21637 W DUMETZ ROAD 91364

Certificate Information: 21637 W DUMETZ ROAD 91364

Application / Permit
19010-30000-01041
Plan Check / Job No.
B19WL01350
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New 2-story accessory dwelling unit per AB 494 and SB 229
Permit Issued
Issued on 2/14/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 8/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/12/2019 APPLICANT
Assigned to Plan Check Engineer 4/11/2019 MARJAN SHENASI
Green Plans Picked Up 4/17/2019 APPLICANT
Corrections Issued 4/18/2019 MARJAN SHENASI
Quality Review Completed 4/25/2019 KAMRAN GHOTBI RAVANDI
Applicant returned to address corrections 9/23/2019 MARJAN SHENASI
Applicant returned to address corrections 10/31/2019 MARJAN SHENASI
Applicant returned to address corrections 11/7/2019 MARJAN SHENASI
Plan Check Approved 2/14/2020 MARJAN SHENASI
Issued 2/14/2020 LADBS
Building Plans Picked Up 1/25/2021 APPLICANT
CofO in Progress 8/10/2022 PETER FOLLING
Permit Finaled 8/12/2022 JOHN JANSON
CofO Issued 8/12/2022 JOHN JANSON
Permit Finaled 8/12/2022 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 5/9/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 5/9/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 5/9/2019 JEANETTE VONG
BHO/Hillside ordinance Cleared 5/9/2019 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/9/2019 JEANETTE VONG
Sewer availability Cleared 5/9/2019 JEANETTE VONG
Low Impact Development Cleared 6/20/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 6/20/2019 JEANETTE VONG
Green Code Cleared 8/6/2019 RICHARD GARCIA
Disturb/Remove Protected Trees Cleared 9/3/2019 ADRIAN SANCHEZ
Specific Plan Cleared 9/17/2019 VALENTINA KNOX
GPI Written Notices Cleared 11/7/2019 MARJAN SHENASI
Grading Pre-Inspection Cleared 11/7/2019 MARJAN SHENASI
Hydrant and Access approval Cleared 11/14/2019 ROBERT DUFF

Contact Information

Contractor J L S Development Inc; Lic. No.: 919951-B 24007 VENTURA BLVD #207      CALABASAS, CA 91302
Engineer Eden,, Joseph Taki; Lic. No.: C39955 14412 FRIAR ST      VAN NUYS, CA 91401
Engineer Zweigler,, Robert Ingraham; Lic. No.: GE2120 1461 E. CHEVY CHASE DR. #200      GLENDALE, CA 91206
Geologist Cugno,, Giuseppe; Lic. No.: EG1804 1461 E CHEVY CHASE DR 200   BYER GEOTECHNICAL, INC.    GLENDALE, CA 91206

Inspector Information

JOHN HAYES, (818) 774-4302 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/25/2020 Corrections Issued DAVID SANDOVAL
Footing/Foundation/Slab 12/2/2020 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 12/7/2020 Approved DONALD SUNSERI
Reinforced Masonry Frame 12/15/2020 Corrections Issued DONALD SUNSERI
ELECTRICAL-Rough 1/6/2021 Partial Approval PAUL CHOPP
Gas Test 1/6/2021 Approved PAUL CHOPP
Underground Mechanical 1/6/2021 Partial Approval PAUL CHOPP
Reinforced Masonry Frame 2/1/2021 Partial Inspection PAUL CHOPP
Reinforced Masonry Frame 2/3/2021 Approved PAUL CHOPP
BUILDING-Rough-Frame 2/23/2021 Partial Approval PAUL CHOPP
Green Building Rough 2/23/2021 Not Ready for Inspection PAUL CHOPP
PLUMBING-Rough 2/23/2021 Partial Approval PAUL CHOPP
Sewer 2/23/2021 Approved PAUL CHOPP
Verify Sprinkler Sign Off 2/23/2021 Not Ready for Inspection PAUL CHOPP
Floor/Roof Diaphrgm/Shear Wall 4/12/2021 Partial Approval DAVID SANDOVAL
Floor/Roof Diaphrgm/Shear Wall 5/14/2021 Approved DAVID SANDOVAL
ELECTRICAL-Rough 9/9/2021 Approved PETER FOLLING
HVAC-Rough 9/9/2021 Corrections Issued PETER FOLLING
Interior/Exterior Lathing 9/14/2021 Partial Approval PETER FOLLING
PLUMBING-Rough 9/14/2021 Approved PETER FOLLING
HVAC-Rough 10/20/2021 Not Ready for Inspection SHAVONNE ESPINOZA
BUILDING-Rough-Frame 10/25/2021 Partial Approval PETER FOLLING
Green Building Rough 10/25/2021 Approved PETER FOLLING
HVAC-Rough 10/25/2021 Approved PETER FOLLING
Insulation 11/8/2021 Approved PETER FOLLING
Drywall Nailing 11/17/2021 Approved PETER FOLLING
Interior/Exterior Lathing 11/17/2021 Approved PETER FOLLING
Shower Pan 11/17/2021 Approved PETER FOLLING
Final 6/28/2022 Corrections Issued PETER FOLLING
Gas Test 6/28/2022 Approved PETER FOLLING
PLUMBING-Final 6/28/2022 Approved PETER FOLLING
BUILDING-Rough-Frame 7/29/2022 Approved PETER FOLLING
ELECTRICAL-Final 7/29/2022 Not Ready for Inspection PETER FOLLING
Final 7/29/2022 Corrections Issued PETER FOLLING
Green Building Final 7/29/2022 Approved PETER FOLLING
HVAC-Final 7/29/2022 Approved PETER FOLLING
SGSOV-Seismic Gas S/O Valve 7/29/2022 SGSOV Approved PETER FOLLING
Service/Power Release 7/29/2022 Not Ready for Inspection PETER FOLLING
Smoke Detectors 7/29/2022 Approved PETER FOLLING
Verify Sprinkler Sign Off 7/29/2022 Approved PETER FOLLING
Final 8/9/2022 OK to Issue CofO PETER FOLLING
Service/Power Release 8/9/2022 Approved PETER FOLLING