8737 N BALBOA BLVD 91325

Certificate Information: 8737 N BALBOA BLVD 91325

Application / Permit
19010-20001-01237
Plan Check / Job No.
B20VN02139
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
SUPPLEMENTAL TO 19010-20000-01237 TO REVISE THE ACCESSORY LIVING QUARTERS DIMMENSIONS FROM 31' X 31'10" TO 33'11" X 59'10" AND FROM 2 STORY TO 1 STORY AND ADD A NEW ATTACHED 41'4" X 33'6" ACCESSORY DWELLING UNIT , NFPA-13D FIRE SPRINKLERS THROUGHOUT , ALL WORK PER ENGINEERING
Permit Issued
Issued on 8/21/2020
Issuing Office
Valley
Current Status
Permit Finaled on 9/21/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 7/28/2020 APPLICANT
Assigned to Plan Check Engineer 8/4/2020 RARES BODEA
Plan Check Approved 8/5/2020 RARES BODEA
Issued 8/21/2020 APPLICANT
Permit Finaled 9/21/2021 MARK JOHNSON

Permit Application Clearance Information

Low Impact Development Cleared 6/8/2020 SARAH YOUSSEF
Eng Process Fee Ord 176,300 Cleared 6/24/2020 ADRIAN CASTRO
Sewer availability Cleared 6/24/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHER ROJAS, (818) 374-1160 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/26/2020 Approved HENRY KIM
PLUMBING-Rough 10/8/2020 Partial Approval MARK JOHNSON
Underground Mechanical 10/8/2020 Partial Approval MARK JOHNSON
PLUMBING-Rough 10/13/2020 Partial Approval MARK JOHNSON
Special/Order Compliance 12/15/2020 Approved MARK JOHNSON
BUILDING-Rough-Frame 1/8/2021 Corrections Issued MARK JOHNSON
ELECTRICAL-Rough 1/8/2021 Approved MARK JOHNSON
Green Building Rough 1/8/2021 Not Ready for Inspection MARK JOHNSON
HVAC-Rough 1/8/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 1/8/2021 Approved MARK JOHNSON
PLUMBING-Rough 1/8/2021 Corrections Issued MARK JOHNSON
PLUMBING-Rough 1/12/2021 Approved MARK JOHNSON
BUILDING-Rough-Frame 1/29/2021 Approved MARK JOHNSON
Green Building Rough 1/29/2021 Approved MARK JOHNSON
MERV13>=Rough 1/29/2021 Approved MARK JOHNSON
Special/Order Compliance 1/29/2021 Approved MARK JOHNSON
Shower Pan 2/19/2021 Approved MARK JOHNSON
Interior/Exterior Lathing 3/1/2021 Approved MARK JOHNSON
Final 9/3/2021 Corrections Issued MARK JOHNSON
Footing/Foundation/Slab 9/3/2021 Approved MARK JOHNSON
Green Building Final 9/3/2021 Approved MARK JOHNSON
Smoke Detectors 9/3/2021 Approved MARK JOHNSON
Final 9/20/2021 Corrections Issued MARK JOHNSON