7105 N NATICK AVE 91405
Certificate Information: 7105 N NATICK AVE 91405
- Application / Permit
- 19010-30000-00162
- Plan Check / Job No.
- B19WL00212
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) ACCESSORY DWELLING UNIT PER AB 494 & SB 229
- Permit Issued
- Issued on 3/6/2019
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 2/10/2020
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/15/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/24/2019 | LAMAR DAVIS |
| Corrections Issued | 1/28/2019 | LAMAR DAVIS |
| Green Plans Picked Up | 2/5/2019 | APPLICANT |
| Quality Review Completed | 2/7/2019 | KAMRAN GHOTBI RAVANDI |
| Building Plans Picked Up | 2/8/2019 | APPLICANT |
| Applicant returned to address corrections | 2/28/2019 | LAMAR DAVIS |
| Plan Check Approved | 3/6/2019 | LAMAR DAVIS |
| Issued | 3/6/2019 | LADBS |
| CofO in Progress | 1/14/2020 | ARAM AVEDISIAN |
| Permit Finaled | 2/10/2020 | DANIEL ORRANTE |
| CofO Issued | 2/10/2020 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 2/12/2019 | HISASHI KOBAYAKAWA |
| Eng Process Fee Ord 176,300 | Cleared | 2/15/2019 | ELAINE LEI |
| Hydrant and Access approval | Cleared | 2/15/2019 | GEORGE SUCHAND |
| Low Impact Development | Cleared | 2/15/2019 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 2/15/2019 | ELAINE LEI |
| Sewer availability | Cleared | 2/15/2019 | ELAINE LEI |
| Green Code | Cleared | 2/20/2019 | RICHARD GARCIA |
| Miscellaneous | Cleared | 2/28/2019 | LAMAR DAVIS |
Contact Information
| Engineer | Messiha,, Hany Gamil; Lic. No.: C56766 | 19648 MULBERRY DR WALNUT, CA 91789 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/27/2019 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 3/27/2019 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 4/2/2019 | Not Ready for Inspection | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 5/6/2019 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 5/24/2019 | Approved | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 5/24/2019 | Approved | ARAM AVEDISIAN |
| Sewer | 6/13/2019 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/17/2019 | No Access for Inspection | MARK JOHNSON |
| PLUMBING-Rough | 6/18/2019 | Corrections Issued | ARAM AVEDISIAN |
| Sewer | 6/18/2019 | Not Ready for Inspection | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/20/2019 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 9/11/2019 | Corrections Issued | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/16/2019 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 10/16/2019 | Approved | ARAM AVEDISIAN |
| Green Building Rough | 10/16/2019 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 10/16/2019 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 10/16/2019 | Approved | ARAM AVEDISIAN |
| Verify Sprinkler Sign Off | 10/16/2019 | Approved | ARAM AVEDISIAN |
| Deputy Wood Construction | 10/18/2019 | No Access for Inspection | MICHEL ABAJAN |
| Drywall Nailing | 10/23/2019 | Approved | CHRISTOPHER DELLEFIELD |
| Underground Mechanical | 10/28/2019 | Partial Approval | GERMAN RODRIGUEZ MENDOZA |
| Interior/Exterior Lathing | 11/8/2019 | Partial Approval | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 11/14/2019 | Approved | HENRY KIM |
| Final | 1/9/2020 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 1/9/2020 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 1/9/2020 | SGSOV Approved | ARAM AVEDISIAN |
| Service/Power Release | 1/9/2020 | Not Required | ARAM AVEDISIAN |
| Smoke Detectors | 1/9/2020 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 1/13/2020 | Approved | ARAM AVEDISIAN |
| Final | 1/13/2020 | OK to Issue CofO | ARAM AVEDISIAN |
| Special/Order Compliance | 1/15/2020 | Approved | ARAM AVEDISIAN |