3755 S CANFIELD AVE 1-8 90034

Certificate Information: 3755 S CANFIELD AVE 1-8 90034

Application / Permit
19010-30000-01478
Plan Check / Job No.
B19WL01983
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4-STORY TYPE VA 8-UNIT APARTMENT BUILDING OVER 1-SUBTERRENEAN TYPE IB PARKING LEVEL, EQUIPPED THROUGHOUT WITH NFPA 13.
Permit Issued
Issued on 8/6/2021
Issuing Office
Current Status
Issued on 8/6/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/12/2019 APPLICANT
Assigned to Plan Check Engineer 5/9/2019 MARJAN SHENASI
Disabled Access Plans Picked Up 5/17/2019 APPLICANT
Corrections Issued 5/22/2019 MARJAN SHENASI
Green Plans Picked Up 5/29/2019 APPLICANT
Quality Review Completed 5/30/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 5/31/2019 APPLICANT
Applicant returned to address corrections 12/20/2019 MARJAN SHENASI
Applicant returned to address corrections 1/3/2020 MARJAN SHENASI
Applicant returned to address corrections 1/9/2020 MARJAN SHENASI
Applicant returned to address corrections 1/16/2020 MARJAN SHENASI
Applicant returned to address corrections 1/27/2020 MARJAN SHENASI
Applicant returned to address corrections 2/4/2020 MARJAN SHENASI
Applicant returned to address corrections 2/10/2020 MARJAN SHENASI
Applicant returned to address corrections 2/18/2020 MARJAN SHENASI
Applicant returned to address corrections 2/25/2020 MARJAN SHENASI
Applicant returned to address corrections 3/3/2020 MARJAN SHENASI
Plan Check Approved 3/11/2020 SERGIO SILVA
No Progress 1/20/2021 SERGIO SILVA
Plan Check Approved 1/20/2021 SERGIO SILVA
Issued 8/6/2021 APPLICANT
TCO Issued (Expire Date: 10-04-2026) 4/7/2026 VASIL MIHALEV

Permit Application Clearance Information

Address approval Cleared 7/18/2019 HISASHI KOBAYAKAWA
Permit Cleared 7/18/2019 HISASHI KOBAYAKAWA
Eng Process Fee Ord 176,300 Cleared 7/19/2019 KATHLEEN HUGHEY
Sewer availability Cleared 7/19/2019 KATHLEEN HUGHEY
CPC Cleared 7/22/2019 SOPHIE GABEL-SCHEINBAU
DAS Clearance Cleared 10/31/2019 SOMKIAT SUPANYACHOTSKUL
Hydrant and Access approval Cleared 11/22/2019 JEREMY CARTER
Frnt yard landscape/Water mgmt Cleared 12/18/2019 JOE LUCKEY
Opn space landscape/Water mgmt Cleared 12/18/2019 JOE LUCKEY
Miscellaneous Cleared 1/3/2020 SARAH GOLDMAN
Grading Pre-Inspection Cleared 1/9/2020 MARJAN SHENASI
GPI Written Notices Cleared 1/16/2020 MARJAN SHENASI
Building over 3-story or 36-ft Cleared 1/27/2020 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/27/2020 CALOSHA APPROVED
Trees in Parkway Cleared 1/30/2020 STEPHEN DUPREY
Construction within easement Cleared 2/25/2020 ERNEST FRESQUEZ
Fire Marshall Fire Life Safety Cleared 2/26/2020 DOMINIQUE MEDINA
Low Impact Development Cleared 2/26/2020 MARTIN FRAGOSO
Miscellaneous Cleared 3/3/2020 JOE LUCKEY
Roof/Waste drainage to street Cleared 3/5/2020 ANTHONY MAINEZ
Green Code Cleared 3/11/2020 RICHARD GARCIA

