11274 W TABOR ST 90066

Certificate Information: 11274 W TABOR ST 90066

Application / Permit
19010-20000-06540
Plan Check / Job No.
B19VN22795
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
REMOVE (E) TWO OPEN PARKING STALLS AND ADD NEW 20'-6" x 29'-0" DETACHED 2-STORY ACCESSORY DWELLING UNIT WITH ROOF TOP DECK PER GCS 65852.2(e)(1)(A)
Permit Issued
Issued on 12/9/2022
Issuing Office
Metro
Current Status
CofO Issued on 2/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 ALYSSA N NARCISO
Corrections Issued 2/19/2020 ALYSSA N NARCISO
Quality Review Completed 2/20/2020 CHON CHIO KUO
Building Plans Picked Up 2/24/2020 APPLICANT
Applicant returned to address corrections 4/23/2020 ALYSSA N NARCISO
Green Plans Picked Up 7/1/2020 APPLICANT
Applicant returned to address corrections 9/28/2020 SEAN SHAHMIRI
Applicant returned to address corrections 10/14/2020 SEAN SHAHMIRI
Plan Check Approved 10/14/2020 SEAN SHAHMIRI
Issued 12/9/2022 APPLICANT
CofO in Progress 1/30/2025 EVAN COOPER
CofO Issued 2/12/2025 RICHARD STEINBACH
Permit Finaled 2/12/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 2/28/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 2/28/2020 ADRIAN CASTRO
Grading Pre-Inspection Cleared 2/28/2020 BARTON HOLMES
Permit Cleared 2/28/2020 ADRIAN CASTRO
Sewer availability Cleared 3/2/2020 CATHERINE ADROVER
Hydrant and Access approval Cleared 3/4/2020 GEORGE SUCHAND
Trees in Parkway Cleared 5/20/2020 JOHN KIM
Green Code Cleared 6/30/2020 COLIN LOREDO
Low Impact Development Cleared 9/3/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 9/22/2020 DINAH GARIN
Miscellaneous Cleared 10/6/2020 VALERIA CEJA

Contact Information

Contractor Owner-Builder       ,
Engineer Erdelyi,, Peter Tibor; Lic. No.: C26962 1950 SAWTELLE BLVD STE 175      LOS ANGELES, CA 90025

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/27/2023 Partial Inspection JESUS PINEDA
PLUMBING-Rough 12/1/2023 Approved TEMISTOCLES CAAL
Footing/Foundation/Slab 12/5/2023 Approved JESUS PINEDA
Deputy Wood Construction 12/19/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 12/21/2023 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 1/18/2024 Corrections Issued MEL KHACHATOURIAN
Floor/Roof Diaphrgm/Shear Wall 1/24/2024 Partial Approval JESUS PINEDA
Special/Order Compliance 1/24/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 3/15/2024 Approved JESUS PINEDA
Green Building Rough 3/15/2024 Approved JESUS PINEDA
HVAC-Rough 3/15/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 3/15/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 3/15/2024 Corrections Issued JESUS PINEDA
BUILDING-Rough-Frame 3/18/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 3/18/2024 Approved JESUS PINEDA
MERV13>=Rough 3/18/2024 Approved JESUS PINEDA
PLUMBING-Rough 3/18/2024 Approved JESUS PINEDA
Insulation 3/27/2024 Corrections Issued JESUS PINEDA
Drywall Nailing 4/3/2024 Partial Approval TEMISTOCLES CAAL
Special/Order Compliance 4/3/2024 Corrections Issued TEMISTOCLES CAAL
Drywall Nailing 4/8/2024 Approved JESUS PINEDA
Insulation 4/8/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 4/16/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 9/11/2024 Corrections Issued DANIEL VERA
Final 9/11/2024 Corrections Issued DANIEL VERA
HVAC-Final 9/11/2024 Corrections Issued DANIEL VERA
PLUMBING-Final 9/11/2024 Corrections Issued DANIEL VERA
Final 10/1/2024 Not Ready for Inspection DANIEL VERA
Green Building Final 10/1/2024 Not Ready for Inspection DANIEL VERA
HVAC-Final 10/1/2024 Corrections Issued DANIEL VERA
MERV13>=Final 10/1/2024 Approved DANIEL VERA
SGSOV-Seismic Gas S/O Valve 10/1/2024 SGSOV Approved DANIEL VERA
Service/Power Release 10/1/2024 Not Ready for Inspection DANIEL VERA
Smoke Detectors 10/1/2024 Approved DANIEL VERA
HVAC-Final 10/7/2024 Not Ready for Inspection DANIEL VERA
Final 11/26/2024 Not Ready for Inspection DANIEL VERA
Green Building Final 11/26/2024 Not Ready for Inspection DANIEL VERA
Service/Power Release 11/26/2024 Not Ready for Inspection DANIEL VERA
Final 12/12/2024 Corrections Issued DANIEL VERA
Green Building Final 12/12/2024 Approved DANIEL VERA
Service/Power Release 12/12/2024 Not Ready for Inspection DANIEL VERA
Final 1/23/2025 No Access for Inspection ARAM AVEDISIAN
Service/Power Release 1/23/2025 No Access for Inspection ARAM AVEDISIAN
Final 1/30/2025 OK to Issue CofO EVAN COOPER
Service/Power Release 1/30/2025 Approved EVAN COOPER