Deputy Reinf. Concrete
|
3/3/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
3/3/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
3/10/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
3/11/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
3/14/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
3/14/2022
|
Partial Approval
|
JAMES POWERS
|
|
Pre-Inspection
|
3/29/2022
|
Partial Inspection
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
4/9/2022
|
Off-Hour Fees Due
|
|
|
Excavation/Setback/Form/Re-Bar
|
4/9/2022
|
Partial Approval
|
RAFAEL ESPINOZA
|
|
Excavation/Setback/Form/Re-Bar
|
4/11/2022
|
Approved
|
JAMES POWERS
|
|
Reinforced Masonry Frame
|
4/25/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
4/28/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
4/28/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
6/1/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/1/2022
|
Partial Approval
|
JAMES POWERS
|
|
Reinforced Concrete Frame
|
6/1/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Deputy Other (see comments)
|
6/3/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/3/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Deputy Reinf. Concrete
|
6/6/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
6/8/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
6/13/2022
|
Partial Approval
|
JAMES POWERS
|
|
Deputy Reinf. Concrete
|
7/1/2022
|
Conditional Approval
|
ERNESTO CORRAL
|
|
Reinforced Concrete Frame
|
7/5/2022
|
Partial Approval
|
JAMES POWERS
|
|
Excavation/Setback/Form/Re-Bar
|
7/8/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/29/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/9/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/24/2022
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
9/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/8/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Green Building Rough
|
9/13/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Insulation
|
9/13/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Verify Sprinkler Sign Off
|
9/13/2022
|
Not Ready for Inspection
|
NICK DANERI
|
|
Wood Frame
|
9/13/2022
|
Partial Approval
|
NICK DANERI
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/16/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/16/2022
|
Off-Hour Fees Due
|
|
|
Insulation
|
9/16/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
9/16/2022
|
Off-Hour Fees Due
|
|
|
Green Building Rough
|
9/20/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
9/20/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
9/20/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/23/2022
|
Partial Approval
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/5/2022
|
Partial Approval
|
JAMES POWERS
|
|
Green Building Rough
|
10/5/2022
|
Approved
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
10/5/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
10/5/2022
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
10/15/2022
|
Partial Approval
|
KATY RAMIREZ
|
|
Verify Sprinkler Sign Off
|
10/26/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wood Frame
|
10/26/2022
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Wall Anchors
|
10/27/2022
|
Partial Approval
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/7/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
11/7/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Interior/Exterior Lathing
|
11/10/2022
|
Approved
|
JAMES POWERS
|
|
Insulation
|
11/15/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/21/2022
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
1/12/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
1/12/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
1/12/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Pre-Inspection
|
1/27/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Special/Order Compliance
|
1/27/2023
|
Partial Approval
|
JAMES POWERS
|
|
Insulation
|
2/25/2023
|
Off-Hour Fees Due
|
|
|
Verify Sprinkler Sign Off
|
2/25/2023
|
Off-Hour Fees Due
|
|
|
Wood Frame
|
2/25/2023
|
Off-Hour Fees Due
|
|
|
Insulation
|
2/28/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
2/28/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
2/28/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
3/2/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
3/2/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
3/2/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
3/23/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
3/28/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
4/17/2023
|
Partial Approval
|
GREGORY POMISH
|
|
Insulation
|
4/17/2023
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Insulation
|
4/21/2023
|
Partial Approval
|
LARRY ARNICK
|
|
Insulation
|
4/27/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Drywall Nailing
|
5/4/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/5/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
5/9/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
5/23/2023
|
Partial Approval
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
5/23/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
5/23/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Verify Sprinkler Sign Off
|
6/7/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Wood Frame
|
6/7/2023
|
Partial Approval
|
JAMES POWERS
|
|
Wall Anchors
|
6/9/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Drywall Nailing
|
8/28/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Insulation
|
8/28/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
9/14/2023
|
Not Ready for Inspection
|
LARRY ARNICK
|
|
Drywall Nailing
|
9/14/2023
|
Partial Approval
|
JAMES POWERS
|
|
Drywall Nailing
|
12/21/2023
|
Not Ready for Inspection
|
JAMES POWERS
|
|
Special/Order Compliance
|
10/18/2024
|
Partial Approval
|
JAMES POWERS
|
|
Special/Order Compliance
|
5/12/2026
|
Partial Approval
|
JAMES POWERS
|
|
Special/Order Compliance
|
7/9/2026
|
Partial Approval
|
JAMES POWERS
|