1623 W FARGO ST 90026
Certificate Information: 1623 W FARGO ST 90026
- Application / Permit
- 19010-20000-06506
- Plan Check / Job No.
- B19VN22760
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (65'-0"x 26'-7 3/4") 3 STORY SINGLE FAMILY DWELLING INCL BASEMENT REC RM AND TWO CAR GARAGE WITH PILES AND GRADE BEAM. NFPA-13D FIRE SPRINKLER THROUGHOUT. WORK PER ENGINEER. THE AFFIDAVIT COVENANT & AGREEMENT REGARDING PAYMENT OF LINKAGE FEE WAS NOT RECORDED DUE TO COVID -19 VIRUS. IT WILL BE RECORDED AT A LATER TIME, PRIOR TO ISSUANCE OF CERTIFICATE OF OCCUPANCY.
- Permit Issued
- Issued on 3/25/2022
- Issuing Office
- Current Status
- CofO Issued on 3/20/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | CHON CHIO KUO |
| Corrections Issued | 2/18/2020 | CHON CHIO KUO |
| Quality Review Completed | 2/18/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 2/20/2020 | APPLICANT |
| Applicant returned to address corrections | 6/17/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 6/21/2021 | CHON CHIO KUO |
| Applicant returned to address corrections | 12/22/2021 | TROY DEGUZMAN |
| Applicant returned to address corrections | 1/28/2022 | TROY DEGUZMAN |
| Plan Check Approved | 3/16/2022 | TROY DEGUZMAN |
| Issued | 3/25/2022 | APPLICANT |
| CofO in Progress | 3/11/2025 | HAMIK HARTOUNIAN |
| No Progress | 3/16/2025 | DEROLD HAUFF |
| CofO in Progress | 3/16/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
| CofO Issued | 3/20/2025 | DEROLD HAUFF |
| Permit Finaled | 3/20/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | ADRIAN CASTRO |
| Permit | Cleared | 2/26/2020 | ADRIAN CASTRO |
| Sewer availability | Cleared | 6/29/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 9/2/2021 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/16/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/21/2021 | WALLIE JONG |
| GPI Written Notices | Cleared | 12/22/2021 | ALEXANDER HELFER |
| Grading Pre-Inspection | Cleared | 12/22/2021 | ALEXANDER HELFER |
| Green Code | Cleared | 12/22/2021 | COLIN LOREDO |
| Address approval | Cleared | 1/28/2022 | WALLIE JONG |
| Excavation more than 5-ft deep | Cleared | 1/28/2022 | CALOSHA APPROVED |
| Work Adjacent to Public Way | Cleared | 1/28/2022 | ADRIAN CASTRO |
| Frnt yard landscape/Water mgmt | Cleared | 2/8/2022 | MAXFIELD VERMY |
| Trees in Parkway | Cleared | 3/16/2022 | TROY DEGUZMAN |
Contact Information
| Architect | Farnham,, Emily; Lic. No.: C34247 | 1621 BAXTER STREET LOS ANGELES, CA 90026 |
| Contractor | Bronstruction Inc; Lic. No.: 762724-B | P O BOX 411196 LOS ANGELES, CA 90041 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
| Engineer | Tsai,, Steve Shi-Shen; Lic. No.: GE2268 | 1545 VICTORY BLVD GLENDALE, CA 91201 |
Inspector Information
| HAMIK HARTOUNIAN, (213) 202-3275 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Partial Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 6/29/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 7/5/2022 | Partial Approval | THOMAS LOGRASSO |
| Piling/Pier/Caisson | 7/5/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/15/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 8/22/2022 | Partial Approval | FREDDIE RIVERA |
| Underground Mechanical | 8/22/2022 | Partial Inspection | FREDDIE RIVERA |
| Footing/Foundation/Slab | 9/12/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Masonry Wall/Backfill | 9/12/2022 | Partial Approval | THOMAS LOGRASSO |
