201 N ROCKINGHAM AVE 90049
Certificate Information: 201 N ROCKINGHAM AVE 90049
- Application / Permit
- 19010-30000-01471
- Plan Check / Job No.
- B19WL01968
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT PER AB494 AND SB229.
- Permit Issued
- Issued on 7/23/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/10/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/25/2019 | KAVIAN REFAHI |
| Corrections Issued | 4/29/2019 | KAVIAN REFAHI |
| Quality Review Completed | 5/10/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 5/10/2019 | APPLICANT |
| Applicant returned to address corrections | 6/5/2019 | KAVIAN REFAHI |
| Green Plans Picked Up | 6/5/2019 | APPLICANT |
| Applicant returned to address corrections | 6/12/2019 | KAVIAN REFAHI |
| Applicant returned to address corrections | 6/24/2019 | MANUEL GARCIA |
| Plan Check Approved | 7/16/2019 | MANUEL GARCIA |
| Issued | 7/23/2019 | LADBS |
| CofO in Progress | 2/23/2022 | JUAN VALENZUELA |
| Permit Finaled | 3/17/2022 | DANIEL ORRANTE |
| CofO Issued | 3/17/2022 | DANIEL ORRANTE |
| Permit Finaled | 3/17/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 5/28/2019 | NOAH MCCOY |
| Hydrant and Access approval | Cleared | 6/18/2019 | GILBERT URREA |
| Address approval | Cleared | 6/27/2019 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 6/27/2019 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 6/27/2019 | MAHELET GEBEYHU |
| BHO/Hillside ordinance | Cleared | 6/27/2019 | MAHELET GEBEYHU |
| Eng Process Fee Ord 176,300 | Cleared | 6/27/2019 | MAHELET GEBEYHU |
| Low Impact Development | Cleared | 6/27/2019 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/27/2019 | MAHELET GEBEYHU |
| Sewer availability | Cleared | 6/27/2019 | MAHELET GEBEYHU |
| Green Code | Cleared | 7/16/2019 | RICHARD GARCIA |
Contact Information
| Contractor | Shain Development Inc; Lic. No.: 937795-B | 14401 VILLA WOODS PLACE PACIFIC PALISADES, CA 90272 |
| Engineer | Daneshfar,, Kourosh Dan; Lic. No.: C68377 | 19722 ARMINTA ST WINNETKA, CA 91306 |
| Engineer | Danz,, Joshua Franklin; Lic. No.: C84764 | 932 WITHERSPOON DRIVE THOUSAND OAKS, CA 91360 |
| Engineer | Tani,, Jason Yukio; Lic. No.: C58271 | 5296 VIA PATRICIA THOUSAND OAKS, CA 91320 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 2/20/2020 | Partial Approval | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 4/29/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 4/30/2020 | Conditional Approval | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 5/6/2020 | Partial Approval | TIM CHRISTENSEN |
| Underground Mechanical | 5/6/2020 | Partial Approval | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 5/20/2020 | Approved | TIM CHRISTENSEN |
| Footing/Foundation/Slab | 5/20/2020 | Approved | TIM CHRISTENSEN |
| Deputy Reinf. Concrete | 5/26/2020 | No Access for Inspection | ROBERT SHELLY |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2020 | Partial Approval | TIM CHRISTENSEN |
| Green Building Rough | 6/4/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| Verify Sprinkler Sign Off | 6/4/2020 | Not Ready for Inspection | TIM CHRISTENSEN |
| HVAC-Rough | 9/23/2020 | Approved | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 9/24/2020 | Approved | TIM CHRISTENSEN |
| HVAC-Rough | 9/24/2020 | Approved | TIM CHRISTENSEN |
| ELECTRICAL-Rough | 2/5/2021 | Corrections Issued | JUAN VALENZUELA |
| Interior/Exterior Lathing | 2/5/2021 | Partial Approval | JUAN VALENZUELA |
| PLUMBING-Rough | 2/5/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Rough | 3/9/2021 | Approved | PIERRE VEGA |
| Interior/Exterior Lathing | 3/9/2021 | Partial Approval | PIERRE VEGA |
| PLUMBING-Rough | 3/9/2021 | Approved | PIERRE VEGA |
| BUILDING-Rough-Frame | 3/18/2021 | Approved | JUAN VALENZUELA |
| Green Building Rough | 3/18/2021 | Approved | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 3/18/2021 | Approved | JUAN VALENZUELA |
| Insulation | 4/7/2021 | Conditional Approval | JUAN VALENZUELA |
| Shower Pan | 4/7/2021 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 4/14/2021 | Approved | PIERRE VEGA |
| Pre-Inspection | 9/20/2021 | Partial Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/6/2021 | No Access for Inspection | JUAN VALENZUELA |
| HVAC-Final | 12/6/2021 | No Access for Inspection | JUAN VALENZUELA |
| PLUMBING-Final | 12/6/2021 | No Access for Inspection | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/7/2021 | Corrections Issued | JUAN VALENZUELA |
| HVAC-Final | 12/7/2021 | Corrections Issued | JUAN VALENZUELA |
| PLUMBING-Final | 12/7/2021 | Corrections Issued | JUAN VALENZUELA |
| ELECTRICAL-Final | 12/14/2021 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 12/14/2021 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/14/2021 | Approved | OGANES TARAKHCHYAN |
| Final | 12/20/2021 | Not Ready for Inspection | ANDREW NAVE |
| Green Building Final | 12/20/2021 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 12/20/2021 | SGSOV Not Ready | ANDREW NAVE |
| Service/Power Release | 12/20/2021 | Not Ready for Inspection | ANDREW NAVE |
| Smoke Detectors | 12/20/2021 | Not Ready for Inspection | ANDREW NAVE |
| Gas Test | 1/3/2022 | Approved | JUAN VALENZUELA |
| Green Building Final | 1/3/2022 | Approved | JUAN VALENZUELA |
| SGSOV-Seismic Gas S/O Valve | 1/3/2022 | SGSOV Approved | JUAN VALENZUELA |
| Smoke Detectors | 1/3/2022 | Approved | JUAN VALENZUELA |
| Final | 2/18/2022 | OK to Issue CofO | JUAN VALENZUELA |
| Service/Power Release | 2/18/2022 | Approved | JUAN VALENZUELA |