10462 W ILONA AVE 90064

Certificate Information: 10462 W ILONA AVE 90064

Application / Permit
19010-30000-00153
Plan Check / Job No.
B19WL00199
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2 story single family with basement and attached 2-car garage
Permit Issued
Issued on 3/21/2019
Issuing Office
West Los Angeles
Current Status
CofO Issued on 11/17/2020
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/15/2019 APPLICANT
Green Plans Picked Up 1/24/2019 APPLICANT
Assigned to Plan Check Engineer 1/31/2019 TARIK SAOUD
Corrections Issued 2/4/2019 TARIK SAOUD
Quality Review Completed 2/14/2019 KAMRAN GHOTBI RAVANDI
Building Plans Picked Up 2/14/2019 APPLICANT
Applicant returned to address corrections 3/15/2019 SERGIO SILVA
Plan Check Approved 3/19/2019 SERGIO SILVA
Issued 3/21/2019 LADBS
CofO in Progress 11/4/2020 GERMAN RODRIGUEZ MENDOZA
CofO Issued 11/17/2020 VINCENT COTTON
Permit Finaled 11/17/2020 VINCENT COTTON

Permit Application Clearance Information

Trees in Parkway Cleared 2/6/2019 ADRIAN SANCHEZ
Address approval Cleared 2/26/2019 APEKSHYA BAJRACHARYA
Eng Process Fee Ord 176,300 Cleared 2/26/2019 APEKSHYA BAJRACHARYA
Hydrant and Access approval Cleared 2/26/2019 JOHN DALLAS
Low Impact Development Cleared 2/26/2019 ANDRES COVARRUBIAS
Permit Cleared 2/26/2019 APEKSHYA BAJRACHARYA
Roof/Waste drainage to street Cleared 2/26/2019 APEKSHYA BAJRACHARYA
Sewer availability Cleared 2/26/2019 APEKSHYA BAJRACHARYA
Green Code Cleared 2/28/2019 DONALD CRICHLOW
Excavation more than 5-ft deep Cleared 3/15/2019 CALOSHA APPROVED
Grading Pre-Inspection Cleared 3/15/2019 TARIK SAOUD
Miscellaneous Cleared 3/15/2019 TARIK SAOUD

Contact Information

Contractor Drexel Construction Management Llc; Lic. No.: 1014160-B 6380 WILSHIRE BLVD #1018      LOS ANGELES, CA 90048

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/20/2019 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 5/20/2019 Partial Approval CARLOS MATAMOROS
METHANE-Barrier 5/20/2019 Not Ready for Inspection CARLOS MATAMOROS
METHANE-Subgrade 5/20/2019 Not Ready for Inspection CARLOS MATAMOROS
Excavation/Setback/Form/Re-Bar 6/7/2019 Partial Approval MICHAEL TEMPLE
Footing/Foundation/Slab 6/7/2019 Partial Approval MICHAEL TEMPLE
METHANE-Barrier 6/7/2019 Not Ready for Inspection MICHAEL TEMPLE
METHANE-Subgrade 6/7/2019 Not Ready for Inspection MICHAEL TEMPLE
Underground Mechanical 6/20/2019 Not Ready for Inspection CARLOS MATAMOROS
Underground Mechanical 6/21/2019 Approved CARLOS MATAMOROS
METHANE-Barrier 6/25/2019 Approved CRAIG DAVIS
METHANE-Rough 7/3/2019 Approved CARLOS MATAMOROS
METHANE-Subgrade 7/3/2019 Approved CARLOS MATAMOROS
Footing/Foundation/Slab 7/16/2019 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 7/22/2019 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 8/8/2019 Conditional Approval CARLOS MATAMOROS
Footing/Foundation/Slab 9/17/2019 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
METHANE-Subgrade 9/24/2019 Approved GERMAN RODRIGUEZ MENDOZA
METHANE-Barrier 10/2/2019 Approved GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 10/4/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 10/11/2019 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 11/15/2019 Partial Approval GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 1/3/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Gas Test 1/3/2020 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Rough 1/3/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/3/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/3/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/6/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 1/7/2020 Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 1/7/2020 Approved GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 1/9/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Floor/Roof Diaphrgm/Shear Wall 1/29/2020 Partial Approval GERMAN RODRIGUEZ MENDOZA
Green Building Rough 1/29/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Shower Pan 1/29/2020 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 1/29/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 2/3/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/3/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Sewer 2/3/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 2/3/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Wood Frame 2/3/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 2/5/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Green Building Rough 2/5/2020 Approved GERMAN RODRIGUEZ MENDOZA
Sewer 2/5/2020 Approved GERMAN RODRIGUEZ MENDOZA
Verify Sprinkler Sign Off 2/5/2020 Approved GERMAN RODRIGUEZ MENDOZA
Wood Frame 2/5/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 2/7/2020 Approved GERMAN RODRIGUEZ MENDOZA
Insulation 2/21/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Insulation 2/26/2020 Approved GERMAN RODRIGUEZ MENDOZA
Drywall Nailing 3/5/2020 Approved ANTHONY MCDOWALL
ELECTRICAL-Final 8/7/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 8/19/2020 Approved GERMAN RODRIGUEZ MENDOZA
Gas Test 8/19/2020 Approved GERMAN RODRIGUEZ MENDOZA
HVAC-Final 8/19/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 8/19/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
SGSOV-Seismic Gas S/O Valve 8/19/2020 SGSOV Approved GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 8/28/2020 Approved GERMAN RODRIGUEZ MENDOZA
Final 9/15/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 9/15/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Final 9/15/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Service/Power Release 9/15/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 9/15/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Final 9/18/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 9/18/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Green Building Final 9/18/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Service/Power Release 9/18/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 9/18/2020 No Access for Inspection GERMAN RODRIGUEZ MENDOZA
Final 9/22/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 9/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
Green Building Final 9/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
Service/Power Release 9/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
Smoke Detectors 9/22/2020 Approved GERMAN RODRIGUEZ MENDOZA
Final 9/25/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Service/Power Release 9/25/2020 Partial Inspection GERMAN RODRIGUEZ MENDOZA
Final 10/1/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Final 10/13/2020 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Service/Power Release 10/13/2020 Not Required GERMAN RODRIGUEZ MENDOZA
Final 10/29/2020 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Final 11/4/2020 Conditional Approval GERMAN RODRIGUEZ MENDOZA