5548 N ELMER AVE 91601

Certificate Information: 5548 N ELMER AVE 91601

Application / Permit
19010-30000-01296
Plan Check / Job No.
B19WL01693
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
4 stories apartment building over 1 story below grade garage total 15 unit apartment lofts with 1 story, type I below grade parking level and 4 stories, type III units above includes roof deck with building amenities. Project will dedicate 2 units to very low income for reduced parking incentive under SB1818, density bonus & AB744, reduced parking within 1/2 mile of major transit stop.
Permit Issued
Issued on 3/11/2021
Issuing Office
Valley
Current Status
Issued on 3/11/2021
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/28/2019 APPLICANT
Green Plans Picked Up 4/24/2019 APPLICANT
Assigned to Plan Check Engineer 4/25/2019 MANUEL GARCIA
Corrections Issued 5/7/2019 MANUEL GARCIA
Quality Review Completed 5/15/2019 KAMRAN GHOTBI RAVANDI
Disabled Access Plans Picked Up 6/6/2019 APPLICANT
Applicant returned to address corrections 6/14/2019 MANUEL GARCIA
Applicant returned to address corrections 9/25/2019 MANUEL GARCIA
Applicant returned to address corrections 2/25/2020 MANUEL GARCIA
Applicant returned to address corrections 8/3/2020 MANUEL GARCIA
Building Plans Picked Up 8/4/2020 APPLICANT
Applicant returned to address corrections 11/15/2020 MANUEL GARCIA
Plan Check Approved 1/20/2021 MANUEL GARCIA
Issued 3/11/2021 APPLICANT

Permit Application Clearance Information

CPC Cleared 6/6/2019 NOAH MCCOY
CPC Cleared 6/6/2019 NOAH MCCOY
Address approval Cleared 6/11/2019 CELINA MORENO
Permit Cleared 6/11/2019 CELINA MORENO
Hydrant and Access approval Cleared 7/15/2019 JOHN CONNEALLY
Density Bonus 12.22.A.25 Cleared 8/6/2019 RICHARD TRUONG
Project located in CRA area Cleared 8/6/2019 JIM URQUHART
Eng Process Fee Ord 176,300 Cleared 9/11/2019 GABRIEL ROBLES
Highway dedication Cleared 9/11/2019 GABRIEL ROBLES
Sewer availability Cleared 9/11/2019 GABRIEL ROBLES
Work Adjacent to Public Way Cleared 9/11/2019 GABRIEL ROBLES
Fire Marshall Fire Life Safety Cleared 9/2/2020 ANDREW KO
Low Impact Development Cleared 9/11/2020 MARTIN FRAGOSO
DAS Clearance Cleared 10/27/2020 MANUEL GARCIA
Green Code Cleared 10/29/2020 DONALD CRICHLOW
Frnt yard landscape/Water mgmt Cleared 12/11/2020 DENZEL HENDERSON
Opn space landscape/Water mgmt Cleared 12/11/2020 DENZEL HENDERSON
Roof/Waste drainage to street Cleared 12/23/2020 ADRIAN CASTRO
Building over 3-story or 36-ft Cleared 1/20/2021 CALOSHA APPROVED
Excavation more than 5-ft deep Cleared 1/20/2021 CALOSHA APPROVED

Contact Information

Contractor Rooter Hero Plumbing; Lic. No.: 1028886-B 11150 SEPULVEDA BLVD STE 2A      MISSION HILLS, CA 91345

