3632 S GREENWOOD AVE 90066
Certificate Information: 3632 S GREENWOOD AVE 90066
- Application / Permit
- 19010-30000-01146
- Plan Check / Job No.
- B19WL01491
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- New two story single family dwelling. Fully sprinklered Type VB.
- Permit Issued
- Issued on 6/27/2019
- Issuing Office
- South Los Angeles
- Current Status
- CofO Issued on 4/9/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/19/2019 | APPLICANT |
| Green Plans Picked Up | 3/29/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 4/4/2019 | RICARDO RAMIREZ |
| Corrections Issued | 4/8/2019 | RICARDO RAMIREZ |
| Quality Review Completed | 4/18/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 4/18/2019 | APPLICANT |
| Plan Check Approved | 6/10/2019 | RICARDO RAMIREZ |
| Issued | 6/27/2019 | LADBS |
| CofO in Progress | 3/18/2021 | ENRIQUE MIRELES |
| CofO Issued | 4/9/2021 | VINCENT COTTON |
| Permit Finaled | 4/9/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/22/2019 | ROBYN STEELE |
| Hydrant and Access approval | Cleared | 5/22/2019 | GILBERT URREA |
| Permit | Cleared | 5/22/2019 | CELINA MORENO |
| Sewer availability | Cleared | 5/22/2019 | CELINA MORENO |
| Trees in Parkway | Cleared | 5/22/2019 | JOHN KIM |
| Low Impact Development | Cleared | 5/24/2019 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/24/2019 | ZIXUAN CHEN |
| Green Code | Cleared | 6/6/2019 | DONALD CRICHLOW |
| GPI Written Notices | Cleared | 6/10/2019 | RICARDO RAMIREZ |
| Grading Pre-Inspection | Cleared | 6/10/2019 | RICARDO RAMIREZ |
Contact Information
| Architect | Scrafano,, Elissa F; Lic. No.: C26071 | 163 N SYCAMORE LOS ANGELES, CA 90036 |
| Contractor | Owner-Builder | , |
| Engineer | Manalo,, Philip Casis; Lic. No.: S3823 | 9547 WYSTONE AVE NORTHRIDGE, CA 91324 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/8/2019 | Corrections Issued | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 7/11/2019 | Not Ready for Inspection | JUAN VALENZUELA |
| Pre-Inspection | 8/6/2019 | Not Ready for Inspection | DAVID FEILER |
| Pre-Inspection | 8/23/2019 | Not Ready for Inspection | CRAIG DAVIS |
| Underground Mechanical | 8/23/2019 | Partial Approval | CRAIG DAVIS |
| Excavation/Setback/Form/Re-Bar | 9/19/2019 | Partial Approval | JOHNNY MIRANDA |
| Piling/Pier/Caisson | 9/19/2019 | Partial Approval | JOHNNY MIRANDA |
| Underground Mechanical | 10/7/2019 | Approved | RONALD WEBER |
| Footing/Foundation/Slab | 10/11/2019 | Corrections Issued | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 10/22/2019 | Partial Approval | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 10/23/2019 | Partial Approval | JOHNNY MIRANDA |
| Footing/Foundation/Slab | 11/4/2019 | Partial Approval | JOHNNY MIRANDA |
| Deputy Steel/Welding | 11/18/2019 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 12/17/2019 | Partial Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 2/12/2020 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 2/25/2020 | Partial Approval | JUAN VALENZUELA |
| HVAC-Rough | 4/21/2020 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 4/21/2020 | Partial Approval | DAVID FEILER |
| Interior/Exterior Lathing | 4/23/2020 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 5/4/2020 | Corrections Issued | DAVID FEILER |
| HVAC-Rough | 5/4/2020 | Partial Inspection | DAVID FEILER |
| PLUMBING-Rough | 5/4/2020 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 5/5/2020 | Approved | DAVID FEILER |
| Green Building Rough | 5/5/2020 | Approved | DAVID FEILER |
| Rough-Elec/Plmb/HVAC | 5/5/2020 | Approved | DAVID FEILER |
| Shower Pan | 5/5/2020 | Approved | DAVID FEILER |
| Verify Sprinkler Sign Off | 5/5/2020 | Approved | DAVID FEILER |
| Insulation | 6/9/2020 | Approved | JOHNNY MIRANDA |
| Drywall Nailing | 6/16/2020 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 7/15/2020 | Approved | JOHNNY MIRANDA |
| Enclosure/Fence | 9/28/2020 | Partial Approval | ENRIQUE MIRELES |
| Enclosure/Fence | 9/29/2020 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/7/2020 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 10/13/2020 | Partial Approval | ENRIQUE MIRELES |
| PLUMBING-Final | 10/27/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 11/4/2020 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Final | 11/9/2020 | Approved | ENRIQUE MIRELES |
| Enclosure/Fence | 11/17/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 11/20/2020 | Approved | ENRIQUE MIRELES |
| HVAC-Final | 11/20/2020 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Final | 1/25/2021 | Approved | ENRIQUE MIRELES |
| Final | 3/12/2021 | Corrections Issued | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 3/12/2021 | Approved | ENRIQUE MIRELES |
| Green Building Final | 3/12/2021 | Approved | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 3/12/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Service/Power Release | 3/12/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Smoke Detectors | 3/12/2021 | Approved | ENRIQUE MIRELES |
| Final | 3/18/2021 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 3/18/2021 | Approved | ENRIQUE MIRELES |