Pre-Inspection
|
10/4/2019
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Excavation/Setback/Form/Re-Bar
|
11/18/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/20/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
11/20/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/21/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/22/2019
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/12/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/12/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
12/13/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
12/13/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Special/Order Compliance
|
12/14/2019
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/27/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/30/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
12/31/2019
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/2/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/21/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/3/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/3/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/5/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/5/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
2/5/2020
|
Partial Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/6/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
2/6/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/7/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Drilled-In Anchors
|
2/27/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/28/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/28/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/4/2020
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Excavation/Setback/Form/Re-Bar
|
3/24/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/27/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/3/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
4/3/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
7/20/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/21/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/21/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/22/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/23/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/28/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/31/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/1/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/4/2020
|
Conditional Approval
|
MATT KELLERMAN
|
|
Deputy Reinf. Concrete
|
9/9/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/16/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/17/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Piling/Pier/Caisson
|
9/22/2020
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/28/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/30/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/28/2020
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/29/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
10/30/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/9/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/12/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/16/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/24/2020
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/24/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/25/2020
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/18/2020
|
Partial Approval
|
THOMAS FINNILA
|
|
Deputy Reinf. Concrete
|
12/28/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
12/30/2020
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Deputy Reinf. Concrete
|
12/31/2020
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Reinf. Concrete
|
1/5/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/14/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
1/19/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
1/20/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Shotcrete
|
1/21/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Shotcrete
|
1/22/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
1/22/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/26/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
1/27/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
1/28/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/2/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/2/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/3/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/3/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/4/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/5/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
2/8/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/24/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Reinf. Concrete
|
2/25/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
2/25/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
3/8/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/8/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
3/9/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/1/2021
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/5/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
4/7/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/21/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Shotcrete
|
4/22/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/22/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/5/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/5/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/6/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/7/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
5/17/2021
|
Conditional Approval
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/1/2021
|
Partial Approval
|
JUAN VALENZUELA
|
|
Deputy Reinf. Concrete
|
6/2/2021
|
Conditional Approval
|
MATT KELLERMAN
|
|
Deputy Steel/Welding
|
6/2/2021
|
Conditional Approval
|
MATT KELLERMAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/18/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
6/24/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/6/2021
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Pre-Inspection
|
7/6/2021
|
Partial Inspection
|
AMY COLIN
|
|
Excavation/Setback/Form/Re-Bar
|
7/7/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/30/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Deputy Wood Construction
|
8/2/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/3/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
8/20/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/13/2021
|
Partial Approval
|
MATT KELLERMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/13/2021
|
Not Ready for Inspection
|
MATT KELLERMAN
|
|
Deputy Reinf. Concrete
|
9/14/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/17/2021
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/17/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
9/20/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/20/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/21/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
9/30/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
10/4/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/5/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/6/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/21/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
10/26/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
10/29/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
10/29/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
11/3/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/12/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/16/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
11/30/2021
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
11/30/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/2/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/10/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/17/2021
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/10/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/11/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
1/12/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
1/19/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/4/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
2/7/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
2/11/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
PLUMBING-Rough
|
2/11/2022
|
Partial Approval
|
BRENDAN LOONEY
|
|
Deputy Reinf. Concrete
|
2/15/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
3/29/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
3/31/2022
|
Approved
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
4/27/2022
|
Approved
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
4/27/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
4/28/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/2/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Underground Mechanical
|
5/13/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
5/17/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
5/17/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
7/26/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
7/27/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
8/11/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Deputy Wood Construction
|
8/11/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
8/11/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
8/11/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
8/11/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
8/11/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/15/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
8/15/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/18/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/18/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Reinf. Concrete
|
8/19/2022
|
Conditional Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/22/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
8/22/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/24/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
8/24/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
8/26/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
8/29/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
8/31/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
9/2/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
9/2/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Rough
|
9/6/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
9/9/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Rough
|
9/21/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
9/21/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
PLUMBING-Rough
|
10/6/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Verify Sprinkler Sign Off
|
10/6/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
10/13/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
10/17/2022
|
Not Ready for Inspection
|
GERMAN RODRIGUEZ MENDOZA
|
|
Green Building Rough
|
10/17/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Interior/Exterior Lathing
|
10/17/2022
|
Partial Approval
|
GERMAN RODRIGUEZ MENDOZA
|
|
Wood Frame
|
10/20/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
10/24/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
10/24/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/1/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Wood Frame
|
11/3/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
BUILDING-Rough-Frame
|
11/7/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Rough
|
11/7/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Insulation
|
11/15/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Insulation
|
11/28/2022
|
Approved
|
DANIEL ORRANTE
|
|
Insulation
|
12/13/2022
|
Approved
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
12/29/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
1/6/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
2/3/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
2/3/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
2/9/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Interior/Exterior Lathing
|
2/9/2023
|
Partial Approval
|
CARLOS MATAMOROS
|
|
Shower Pan
|
2/23/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/1/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
3/1/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/9/2023
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Interior/Exterior Lathing
|
3/13/2023
|
Partial Approval
|
JESUS PINEDA
|
|
Interior/Exterior Lathing
|
5/17/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Shower Pan
|
5/17/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/22/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
8/30/2023
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Service/Power Release
|
9/1/2023
|
Approved
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
1/8/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
1/12/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
HVAC-Final
|
1/12/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
1/23/2024
|
Partial Approval
|
BRENDAN LOONEY
|
|
Gas Test
|
1/24/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
1/24/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
SGSOV-Seismic Gas S/O Valve
|
1/24/2024
|
SGSOV Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
2/12/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
PLUMBING-Final
|
2/20/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
ELECTRICAL-Final
|
3/14/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Sewer
|
3/19/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Drywall Nailing
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
3/29/2024
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Green Building Final
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Reinforced Concrete Frame
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Smoke Detectors
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Structural Steel Frame
|
3/29/2024
|
Approved
|
CHRISTOPHER WILSON
|
|
Final
|
4/3/2024
|
OK to Issue CofO
|
CHRISTOPHER WILSON
|