| Underground Mechanical | 9/12/2022 | Not Ready for Inspection | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 10/7/2022 | Partial Approval | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 10/18/2022 | Partial Approval | THOMAS LOGRASSO |
| PLUMBING-Rough | 11/14/2022 | Partial Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 11/16/2022 | Conditional Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 12/6/2022 | Partial Approval | THOMAS LOGRASSO |
| Excavation/Setback/Form/Re-Bar | 2/8/2023 | Not Ready for Inspection | THOMAS LOGRASSO |
| Footing/Foundation/Slab | 2/8/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Partial Approval | THOMAS LOGRASSO |
| Deputy Steel/Welding | 6/30/2023 | Approved | DONALD CRICHLOW |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2023 | Partial Approval | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2023 | Corrections Issued | THOMAS LOGRASSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/27/2023 | Corrections Issued | THOMAS LOGRASSO |
| Deputy Wood Construction | 11/29/2023 | Conditional Approval | THOMAS LOGRASSO |
| ELECTRICAL-Rough | 2/20/2024 | Corrections Issued | THOMAS LOGRASSO |
| HVAC-Rough | 2/20/2024 | Corrections Issued | THOMAS LOGRASSO |
| PLUMBING-Rough | 2/20/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 3/4/2024 | Corrections Issued | THOMAS LOGRASSO |
| Rough-Elec/Plmb/HVAC | 3/4/2024 | Approved | THOMAS LOGRASSO |
| Shower Pan | 3/4/2024 | Approved | THOMAS LOGRASSO |
| Verify Sprinkler Sign Off | 3/4/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 4/17/2024 | Not Ready for Inspection | THOMAS LOGRASSO |
| Green Building Rough | 4/17/2024 | Approved | THOMAS LOGRASSO |
| Interior/Exterior Lathing | 4/17/2024 | Approved | THOMAS LOGRASSO |
| BUILDING-Rough-Frame | 5/14/2024 | Approved | HAMIK HARTOUNIAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/14/2024 | Approved | HAMIK HARTOUNIAN |
| Footing/Foundation/Slab | 5/14/2024 | Approved | HAMIK HARTOUNIAN |
| Insulation | 5/20/2024 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 5/31/2024 | Approved | ALIZAH MAYAGOITIA |
| Underground Mechanical | 11/4/2024 | Approved | LUIS CASTRO |
| Deputy Drilled-In Anchors | 12/2/2024 | Conditional Approval | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| Final | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| Gas Test | 1/17/2025 | Approved | WILLIAM SIERRA |
| Green Building Final | 1/17/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| HVAC-Final | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| PLUMBING-Final | 1/17/2025 | Corrections Issued | WILLIAM SIERRA |
| Reinforced Concrete Frame | 1/17/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Reinforced Masonry Frame | 1/17/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | WILLIAM SIERRA |
| Service/Power Release | 1/17/2025 | Not Ready for Inspection | WILLIAM SIERRA |
| Smoke Detectors | 1/17/2025 | Approved | WILLIAM SIERRA |
| ELECTRICAL-Final | 1/31/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| HVAC-Final | 1/31/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| PLUMBING-Final | 1/31/2025 | Approved | HAMIK HARTOUNIAN |
| Pre-Inspection | 2/28/2025 | Corrections Issued | HAMIK HARTOUNIAN |
| Final | 3/5/2025 | Partial Inspection | HAMIK HARTOUNIAN |
| Final | 3/11/2025 | OK to Issue CofO | HAMIK HARTOUNIAN |
| Green Building Final | 3/11/2025 | Approved | HAMIK HARTOUNIAN |
| Reinforced Concrete Frame | 3/11/2025 | Approved | HAMIK HARTOUNIAN |
| Reinforced Masonry Frame | 3/11/2025 | Approved | HAMIK HARTOUNIAN |
| Service/Power Release | 3/11/2025 | Approved | HAMIK HARTOUNIAN |