11422 W OXNARD ST 91606
Certificate Information: 11422 W OXNARD ST 91606
- Application / Permit
- 19010-20001-03266
- Plan Check / Job No.
- B21VN02158
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- SUPPLEMENTAL PERMIT TO 19010-20000-03266 FOR 12'-5" X 27'-10" ADDITION AND REMOVE ONE OF THE 2-CAR GARAGE FOR ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e).
- Permit Issued
- Issued on 1/25/2022
- Issuing Office
- Current Status
- Permit Finaled on 12/5/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 2/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 3/18/2021 | SERGIO MUNIZ |
| Corrections Issued | 3/22/2021 | SERGIO MUNIZ |
| Quality Review Completed | 3/24/2021 | OMID HEDAYAT |
| Applicant returned to address corrections | 11/19/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 12/23/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 1/6/2022 | SERGIO MUNIZ |
| Plan Check Approved | 1/19/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| Issued | 1/25/2022 | APPLICANT |
| Permit Finaled | 12/5/2023 | JOHN COLEMAN |
Permit Application Clearance Information
| Address approval | Cleared | 5/6/2021 | LEE GUILBEAUX |
| "Q" conditions | Cleared | 5/10/2021 | ANACANY HURTADO |
| Sewer availability | Cleared | 5/11/2021 | LEE GUILBEAUX |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 11/8/2021 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 11/15/2021 | WALLIE JONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Yenjai,, Seree; Lic. No.: C73151 | 3249 SHADYLAWN DRIVE DUARTE, CA 91010 |
Inspector Information
| JAVIER RAMOS JR, (818) 374-1163 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 2/24/2022 | Partial Approval | CALEB MEISTER |
| Deputy Drilled-In Anchors | 3/1/2022 | Partial Approval | MATT KELLERMAN |
| Footing/Foundation/Slab | 3/3/2022 | Approved | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/13/2022 | Partial Approval | MATT KELLERMAN |
| Green Building Rough | 4/13/2022 | Partial Approval | MATT KELLERMAN |
| ELECTRICAL-Rough | 5/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| HVAC-Rough | 5/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| PLUMBING-Rough | 5/18/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Shower Pan | 5/31/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/6/2022 | Conditional Approval | THOMAS FINNILA |
| ELECTRICAL-Rough | 6/6/2022 | Approved | THOMAS FINNILA |
| HVAC-Rough | 6/6/2022 | Corrections Issued | THOMAS FINNILA |
| PLUMBING-Rough | 6/6/2022 | Approved | THOMAS FINNILA |
| BUILDING-Rough-Frame | 7/29/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Green Building Rough | 7/29/2022 | No Access for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 7/29/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Insulation | 7/29/2022 | No Access for Inspection | JAVIER RAMOS JR |
| Insulation | 8/4/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Rough-Elec/Plmb/HVAC | 8/4/2022 | Corrections Issued | THOMAS FINNILA |
| BUILDING-Rough-Frame | 8/11/2022 | Not Ready for Inspection | CALEB MEISTER |
| Green Building Rough | 8/11/2022 | Approved | CALEB MEISTER |
| Insulation | 8/11/2022 | Not Ready for Inspection | CALEB MEISTER |
| Rough-Elec/Plmb/HVAC | 8/11/2022 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 8/26/2022 | Approved | CALEB MEISTER |
| Drywall Nailing | 8/26/2022 | Approved | CALEB MEISTER |
| Insulation | 8/26/2022 | Approved | CALEB MEISTER |