1623 W FARGO ST 90026

Certificate Information: 1623 W FARGO ST 90026

Application / Permit
19010-20000-06506
Plan Check / Job No.
B19VN22760
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW (65'-0"x 26'-7 3/4") 3 STORY SINGLE FAMILY DWELLING INCL BASEMENT REC RM AND TWO CAR GARAGE WITH PILES AND GRADE BEAM. NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER. THE AFFIDAVIT COVENANT & AGREEMENT REGARDING PAYMENT OF LINKAGE FEE WAS NOT RECORDED DUE TO COVID -19 VIRUS. IT WILL BE RECORDED AT A LATER TIME, PRIOR TO ISSUANCE OF CERTIFICATE OF OCCUPANCY.
Permit Issued
Issued on 3/25/2022
Issuing Office
Current Status
CofO Issued on 3/20/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/31/2019 APPLICANT
Green Plans Picked Up 2/5/2020 APPLICANT
Assigned to Plan Check Engineer 2/13/2020 CHON CHIO KUO
Corrections Issued 2/18/2020 CHON CHIO KUO
Quality Review Completed 2/18/2020 GUANG MIN TUNG
Building Plans Picked Up 2/20/2020 APPLICANT
Applicant returned to address corrections 6/17/2021 CHON CHIO KUO
Applicant returned to address corrections 6/21/2021 CHON CHIO KUO
Applicant returned to address corrections 12/22/2021 TROY DEGUZMAN
Applicant returned to address corrections 1/28/2022 TROY DEGUZMAN
Plan Check Approved 3/16/2022 TROY DEGUZMAN
Issued 3/25/2022 APPLICANT
CofO in Progress 3/11/2025 HAMIK HARTOUNIAN
No Progress 3/16/2025 DEROLD HAUFF
CofO in Progress 3/16/2025 DEROLD HAUFF
Permit Finaled 3/20/2025 DEROLD HAUFF
CofO Issued 3/20/2025 DEROLD HAUFF
Permit Finaled 3/20/2025 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/26/2020 ADRIAN CASTRO
Permit Cleared 2/26/2020 ADRIAN CASTRO
Sewer availability Cleared 6/29/2021 WALLIE JONG
Hydrant and Access approval Cleared 9/2/2021 MATTHEW CRAIG
Low Impact Development Cleared 12/16/2021 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 12/21/2021 WALLIE JONG
GPI Written Notices Cleared 12/22/2021 ALEXANDER HELFER
Grading Pre-Inspection Cleared 12/22/2021 ALEXANDER HELFER
Green Code Cleared 12/22/2021 COLIN LOREDO
Address approval Cleared 1/28/2022 WALLIE JONG
Excavation more than 5-ft deep Cleared 1/28/2022 CALOSHA APPROVED
Work Adjacent to Public Way Cleared 1/28/2022 ADRIAN CASTRO
Frnt yard landscape/Water mgmt Cleared 2/8/2022 MAXFIELD VERMY
Trees in Parkway Cleared 3/16/2022 TROY DEGUZMAN

Contact Information

Architect Farnham,, Emily; Lic. No.: C34247 1621 BAXTER STREET      LOS ANGELES, CA 90026
Contractor Bronstruction Inc; Lic. No.: 762724-B P O BOX 411196      LOS ANGELES, CA 90041
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026
Engineer Tsai,, Steve Shi-Shen; Lic. No.: GE2268 1545 VICTORY BLVD      GLENDALE, CA 91201

