15033 W HARTLAND ST 91405
Certificate Information: 15033 W HARTLAND ST 91405
- Application / Permit
- 19010-30000-00164
- Plan Check / Job No.
- B19WL00213
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 3/6/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/3/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | LAMAR DAVIS |
| Corrections Issued | 1/28/2019 | LAMAR DAVIS |
| Green Plans Picked Up | 2/5/2019 | APPLICANT |
| Quality Review Completed | 2/7/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/8/2019 | APPLICANT |
| Plan Check Approved | 3/6/2019 | LAMAR DAVIS |
| Issued | 3/6/2019 | LADBS |
| CofO in Progress | 3/4/2020 | MISAEL ESPARZA |
| Permit Finaled | 4/3/2020 | MICHAEL SMITH |
| CofO Issued | 4/3/2020 | MICHAEL SMITH |
| Permit Finaled | 4/3/2020 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 2/12/2019 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 2/15/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/15/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/15/2019 | ELAINE LEI |
| Sewer availability | Cleared | 2/15/2019 | ELAINE LEI |
| Green Code | Cleared | 2/20/2019 | RICHARD GARCIA |
| Miscellaneous | Cleared | 2/28/2019 | LAMAR DAVIS |
Contact Information
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/2/2019 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 4/2/2019 | Approved | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2019 | No Access for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 5/24/2019 | No Access for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/24/2019 | No Access for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 5/31/2019 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2019 | Not Ready for Inspection | ARAM AVEDISIAN |
| Underground Mechanical | 10/15/2019 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 10/17/2019 | Conditional Approval | ARAM AVEDISIAN |
| Gas Test | 10/24/2019 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/24/2019 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/28/2019 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| HVAC-Rough | 10/28/2019 | Partial Inspection | GERMAN RODRIGUEZ MENDOZA |
| BUILDING-Rough-Frame | 11/1/2019 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Rough | 11/1/2019 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Green Building Rough | 11/1/2019 | Corrections Issued | OGANES TARAKHCHYAN |
| HVAC-Rough | 11/1/2019 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Verify Sprinkler Sign Off | 11/1/2019 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Wood Frame | 11/1/2019 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 11/7/2019 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 11/7/2019 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/7/2019 | Not Ready for Inspection | ARAM AVEDISIAN |
| HVAC-Rough | 11/7/2019 | Not Ready for Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 11/7/2019 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 11/14/2019 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 11/14/2019 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 11/14/2019 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/19/2019 | Partial Approval | ARAM AVEDISIAN |
| Drywall Nailing | 11/22/2019 | Approved | JENNIFER RABUCHIN |
| Interior/Exterior Lathing | 12/20/2019 | Corrections Issued | ROBERT MINASSIANS |
| Interior/Exterior Lathing | 12/23/2019 | Corrections Issued | ROBERT MINASSIANS |
| Interior/Exterior Lathing | 12/26/2019 | Approved | JENNIFER RABUCHIN |
| Final | 2/3/2020 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 2/3/2020 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 2/3/2020 | Approved | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 2/3/2020 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 2/3/2020 | Approved | JENNIFER RABUCHIN |
| Final | 2/10/2020 | Partial Approval | MISAEL ESPARZA |
| Final | 2/19/2020 | Partial Approval | MISAEL ESPARZA |