Inspector Information

ROBERT DAVIS, (818) 374-1125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 7/6/2021 Approved JOHN KITCKO
Deputy Shotcrete 7/13/2021 Conditional Approval JEFFREY DURAN
Green Building Rough 7/16/2021 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 7/16/2021 Conditional Approval ROBERT DAVIS
Verify Sprinkler Sign Off 7/16/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Shotcrete 7/21/2021 Conditional Approval CAMERON CHABAN
Wood Frame 7/30/2021 Partial Inspection JOHN KITCKO
Excavation/Setback/Form/Re-Bar 8/17/2021 Partial Approval JOHN KITCKO
Deputy Reinf. Concrete 8/19/2021 Approved JOHN KITCKO
Deputy Reinf. Concrete 8/25/2021 Approved ROBERT DAVIS
Structural Steel Frame 8/25/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 8/30/2021 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 9/2/2021 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 9/2/2021 Partial Approval ROBERT DAVIS
Deputy Reinf. Masonry 9/13/2021 Approved ROBERT DAVIS
Green Building Rough 9/13/2021 Not Ready for Inspection ROBERT DAVIS
Masonry Wall/Backfill 9/13/2021 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 9/13/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Masonry 9/15/2021 Conditional Approval ROBERT DAVIS
Green Building Rough 9/20/2021 Not Ready for Inspection ROBERT DAVIS
Reinforced Masonry Frame 9/20/2021 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 9/20/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Masonry 9/21/2021 Approved ROBERT DAVIS
Deputy Reinf. Concrete 9/28/2021 Conditional Approval KENNETH ROBERTS
Footing/Foundation/Slab 9/28/2021 Partial Approval ROBERT DAVIS
Green Building Rough 9/28/2021 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 9/28/2021 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 9/28/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 10/4/2021 Conditional Approval ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 11/18/2021 Partial Approval ROBERT DAVIS
Green Building Rough 11/18/2021 Not Ready for Inspection ROBERT DAVIS
Reinforced Concrete Frame 11/18/2021 Partial Approval ROBERT DAVIS
Verify Sprinkler Sign Off 11/18/2021 Not Ready for Inspection ROBERT DAVIS
Deputy Reinf. Concrete 2/7/2022 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 2/24/2022 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 3/29/2022 Partial Approval ROBERT DAVIS
Deputy Steel/Welding 4/4/2022 Conditional Approval ROBERT DAVIS
Deputy Steel/Welding 4/5/2022 Conditional Approval ROBERT DAVIS
Wood Frame 4/12/2022 Conditional Approval ROBERT DAVIS
Deputy Wood Construction 4/13/2022 Conditional Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 6/1/2022 Corrections Issued ROBERT DAVIS
Insulation 10/31/2022 Corrections Issued ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Partial Approval ROBERT DAVIS
Special/Order Compliance 1/6/2023 Partial Inspection ANDREW DORSO
Special/Order Compliance 1/10/2023 Partial Inspection ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Not Ready for Inspection ROBERT DAVIS
Special/Order Compliance 1/12/2023 Partial Inspection STEVEN LEVITT
Wood Frame 1/12/2023 Corrections Issued ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 2/15/2023 Not Ready for Inspection ROBERT DAVIS
Insulation 2/15/2023 Not Ready for Inspection ROBERT DAVIS
Wood Frame 2/15/2023 Not Ready for Inspection ROBERT DAVIS
Insulation 2/23/2023 Partial Approval ROBERT DAVIS
Insulation 3/6/2023 Partial Approval ROBERT DAVIS
Wood Frame 3/6/2023 Conditional Approval ROBERT DAVIS
Drywall Nailing 3/28/2023 Not Ready for Inspection ROBERT DAVIS
Insulation 4/21/2023 Partial Approval ROBERT DAVIS
Drywall Nailing 5/25/2023 Partial Inspection ROBERT DAVIS
Drywall Nailing 5/30/2023 Not Ready for Inspection ROBERT DAVIS
Footing/Foundation/Slab 7/26/2023 Partial Approval ROBERT DAVIS
Floor/Roof Diaphrgm/Shear Wall 9/20/2023 Partial Approval ROBERT DAVIS
Insulation 11/1/2023 Partial Approval ROBERT DAVIS
Drywall Nailing 11/21/2023 Partial Approval ROBERT DAVIS
Insulation 11/21/2023 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 12/18/2023 Not Ready for Inspection ROBERT DAVIS
Interior/Exterior Lathing 12/21/2023 Partial Approval ROBERT DAVIS
Wood Frame 3/4/2024 Partial Approval ROBERT DAVIS
Special/Order Compliance 3/5/2024 Corrections Issued ROBERT DAVIS
Drywall Nailing 3/6/2024 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 3/8/2024 Corrections Issued ROBERT DAVIS
Drywall Nailing 3/14/2024 Not Ready for Inspection ROBERT DAVIS
Drywall Nailing 3/15/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 3/18/2024 Not Ready for Inspection ROBERT DAVIS
Interior/Exterior Lathing 3/28/2024 Partial Inspection ANDREW DORSO
Drywall Nailing 3/29/2024 Not Ready for Inspection ROBERT DAVIS
Interior/Exterior Lathing 3/29/2024 Not Ready for Inspection ROBERT DAVIS
Interior/Exterior Lathing 6/7/2024 Partial Approval ROBERT DAVIS
Wood Frame 6/11/2024 Not Ready for Inspection ROBERT DAVIS
Insulation 6/18/2024 Not Ready for Inspection ROBERT DAVIS
Wood Frame 7/3/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 7/9/2024 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 8/1/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 8/8/2024 No Access for Inspection ROBERT DAVIS
Drywall Nailing 8/9/2024 Partial Approval ROBERT DAVIS
Drywall Nailing 10/2/2024 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 10/2/2024 Approved ROBERT DAVIS
Footing/Foundation/Slab 3/21/2025 Partial Approval ROBERT DAVIS
Footing/Foundation/Slab 5/1/2025 Corrections Issued ROBERT DAVIS
Drywall Nailing 5/6/2025 Partial Inspection ROBERT DAVIS
Drywall Nailing 5/23/2025 Partial Approval ROBERT DAVIS
Interior/Exterior Lathing 5/23/2025 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/11/2025 Corrections Issued ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/13/2025 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 6/17/2025 Partial Approval ROBERT DAVIS
Special/Order Compliance 9/11/2025 Partial Inspection ROBERT DAVIS
Special/Order Compliance 10/2/2025 Partial Inspection ROBERT DAVIS
Pre-Inspection 12/4/2025 Partial Inspection ROBERT DAVIS