Contact Information

Architect Driscoll,, Christopher; Lic. No.: C36073 1502 1/2 S SYCAMORE AVENUE      LOS ANGELES, CA 90019
Contractor Hyeco Heating And Air Conditioning; Lic. No.: 901874-B 1515 OPECHEE WAY      GLENDALE, CA 91208
Engineer Labib,, Youhanna T; Lic. No.: S4549 319 MAIN STREET      EL SEGUNDO, CA 90245
Engineer Pukkanasut,, Jirayus; Lic. No.: C73728 15038 CLARK AVE      HACIENDA HEIGHTS, CA 91745

Inspector Information

PAUL DAVIDSON, (310) 914-3914 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/12/2021 Approved JEFF BYTHEWAY
Excavation/Setback/Form/Re-Bar 9/1/2021 Not Ready for Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 9/24/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 9/27/2021 Approved DERRICK SPENCER
Deputy Reinf. Concrete 10/5/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 10/6/2021 Partial Approval JEFF BYTHEWAY
Deputy Shotcrete 10/19/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 10/20/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 10/21/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 10/25/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 10/25/2021 Approved JEFF BYTHEWAY
Green Building Rough 10/27/2021 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 10/27/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 10/27/2021 Partial Approval JEFF BYTHEWAY
Verify Sprinkler Sign Off 10/27/2021 Approved JEFF BYTHEWAY
Deputy Shotcrete 10/28/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 11/9/2021 Partial Inspection JEFF BYTHEWAY
Reinforced Concrete Frame 11/9/2021 Partial Approval JEFF BYTHEWAY
Reinforced Masonry Frame 11/9/2021 Partial Inspection JEFF BYTHEWAY
Deputy Shotcrete 11/10/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 11/12/2021 Approved JEFF BYTHEWAY
Deputy Reinf. Masonry 11/12/2021 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 12/16/2021 Partial Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 1/28/2022 Approved JEFF BYTHEWAY
Footing/Foundation/Slab 2/22/2022 Conditional Approval JEFF BYTHEWAY
Deputy Reinf. Concrete 2/23/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 2/28/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/21/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 4/25/2022 Approved JEFF BYTHEWAY
Reinforced Concrete Frame 5/2/2022 Partial Inspection JEFF BYTHEWAY
Footing/Foundation/Slab 5/3/2022 Approved JEFF BYTHEWAY
Deputy Reinf. Concrete 5/4/2022 Approved JEFF BYTHEWAY
Reinforced Masonry Frame 5/18/2022 Partial Approval JEFF BYTHEWAY
Deputy Steel/Welding 5/26/2022 Approved NICK LAROCCA
Reinforced Masonry Frame 6/13/2022 Partial Inspection SORIN CIRSTOIU
Deputy Wood Construction 6/15/2022 Approved SORIN CIRSTOIU
Wood Frame 6/15/2022 Partial Approval SORIN CIRSTOIU
Wood Frame 6/30/2022 Partial Inspection SORIN CIRSTOIU
Deputy Wood Construction 7/7/2022 Approved DERRICK SPENCER
Deputy Wood Construction 7/26/2022 Approved SORIN CIRSTOIU
Wood Frame 7/26/2022 Partial Approval SORIN CIRSTOIU
Deputy Wood Construction 9/7/2022 Approved SORIN CIRSTOIU
Wood Frame 9/12/2022 Partial Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Corrections Issued SORIN CIRSTOIU
Wood Frame 2/2/2023 Partial Inspection SORIN CIRSTOIU
Structural Steel Frame 3/2/2023 Partial Inspection SORIN CIRSTOIU
Wood Frame 3/2/2023 Partial Inspection SORIN CIRSTOIU
Wood Frame 3/7/2023 Not Ready for Inspection DERRICK SPENCER
Interior/Exterior Lathing 4/6/2023 Partial Approval SORIN CIRSTOIU
