538 E VERNON AVE 90291

Certificate Information: 538 E VERNON AVE 90291

Application / Permit
19010-30000-00455
Plan Check / Job No.
B19WL00526
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3 STORY TYPE VB SINGLE FAMILY DWELLING WITH ATTACHED GARAGE, EQUIPPED THROUGHOUT WTIH NFPA 13D FIRE SPRINKLERS.
Permit Issued
Issued on 1/28/2020
Issuing Office
West Los Angeles
Current Status
CofO Issued on 2/1/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/31/2019 APPLICANT
Assigned to Plan Check Engineer 2/21/2019 SERGIO SILVA
Corrections Issued 2/28/2019 SERGIO SILVA
Quality Review Completed 3/7/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 3/8/2019 APPLICANT
Applicant returned to address corrections 4/24/2019 SERGIO SILVA
Applicant returned to address corrections 5/6/2019 SERGIO SILVA
Plan Check Approved 5/24/2019 SERGIO SILVA
Issued 1/28/2020 LADBS
CofO in Progress 1/25/2024 HERBERT GIRON
Permit Finaled 2/1/2024 DANIEL ORRANTE
CofO Issued 2/1/2024 DANIEL ORRANTE
Permit Finaled 2/1/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 4/30/2019 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 4/30/2019 DENNIS BRAGIN
Housing rent stabilization Cleared 4/30/2019 STEVEN HOFSTAD
Low Impact Development Cleared 4/30/2019 ANDRES COVARRUBIAS
Miscellaneous Cleared 4/30/2019 NOAH MCCOY
Miscellaneous Cleared 4/30/2019 NOAH MCCOY
Permit Cleared 4/30/2019 DENNIS BRAGIN
Roof/Waste drainage to street Cleared 4/30/2019 DENNIS BRAGIN
Sewer availability Cleared 4/30/2019 DENNIS BRAGIN
Specific Plan Cleared 4/30/2019 CLIVE GRAWE
Green Code Cleared 5/15/2019 RICHARD GARCIA
Trees in Parkway Cleared 5/20/2019 JOHN KIM
Coastal Zone Cleared 5/23/2019 BLAYNE SUTTON-WILLS
Miscellaneous Cleared 5/23/2019 BLAYNE SUTTON-WILLS
Specific Plan Cleared 5/23/2019 BLAYNE SUTTON-WILLS

Contact Information

Contractor Blair Construction Inc; Lic. No.: 529043-B 3014 STEINER AVENUE      SANTA MONICA, CA 90405
Engineer Chiang,, Eric Kam-Leung; Lic. No.: L6671 301 W OAKMONT DR      MONTEBELLO, CA 90640
Engineer Hollingsworth,, Robert Alan; Lic. No.: GE2022 31129 VIA COLINAS SUITE 707      WESTLAKE VILLAGE, CA 91362
Engineer Lau,, David Harkwong; Lic. No.: C34961 12467 W WASHINGTON BLVD      LOS ANGELES, CA 90066

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/22/2020 Not Ready for Inspection DAVID HEINE
METHANE-Barrier 5/22/2020 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 5/22/2020 Not Ready for Inspection DAVID HEINE
Sewer 5/22/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 8/25/2020 Corrections Issued DAVID HEINE
METHANE-Barrier 8/25/2020 Not Ready for Inspection DAVID HEINE
METHANE-Subgrade 8/25/2020 Not Ready for Inspection DAVID HEINE
PLUMBING-Rough 9/22/2020 Partial Approval DAVID HEINE
Footing/Foundation/Slab 9/25/2020 Approved DAVID HEINE
METHANE-Barrier 9/25/2020 Approved DAVID HEINE
METHANE-Subgrade 9/25/2020 Approved DAVID HEINE
Deputy Steel/Welding 10/15/2020 Partial Approval DAVID HEINE
Floor/Roof Diaphrgm/Shear Wall 11/18/2020 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 1/12/2021 Partial Approval JUAN VALENZUELA
Floor/Roof Diaphrgm/Shear Wall 12/9/2021 Not Ready for Inspection DAVID FEILER
Rough-Elec/Plmb/HVAC 12/9/2021 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 12/10/2021 Corrections Issued ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/10/2021 Approved ENRIQUE MIRELES
Floor/Roof Diaphrgm/Shear Wall 1/5/2022 Corrections Issued EVAN COOPER
HVAC-Rough 1/5/2022 Corrections Issued EVAN COOPER
HVAC-Rough 2/11/2022 Approved DAVID FEILER
Verify Sprinkler Sign Off 2/11/2022 Approved DAVID FEILER
Wood Frame 2/11/2022 Partial Approval DAVID FEILER
BUILDING-Rough-Frame 3/16/2022 Approved DAVID FEILER
Green Building Rough 3/16/2022 Approved DAVID FEILER
Insulation 3/16/2022 Approved DAVID FEILER
Interior/Exterior Lathing 3/16/2022 Partial Approval DAVID FEILER
Drywall Nailing 3/23/2022 Approved RYAN SALAZAR
Interior/Exterior Lathing 6/2/2022 Approved JESUS RODRIGUEZ
Shower Pan 6/2/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 3/2/2023 Approved EVAN COOPER
Green Building Final 11/21/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 11/21/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/21/2023 SGSOV Not Ready HERBERT GIRON
Service/Power Release 11/21/2023 Not Ready for Inspection HERBERT GIRON
Smoke Detectors 11/21/2023 Approved HERBERT GIRON
Gas Test 12/1/2023 Approved HERBERT GIRON
PLUMBING-Final 12/1/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 12/1/2023 SGSOV Approved HERBERT GIRON
HVAC-Final 12/7/2023 Corrections Issued HERBERT GIRON
Final 1/24/2024 OK to Issue CofO HERBERT GIRON
Green Building Final 1/24/2024 Approved HERBERT GIRON
Service/Power Release 1/24/2024 Approved HERBERT GIRON
Structural Steel Frame 1/24/2024 Approved HERBERT GIRON