425 N PARKWOOD DR 90077

Certificate Information: 425 N PARKWOOD DR 90077

Application / Permit
19010-30000-00928
Plan Check / Job No.
B19WL01147
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) Single Family Dwelling w/ Basement and attached garage. Equipped with an automatic residential fire sprinkler system NFPA13D.
Permit Issued
Issued on 10/10/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/31/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/6/2019 APPLICANT
Assigned to Plan Check Engineer 3/21/2019 ALFREDO JARA
Corrections Issued 3/26/2019 ALFREDO JARA
Quality Review Completed 4/4/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 4/5/2019 APPLICANT
Green Plans Picked Up 4/29/2019 APPLICANT
Plan Check Approved 7/10/2019 ALFREDO JARA
Issued 10/10/2019 LADBS
CofO in Progress 5/27/2023 CHRISTOPHER WILSON
Permit Finaled 5/31/2023 DANIEL ORRANTE
CofO Issued 5/31/2023 DANIEL ORRANTE
Permit Finaled 5/31/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/4/2019 ELENA LOPEZ
BHO/Hillside ordinance Cleared 4/4/2019 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 4/4/2019 DENNIS BRAGIN
BHO/Hillside ordinance Cleared 4/4/2019 DENNIS BRAGIN
Construction near power lines Cleared 4/4/2019 NADER ISKANDER
Eng Process Fee Ord 176,300 Cleared 4/4/2019 ELENA LOPEZ
Permit Cleared 4/4/2019 ELENA LOPEZ
Sewer availability Cleared 4/4/2019 ELENA LOPEZ
Hydrant and Access approval Cleared 4/5/2019 JOHN CONNEALLY
Trees in Parkway Cleared 4/12/2019 ADRIAN SANCHEZ
Disturb/Remove Protected Trees Cleared 4/19/2019 JOHN KIM
Low Impact Development Cleared 5/10/2019 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 5/14/2019 ELENA LOPEZ
Excavation more than 5-ft deep Cleared 5/30/2019 CALOSHA APPROVED
GPI Written Notices Cleared 5/30/2019 ALFREDO JARA
Grading Pre-Inspection Cleared 5/30/2019 ALFREDO JARA
Green Code Cleared 5/30/2019 RICHARD GARCIA

Contact Information

Architect Manion,, Richard M; Lic. No.: C26957 11400 WEST OLYMPIC BLVD SUITE 410      LOS ANGELES, CA 90025
Contractor Conquest Construction Management Inc; Lic. No.: 850578-B 19360 RINALDI ST STE 335      PORTER RANCH, CA 91326
Engineer Harris,, William Donald; Lic. No.: S5121 26344 DUNWOOD RD      ROLLING HILLS ESTATES, CA 90274
Geologist Hollingsworth,, Robert Alan; Lic. No.: EG1265 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362

