11274 W TABOR ST 90066
Certificate Information: 11274 W TABOR ST 90066
- Application / Permit
- 19010-20000-06540
- Plan Check / Job No.
- B19VN22795
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- REMOVE (E) TWO OPEN PARKING STALLS AND ADD NEW 20'-6" x 29'-0" DETACHED 2-STORY ACCESSORY DWELLING UNIT WITH ROOF TOP DECK PER GCS 65852.2(e)(1)(A)
- Permit Issued
- Issued on 12/9/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 2/12/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | ALYSSA N NARCISO |
| Corrections Issued | 2/19/2020 | ALYSSA N NARCISO |
| Quality Review Completed | 2/20/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 2/24/2020 | APPLICANT |
| Applicant returned to address corrections | 4/23/2020 | ALYSSA N NARCISO |
| Green Plans Picked Up | 7/1/2020 | APPLICANT |
| Applicant returned to address corrections | 9/28/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 10/14/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 10/14/2020 | SEAN SHAHMIRI |
| Issued | 12/9/2022 | APPLICANT |
| CofO in Progress | 1/30/2025 | EVAN COOPER |
| CofO Issued | 2/12/2025 | RICHARD STEINBACH |
| Permit Finaled | 2/12/2025 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 2/28/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/28/2020 | ADRIAN CASTRO |
| Grading Pre-Inspection | Cleared | 2/28/2020 | BARTON HOLMES |
| Permit | Cleared | 2/28/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 3/2/2020 | CATHERINE ADROVER |
| Hydrant and Access approval | Cleared | 3/4/2020 | GEORGE SUCHAND |
| Trees in Parkway | Cleared | 5/20/2020 | JOHN KIM |
| Green Code | Cleared | 6/30/2020 | COLIN LOREDO |
| Low Impact Development | Cleared | 9/3/2020 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 9/22/2020 | DINAH GARIN |
| Miscellaneous | Cleared | 10/6/2020 | VALERIA CEJA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 1950 SAWTELLE BLVD STE 175 LOS ANGELES, CA 90025 |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/27/2023 | Partial Inspection | JESUS PINEDA |
| PLUMBING-Rough | 12/1/2023 | Approved | TEMISTOCLES CAAL |
| Footing/Foundation/Slab | 12/5/2023 | Approved | JESUS PINEDA |
| Deputy Wood Construction | 12/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2023 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/24/2024 | Partial Approval | JESUS PINEDA |
| Special/Order Compliance | 1/24/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 3/15/2024 | Approved | JESUS PINEDA |
| HVAC-Rough | 3/15/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 3/15/2024 | Partial Approval | JESUS PINEDA |
| PLUMBING-Rough | 3/15/2024 | Corrections Issued | JESUS PINEDA |
| BUILDING-Rough-Frame | 3/18/2024 | Approved | JESUS PINEDA |
| ELECTRICAL-Rough | 3/18/2024 | Approved | JESUS PINEDA |
| MERV13>=Rough | 3/18/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 3/18/2024 | Approved | JESUS PINEDA |
| Insulation | 3/27/2024 | Corrections Issued | JESUS PINEDA |
| Drywall Nailing | 4/3/2024 | Partial Approval | TEMISTOCLES CAAL |
| Special/Order Compliance | 4/3/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Drywall Nailing | 4/8/2024 | Approved | JESUS PINEDA |
| Insulation | 4/8/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 4/16/2024 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 9/11/2024 | Corrections Issued | DANIEL VERA |
| Final | 9/11/2024 | Corrections Issued | DANIEL VERA |
| HVAC-Final | 9/11/2024 | Corrections Issued | DANIEL VERA |
| PLUMBING-Final | 9/11/2024 | Corrections Issued | DANIEL VERA |
| Final | 10/1/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 10/1/2024 | Not Ready for Inspection | DANIEL VERA |
| HVAC-Final | 10/1/2024 | Corrections Issued | DANIEL VERA |
| MERV13>=Final | 10/1/2024 | Approved | DANIEL VERA |
| SGSOV-Seismic Gas S/O Valve | 10/1/2024 | SGSOV Approved | DANIEL VERA |
| Service/Power Release | 10/1/2024 | Not Ready for Inspection | DANIEL VERA |
| Smoke Detectors | 10/1/2024 | Approved | DANIEL VERA |
| HVAC-Final | 10/7/2024 | Not Ready for Inspection | DANIEL VERA |
| Final | 11/26/2024 | Not Ready for Inspection | DANIEL VERA |
| Green Building Final | 11/26/2024 | Not Ready for Inspection | DANIEL VERA |
| Service/Power Release | 11/26/2024 | Not Ready for Inspection | DANIEL VERA |
| Final | 12/12/2024 | Corrections Issued | DANIEL VERA |
| Green Building Final | 12/12/2024 | Approved | DANIEL VERA |
| Service/Power Release | 12/12/2024 | Not Ready for Inspection | DANIEL VERA |
| Final | 1/23/2025 | No Access for Inspection | ARAM AVEDISIAN |
| Service/Power Release | 1/23/2025 | No Access for Inspection | ARAM AVEDISIAN |
| Final | 1/30/2025 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 1/30/2025 | Approved | EVAN COOPER |