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/29/2022 Partial Approval THOMAS LOGRASSO
Piling/Pier/Caisson 6/29/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 7/5/2022 Partial Approval THOMAS LOGRASSO
Piling/Pier/Caisson 7/5/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 7/26/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 8/15/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 8/22/2022 Partial Approval FREDDIE RIVERA
Underground Mechanical 8/22/2022 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 9/12/2022 Not Ready for Inspection THOMAS LOGRASSO
Masonry Wall/Backfill 9/12/2022 Partial Approval THOMAS LOGRASSO
Underground Mechanical 9/12/2022 Not Ready for Inspection THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 10/7/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 10/18/2022 Partial Approval THOMAS LOGRASSO
PLUMBING-Rough 11/14/2022 Partial Approval THOMAS LOGRASSO
Deputy Steel/Welding 11/16/2022 Conditional Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 12/6/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 2/8/2023 Not Ready for Inspection THOMAS LOGRASSO
Footing/Foundation/Slab 2/8/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 6/28/2023 Partial Approval THOMAS LOGRASSO
Deputy Steel/Welding 6/30/2023 Approved DONALD CRICHLOW
Floor/Roof Diaphrgm/Shear Wall 8/4/2023 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/1/2023 Corrections Issued THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Corrections Issued THOMAS LOGRASSO
Deputy Wood Construction 11/29/2023 Conditional Approval THOMAS LOGRASSO
ELECTRICAL-Rough 2/20/2024 Corrections Issued THOMAS LOGRASSO
HVAC-Rough 2/20/2024 Corrections Issued THOMAS LOGRASSO
PLUMBING-Rough 2/20/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 3/4/2024 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 3/4/2024 Approved THOMAS LOGRASSO
Shower Pan 3/4/2024 Approved THOMAS LOGRASSO
Verify Sprinkler Sign Off 3/4/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 4/17/2024 Not Ready for Inspection THOMAS LOGRASSO
Green Building Rough 4/17/2024 Approved THOMAS LOGRASSO
Interior/Exterior Lathing 4/17/2024 Approved THOMAS LOGRASSO
BUILDING-Rough-Frame 5/14/2024 Approved HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 5/14/2024 Approved HAMIK HARTOUNIAN
Footing/Foundation/Slab 5/14/2024 Approved HAMIK HARTOUNIAN
Insulation 5/20/2024 Approved HAMIK HARTOUNIAN
Drywall Nailing 5/31/2024 Approved ALIZAH MAYAGOITIA
Underground Mechanical 11/4/2024 Approved LUIS CASTRO
Deputy Drilled-In Anchors 12/2/2024 Conditional Approval HAMIK HARTOUNIAN
ELECTRICAL-Final 1/17/2025 Corrections Issued WILLIAM SIERRA
Final 1/17/2025 Corrections Issued WILLIAM SIERRA
Gas Test 1/17/2025 Approved WILLIAM SIERRA
Green Building Final 1/17/2025 Not Ready for Inspection WILLIAM SIERRA
HVAC-Final 1/17/2025 Corrections Issued WILLIAM SIERRA
PLUMBING-Final 1/17/2025 Corrections Issued WILLIAM SIERRA
Reinforced Concrete Frame 1/17/2025 Not Ready for Inspection WILLIAM SIERRA
Reinforced Masonry Frame 1/17/2025 Not Ready for Inspection WILLIAM SIERRA
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Approved WILLIAM SIERRA
Service/Power Release 1/17/2025 Not Ready for Inspection WILLIAM SIERRA
Smoke Detectors 1/17/2025 Approved WILLIAM SIERRA
ELECTRICAL-Final 1/31/2025 Not Ready for Inspection HAMIK HARTOUNIAN
HVAC-Final 1/31/2025 Corrections Issued HAMIK HARTOUNIAN
PLUMBING-Final 1/31/2025 Approved HAMIK HARTOUNIAN
Pre-Inspection 2/28/2025 Corrections Issued HAMIK HARTOUNIAN
Final 3/5/2025 Partial Inspection HAMIK HARTOUNIAN
Final 3/11/2025 OK to Issue CofO HAMIK HARTOUNIAN
Green Building Final 3/11/2025 Approved HAMIK HARTOUNIAN
Reinforced Concrete Frame 3/11/2025 Approved HAMIK HARTOUNIAN
Reinforced Masonry Frame 3/11/2025 Approved HAMIK HARTOUNIAN
Service/Power Release 3/11/2025 Approved HAMIK HARTOUNIAN