4427 E SAN ANDREAS AVE 90065
Certificate Information: 4427 E SAN ANDREAS AVE 90065
- Application / Permit
- 19010-20003-04272
- Plan Check / Job No.
- B24VN02717
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPP. TO PERMIT 19010-20000-04272 TO REVISE THE STRUCTURAL PLANS AND TITEL 24
- Permit Issued
- Issued on 3/1/2024
- Issuing Office
- Metro
- Current Status
- Permit Finaled on 4/16/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 2/29/2024 | SEAN SHAHMIRI |
| Issued | 3/1/2024 | APPLICANT |
| Permit Finaled | 4/15/2025 | ALIZAH MAYAGOITIA |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Alam,, Elsye; Lic. No.: C35910 | 1847 KAWEAH DR. PASADENA, CA 91105 |
| Contractor | Hernz Construction Incorporated; Lic. No.: 581129-B | 8931 WOODMAN AVENUE PACOIMA, CA 91331 |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 3/29/2024 | Partial Approval | OSVALDO PARAMO |
| Structural Steel Frame | 3/29/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2024 | Partial Approval | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/1/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2024 | Corrections Issued | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/3/2024 | Conditional Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Insulation | 6/5/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 6/14/2024 | Conditional Approval | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Approved | OSVALDO PARAMO |
| Deputy Reinf. Concrete | 12/30/2024 | Conditional Approval | THOMAS LOGRASSO |
| Final | 4/15/2025 | Permit Finaled | ALIZAH MAYAGOITIA |