Insulation 4/12/2023 Not Ready for Inspection PAUL DAVIDSON
Interior/Exterior Lathing 4/12/2023 Partial Approval PAUL DAVIDSON
Insulation 4/13/2023 Corrections Issued SORIN CIRSTOIU
Interior/Exterior Lathing 4/13/2023 Partial Approval SORIN CIRSTOIU
Insulation 5/8/2023 Partial Inspection PAUL DAVIDSON
Insulation 5/10/2023 Partial Inspection SORIN CIRSTOIU
Floor/Roof Diaphrgm/Shear Wall 6/21/2023 Not Ready for Inspection GRANT WOODS
Insulation 6/21/2023 Not Ready for Inspection GRANT WOODS
Special/Order Compliance 6/26/2023 Partial Inspection GRANT WOODS
Insulation 6/28/2023 Partial Inspection GRANT WOODS
Insulation 6/30/2023 Partial Inspection GRANT WOODS
Interior/Exterior Lathing 7/17/2023 Not Ready for Inspection MICHAEL PETRUSKO
Interior/Exterior Lathing 7/19/2023 Approved MICHAEL PETRUSKO
Insulation 8/15/2023 Partial Approval SORIN CIRSTOIU
Drywall Nailing 8/25/2023 Partial Inspection SORIN CIRSTOIU
Drywall Nailing 9/1/2023 Partial Inspection GRANT WOODS
Insulation 9/13/2023 Partial Approval GRANT WOODS
Drywall Nailing 11/1/2023 No Access for Inspection GRANT WOODS
Interior/Exterior Lathing 11/1/2023 No Access for Inspection GRANT WOODS
Wood Frame 11/1/2023 No Access for Inspection GRANT WOODS
Drywall Nailing 11/9/2023 Partial Approval PAUL DAVIDSON
Interior/Exterior Lathing 11/9/2023 Not Ready for Inspection PAUL DAVIDSON
Drywall Nailing 11/13/2023 Partial Approval GRANT WOODS
Final 2/29/2024 Corrections Issued GRANT WOODS
Green Building Final 2/29/2024 Not Ready for Inspection GRANT WOODS
Reinforced Concrete Frame 2/29/2024 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 2/29/2024 SGSOV Not Ready GRANT WOODS
Smoke Detectors 2/29/2024 Not Ready for Inspection GRANT WOODS
Wood Frame 2/29/2024 Not Ready for Inspection GRANT WOODS
Final 4/8/2024 Corrections Issued GRANT WOODS
Green Building Final 4/8/2024 Not Ready for Inspection GRANT WOODS
Reinforced Concrete Frame 4/8/2024 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 4/8/2024 SGSOV Not Ready GRANT WOODS
Smoke Detectors 4/8/2024 Not Ready for Inspection GRANT WOODS
Wood Frame 4/8/2024 Not Ready for Inspection GRANT WOODS
Final 7/31/2024 Not Ready for Inspection GRANT WOODS
Green Building Final 7/31/2024 Not Ready for Inspection GRANT WOODS
Reinforced Concrete Frame 7/31/2024 Not Ready for Inspection GRANT WOODS
SGSOV-Seismic Gas S/O Valve 7/31/2024 SGSOV Not Ready GRANT WOODS
Smoke Detectors 7/31/2024 Not Ready for Inspection GRANT WOODS
Wood Frame 7/31/2024 Not Ready for Inspection GRANT WOODS
Special/Order Compliance 11/14/2024 Partial Inspection GRANT WOODS
Final 10/29/2025 Not Ready for Inspection DANIEL VARNUM
Green Building Final 10/29/2025 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 10/29/2025 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 10/29/2025 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 10/29/2025 Not Ready for Inspection DANIEL VARNUM
Wood Frame 10/29/2025 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 12/12/2025 SGSOV Not Ready PAUL DAVIDSON
Special/Order Compliance 12/15/2025 Partial Inspection PAUL DAVIDSON
Special/Order Compliance 1/7/2026 Corrections Issued PAUL DAVIDSON
Final 4/1/2026 OK for TCO PAUL DAVIDSON
Green Building Final 4/1/2026 Conditional Approval PAUL DAVIDSON
Reinforced Concrete Frame 4/1/2026 Approved PAUL DAVIDSON
SGSOV-Seismic Gas S/O Valve 4/1/2026 SGSOV Approved PAUL DAVIDSON
Smoke Detectors 4/1/2026 Approved PAUL DAVIDSON
Special/Order Compliance 4/1/2026 Approved VASIL MIHALEV