Inspector Information

RYAN SALAZAR, (310) 914-3862 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/12/2019 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 3/31/2020 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 4/1/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 4/1/2020 Partial Approval CHRISTOPHER WILSON
Deputy Reinf. Concrete 4/2/2020 Conditional Approval CHRISTOPHER WILSON
PLUMBING-Rough 4/3/2020 Partial Approval CHRISTOPHER WILSON
Sewer 4/3/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/4/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 5/13/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 5/13/2020 Partial Approval MATT KELLERMAN
Reinforced Concrete Frame 5/14/2020 Partial Approval CHRISTOPHER WILSON
Grading Pre-Inspection 5/27/2020 Partial Inspection CHRISTOPHER WILSON
PLUMBING-Rough 6/2/2020 Corrections Issued CHRISTOPHER WILSON
Underground Mechanical 6/2/2020 Partial Approval CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 6/3/2020 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 6/3/2020 Partial Approval CHRISTOPHER WILSON
Piling/Pier/Caisson 6/5/2020 Partial Inspection CHRISTOPHER WILSON
Piling/Pier/Caisson 6/8/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 6/18/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 7/8/2020 Corrections Issued CHRISTOPHER WILSON
Reinforced Masonry Frame 7/9/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 7/10/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/10/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/24/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 8/14/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 8/20/2020 Partial Approval MATT KELLERMAN
Footing/Foundation/Slab 8/27/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/11/2020 Corrections Issued CHRISTOPHER WILSON
Excavation/Setback/Form/Re-Bar 9/14/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 9/24/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 9/30/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/9/2020 Partial Approval CHRISTOPHER WILSON
Wood Frame 10/14/2020 Partial Approval MATT KELLERMAN
BUILDING-Rough-Frame 10/16/2020 Corrections Issued CHRISTOPHER WILSON
Wood Frame 10/19/2020 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 10/22/2020 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Rough 10/22/2020 Partial Approval CHRISTOPHER WILSON
Reinforced Concrete Frame 10/22/2020 Not Ready for Inspection CHRISTOPHER WILSON
Reinforced Concrete Frame 10/27/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/28/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/12/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 11/17/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/23/2020 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/1/2020 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 12/1/2020 Partial Approval CHRISTOPHER WILSON
Wood Frame 12/9/2020 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 12/22/2020 Partial Approval MATT KELLERMAN
Special/Order Compliance 1/9/2021 Partial Inspection CHRISTOPHER WILSON
Special/Order Compliance 1/9/2021 Partial Inspection MICHAEL PELHAM
Footing/Foundation/Slab 2/2/2021 Corrections Issued CHRISTOPHER WILSON
Deputy Steel/Welding 2/19/2021 Conditional Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 2/19/2021 Corrections Issued CHRISTOPHER WILSON
Deputy Steel/Welding 2/25/2021 Conditional Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 3/4/2021 Corrections Issued CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/5/2021 Not Ready for Inspection CHRISTOPHER WILSON
Footing/Foundation/Slab 3/5/2021 Partial Approval CHRISTOPHER WILSON
Special/Order Compliance 3/6/2021 Partial Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Corrections Issued CHRISTOPHER WILSON
Piling/Pier/Caisson 3/12/2021 Corrections Issued CHRISTOPHER WILSON
BUILDING-Rough-Frame 3/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 3/16/2021 Partial Approval CHRISTOPHER WILSON
Green Building Rough 3/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
Verify Sprinkler Sign Off 3/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
PLUMBING-Rough 5/4/2021 Partial Approval CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 5/10/2021 Partial Approval CHRISTOPHER WILSON
Footing/Foundation/Slab 7/12/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 7/12/2021 Partial Approval CHRISTOPHER WILSON
Wood Frame 8/4/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 8/31/2021 Partial Approval CHRISTOPHER WILSON
Gas Test 10/12/2021 Partial Approval CHRISTOPHER WILSON
PLUMBING-Rough 10/12/2021 Conditional Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 10/20/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 11/19/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 11/23/2021 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 11/24/2021 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Rough 12/6/2021 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 12/7/2021 Approved CHRISTOPHER WILSON
HVAC-Rough 12/8/2021 Corrections Issued CHRISTOPHER WILSON
HVAC-Rough 12/16/2021 Not Ready for Inspection CHRISTOPHER WILSON
Floor/Roof Diaphrgm/Shear Wall 12/20/2021 Corrections Issued CHRISTOPHER WILSON
Special/Order Compliance 12/20/2021 Partial Inspection CLAYTON GRAHAM
BUILDING-Rough-Frame 12/21/2021 Partial Approval CHRISTOPHER WILSON
Green Building Rough 12/21/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 12/21/2021 Partial Approval CHRISTOPHER WILSON
Verify Sprinkler Sign Off 12/21/2021 Approved CHRISTOPHER WILSON
Shower Pan 12/22/2021 Not Ready for Inspection RYAN SALAZAR
Shower Pan 12/27/2021 Partial Approval CHRISTOPHER WILSON
Interior/Exterior Lathing 1/12/2022 Not Ready for Inspection CHRISTOPHER WILSON
Special/Order Compliance 1/12/2022 Partial Approval OGANES TARAKHCHYAN
Interior/Exterior Lathing 1/18/2022 Approved DEANDRE HOFFMAN
BUILDING-Rough-Frame 1/28/2022 Corrections Issued CHRISTOPHER WILSON
Green Building Rough 1/28/2022 Approved CHRISTOPHER WILSON
HVAC-Rough 1/28/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 2/1/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Shower Pan 2/4/2022 Approved CHRISTOPHER WILSON
Insulation 2/8/2022 Conditional Approval BRENDAN LOONEY
Interior/Exterior Lathing 2/9/2022 Partial Approval STEPHANIE SWANSON
Insulation 2/10/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Interior/Exterior Lathing 2/10/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 2/23/2022 Not Ready for Inspection CHRISTOPHER WILSON
Interior/Exterior Lathing 2/23/2022 Not Ready for Inspection CHRISTOPHER WILSON
Drywall Nailing 2/25/2022 Partial Approval STEPHANIE SWANSON
Drywall Nailing 3/3/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 3/8/2022 Approved CHRISTOPHER WILSON
Interior/Exterior Lathing 4/26/2022 Partial Approval GERMAN RODRIGUEZ MENDOZA
Pre-Inspection 8/24/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 8/31/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 9/1/2022 Corrections Issued CHRISTOPHER WILSON
Pre-Inspection 9/2/2022 Partial Approval CHRISTOPHER WILSON
ELECTRICAL-Rough 9/15/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 9/22/2022 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Rough 9/28/2022 Not Ready for Inspection CHRISTOPHER WILSON
Service/Power Release 9/29/2022 Approved CHRISTOPHER WILSON
Gas Test 3/13/2023 Approved JESUS PINEDA
HVAC-Rough 3/16/2023 Approved CHRISTOPHER WILSON
HVAC-Final 4/3/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 4/5/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 4/11/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 4/12/2023 Corrections Issued CHRISTOPHER WILSON
HVAC-Final 4/12/2023 Corrections Issued CHRISTOPHER WILSON
PLUMBING-Final 4/13/2023 Approved CHRISTOPHER WILSON
ELECTRICAL-Final 4/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 4/19/2023 Approved GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/24/2023 Approved CHRISTOPHER WILSON
Final 4/24/2023 Corrections Issued CHRISTOPHER WILSON
Footing/Foundation/Slab 4/24/2023 Approved CHRISTOPHER WILSON
Green Building Final 4/24/2023 Approved CHRISTOPHER WILSON
HVAC-Final 4/24/2023 Approved CHRISTOPHER WILSON
SGSOV-Seismic Gas S/O Valve 4/24/2023 SGSOV Approved CHRISTOPHER WILSON
Smoke Detectors 4/24/2023 Approved CHRISTOPHER WILSON
Final 4/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
Final 5/8/2023 Not Ready for Inspection CHRISTOPHER WILSON
Final 5/20/2023 Corrections Issued MICHAEL PELHAM
Final 5/26/2023 Conditional Approval CHRISTOPHER WILSON