1556 W 60TH ST 90047
Certificate Information: 1556 W 60TH ST 90047
- Application / Permit
- 19010-30000-01302
- Plan Check / Job No.
- B19WL01704
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- new two story ADU with attached garage
- Permit Issued
- Issued on 10/10/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 10/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/18/2019 | TARIK SAOUD |
| Corrections Issued | 4/22/2019 | TARIK SAOUD |
| Quality Review Completed | 4/30/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 5/1/2019 | APPLICANT |
| Plan Check Approved | 6/26/2019 | TARIK SAOUD |
| Issued | 10/10/2019 | LADBS |
| CofO in Progress | 10/5/2021 | FREDDIE RIVERA |
| Permit Finaled | 10/13/2021 | DEROLD HAUFF |
| CofO Issued | 10/13/2021 | DEROLD HAUFF |
| Permit Finaled | 10/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/23/2019 | ELAINE LEI |
| Eng Process Fee Ord 176,300 | Cleared | 5/9/2019 | KARAN PATEL |
| Sewer availability | Cleared | 5/9/2019 | KARAN PATEL |
| Green Code | Cleared | 5/29/2019 | RICHARD GARCIA |
| Hydrant and Access approval | Cleared | 5/30/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 6/24/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 6/24/2019 | ELAINE LEI |
Contact Information
| Engineer | Chavez,, Eduardo; Lic. No.: C76372 | 437 ARCADIA WAY WALNUT, CA 91789 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 10/18/2019 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 11/21/2019 | Not Ready for Inspection | ROBERT MCDOWELL |
| Pre-Inspection | 11/25/2019 | No Access for Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/6/2019 | Conditional Approval | FREDDIE RIVERA |
| Underground Mechanical | 12/7/2020 | Partial Approval | FREDDIE RIVERA |
| Footing/Foundation/Slab | 12/21/2020 | Approved | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2021 | Not Ready for Inspection | KATHRYN BUTTERWORTH |
| Floor/Roof Diaphrgm/Shear Wall | 1/8/2021 | Partial Approval | FREDDIE RIVERA |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 3/31/2021 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 3/31/2021 | Approved | FREDDIE RIVERA |
| Green Building Rough | 3/31/2021 | Approved | FREDDIE RIVERA |
| PLUMBING-Rough | 3/31/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 3/31/2021 | Corrections Issued | FREDDIE RIVERA |
| Verify Sprinkler Sign Off | 3/31/2021 | Approved | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/13/2021 | Corrections Issued | FREDDIE RIVERA |
| HVAC-Rough | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Insulation | 4/13/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| BUILDING-Rough-Frame | 4/29/2021 | Approved | FREDDIE RIVERA |
| HVAC-Rough | 4/29/2021 | Approved | FREDDIE RIVERA |
| Insulation | 4/29/2021 | Partial Approval | FREDDIE RIVERA |
| Pre-Inspection | 4/29/2021 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 5/18/2021 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/1/2021 | Partial Approval | FREDDIE RIVERA |
| Interior/Exterior Lathing | 6/1/2021 | Approved | FREDDIE RIVERA |
| Pre-Inspection | 6/1/2021 | Corrections Issued | FREDDIE RIVERA |
| Drywall Nailing | 6/14/2021 | Approved | DAVID FEILER |
| Gas Test | 6/14/2021 | Not Ready for Inspection | DAVID FEILER |
| Sewer | 6/14/2021 | Not Ready for Inspection | DAVID FEILER |
| Gas Test | 7/1/2021 | Partial Approval | EUGENE CASSIDY |
| Sewer | 7/1/2021 | Partial Approval | EUGENE CASSIDY |
| Final | 9/23/2021 | Corrections Issued | FREDDIE RIVERA |
| Gas Test | 9/23/2021 | Approved | FREDDIE RIVERA |
| Green Building Final | 9/23/2021 | Approved | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/23/2021 | SGSOV Not Ready | FREDDIE RIVERA |
| Service/Power Release | 9/23/2021 | Not Ready for Inspection | FREDDIE RIVERA |
| Smoke Detectors | 9/23/2021 | Approved | FREDDIE RIVERA |
| Final | 9/30/2021 | OK to Issue CofO | FREDDIE RIVERA |
| SGSOV-Seismic Gas S/O Valve | 9/30/2021 | SGSOV Approved | FREDDIE RIVERA |
| Service/Power Release | 9/30/2021 | Approved | FREDDIE RIVERA |