18321 W CLARK ST 91356

Certificate Information: 18321 W CLARK ST 91356

Application / Permit
19010-20003-00310
Plan Check / Job No.
B25LA08931
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(23) Miscellaneous Bldg/Structure
Work Description
EPLAN Supplemental to 19010-10000-00310. Includes revisions per coordination with contractor. (Civil/Grading changes under separate permit)
Permit Issued
Issued on 9/30/2025
Issuing Office
Current Status
Issued on 9/30/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 3/18/2025 APPLICANT
Assigned to Plan Check Engineer 3/20/2025 PRANITA SHAH
Corrections Issued 4/8/2025 PRANITA SHAH
Quality Review Completed 4/23/2025 GARO TELMI
Plan Check Approved 6/10/2025 PRANITA SHAH
Issued 9/30/2025 APPLICANT

Permit Application Clearance Information

DAS Clearance Cleared 5/15/2025 Michael Perez

Contact Information

Architect Wood,, Jack Frederick; Lic. No.: NA15130       ,
Contractor Align Builders Inc; Lic. No.: 989507-B       ,
Engineer Reynolds,, Aaron; Lic. No.: NA4338       ,

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Other (see comments) 1/6/2026 Conditional Approval BRIAN KELLY
Piling/Pier/Caisson 1/7/2026 Partial Inspection BRIAN KELLY
Deputy Other (see comments) 1/8/2026 Conditional Approval BRIAN KELLY
Piling/Pier/Caisson 1/8/2026 Partial Approval BRIAN KELLY
Deputy Reinf. Concrete 1/9/2026 Conditional Approval BRIAN KELLY
Piling/Pier/Caisson 1/9/2026 Partial Inspection BRIAN KELLY
Excavation/Setback/Form/Re-Bar 1/22/2026 Partial Inspection ROBERT DAVIS
Footing/Foundation/Slab 1/22/2026 Not Ready for Inspection ROBERT DAVIS
Excavation/Setback/Form/Re-Bar 1/23/2026 Not Ready for Inspection BRIAN KELLY
Footing/Foundation/Slab 1/23/2026 Not Ready for Inspection BRIAN KELLY
Footing/Foundation/Slab 2/6/2026 Not Ready for Inspection BRIAN KELLY
Deputy Reinf. Concrete 2/10/2026 Conditional Approval BRIAN KELLY
Footing/Foundation/Slab 2/10/2026 Partial Approval BRIAN KELLY
Masonry Wall/Backfill 3/2/2026 Partial Inspection BRIAN KELLY
Deputy Reinf. Masonry 4/15/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Masonry 4/16/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Masonry 4/17/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Masonry 4/22/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Masonry 4/23/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Masonry 4/24/2026 Conditional Approval BRIAN KELLY
Deputy Reinf. Concrete 5/5/2026 Conditional Approval DEANDRE HOFFMAN
Deputy Reinf. Concrete 5/6/2026 Conditional Approval GREGORY POMISH
Deputy Reinf. Concrete 5/7/2026 Conditional Approval JEFFREY DURAN
Deputy Reinf. Concrete 5/7/2026 Conditional Approval SEAN GRIFFITH
Deputy Steel/Welding 5/26/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 5/27/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 5/28/2026 Conditional Approval BRIAN KELLY
Deputy Steel/Welding 5/29/2026 Conditional Approval BRIAN KELLY
Masonry Wall/Backfill 6/4/2026 Partial Approval DEANDRE HOFFMAN