12748 W SARAH ST 91604

Certificate Information: 12748 W SARAH ST 91604

Application / Permit
19010-20000-06535
Plan Check / Job No.
B19VN22790
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 38' x 44'-6" TWO-STORY, TYPE VB, SINGLE FAMILY DWELLING W/ ATTACHED GARAGE. AUTOMATIC SPRINKLER SYSTEM IS REQUIRED.
Permit Issued
Issued on 4/30/2020
Issuing Office
Valley
Current Status
CofO Issued on 9/8/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Green Plans Picked Up 2/7/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 SEAN SHAHMIRI
Corrections Issued 2/21/2020 SEAN SHAHMIRI
Quality Review Completed 2/27/2020 OMID HEDAYAT
Building Plans Picked Up 2/27/2020 APPLICANT
Applicant returned to address corrections 4/20/2020 SEAN SHAHMIRI
Plan Check Approved 4/20/2020 SEAN SHAHMIRI
Issued 4/30/2020 LADBS
CofO in Progress 7/1/2021 ARAM AVEDISIAN
Permit Finaled 9/8/2021 MICHAEL SMITH
CofO Issued 9/8/2021 MICHAEL SMITH
Permit Finaled 9/8/2021 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 2/27/2020 MARKOS PEREZ-BRAN
Eng Process Fee Ord 176,300 Cleared 2/27/2020 MARKOS PEREZ-BRAN
Permit Cleared 2/27/2020 MARKOS PEREZ-BRAN
Sewer availability Cleared 2/27/2020 MARKOS PEREZ-BRAN
ZA Case Cleared 2/27/2020 DANG NGUYEN
ZA Case Cleared 2/27/2020 DANG NGUYEN
ZA Case Cleared 2/27/2020 DANG NGUYEN
ZA Case Cleared 2/27/2020 DANG NGUYEN
ZA Case Cleared 2/27/2020 DANG NGUYEN
Hydrant and Access approval Cleared 3/6/2020 GEORGE SUCHAND
Green Code Cleared 3/18/2020 COLIN LOREDO
ZI Cleared 3/19/2020 LAUREN PADICK
Certificate of Compliance Cleared 3/31/2020 LAUREN PADICK
Trees in Parkway Cleared 4/2/2020 JOHN KIM
Low Impact Development Cleared 4/8/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 4/10/2020 ADRIAN CASTRO

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 6/2/2020 Approved ARAM AVEDISIAN
PLUMBING-Rough 6/15/2020 Corrections Issued ARAM AVEDISIAN
BUILDING-Rough-Frame 6/17/2020 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 6/17/2020 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/6/2020 Approved MATTHEW NELSON
Floor/Roof Diaphrgm/Shear Wall 7/27/2020 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 8/17/2020 Partial Approval ARAM AVEDISIAN
Interior/Exterior Lathing 8/24/2020 Partial Approval ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 8/24/2020 Approved ARAM AVEDISIAN
BUILDING-Rough-Frame 9/8/2020 Approved ARAM AVEDISIAN
Green Building Rough 9/8/2020 Approved ARAM AVEDISIAN
Insulation 9/8/2020 Approved ARAM AVEDISIAN
MERV13>=Rough 9/8/2020 Approved ARAM AVEDISIAN
Verify Sprinkler Sign Off 9/8/2020 Approved ARAM AVEDISIAN
Drywall Nailing 9/14/2020 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 9/18/2020 Partial Approval ARAM AVEDISIAN
Shower Pan 9/18/2020 Approved ARAM AVEDISIAN
Special/Order Compliance 10/19/2020 Approved ARAM AVEDISIAN
Sewer 11/12/2020 Approved DANIEL DREW
Underground Mechanical 11/12/2020 Partial Approval DANIEL DREW
Service/Power Release 5/19/2021 Approved ARAM AVEDISIAN
ELECTRICAL-Final 6/29/2021 Approved ARAM AVEDISIAN
Final 6/29/2021 OK to Issue CofO ARAM AVEDISIAN
Green Building Final 6/29/2021 Approved ARAM AVEDISIAN
HVAC-Final 6/29/2021 Approved ARAM AVEDISIAN
MERV13>=Final 6/29/2021 Approved ARAM AVEDISIAN
PLUMBING-Final 6/29/2021 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 6/29/2021 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 6/29/2021 Approved ARAM AVEDISIAN