1/2021 Corrections Issued SCOTT FINNILA
Interior/Exterior Lathing 2/18/2021 Approved SCOTT FINNILA
Shower Pan 2/18/2021 Approved SCOTT FINNILA
Underground Mechanical 6/3/2021 Partial Approval SCOTT FINNILA
Underground Mechanical 6/16/2021 Partial Approval SCOTT FINNILA
PLUMBING-Final 8/16/2021 Corrections Issued SCOTT FINNILA
ELECTRICAL-Final 9/9/2021 Corrections Issued ALEJANDRO DE ARTOLA
Gas Test 9/27/2021 Approved SCOTT FINNILA
PLUMBING-Final 9/27/2021 Approved SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved SCOTT FINNILA
Service/Power Release 9/27/2021 Approved SCOTT FINNILA
HVAC-Final 9/29/2021 Corrections Issued SCOTT FINNILA
HVAC-Final 10/4/2021 Partial Approval SCOTT FINNILA
Service/Power Release 10/5/2021 Approved SCOTT FINNILA
ELECTRICAL-Final 10/29/2021 Approved SCOTT FINNILA
HVAC-Final 11/16/2021 Approved SCOTT FINNILA
Final 11/23/2021 Corrections Issued ALEJANDRO DE ARTOLA
BUILDING-Rough-Frame 12/2/2021 Approved SCOTT FINNILA
Final 12/2/2021 OK to Issue CofO SCOTT FINNILA
Green Building Final 12/2/2021 Approved SCOTT FINNILA
Smoke Detectors 12/2/2021 Approved SCOTT FINNILA