4209 N MATILIJA AVE 91423
Certificate Information: 4209 N MATILIJA AVE 91423
- Application / Permit
- 19010-20000-06500
- Plan Check / Job No.
- B19VN22746
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (57'-6"x 39'-0") IRR SHAPE 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE. WORK PER ENGINEER.
- Permit Issued
- Issued on 3/5/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | TROY DEGUZMAN |
| Green Plans Picked Up | 1/16/2020 | APPLICANT |
| Corrections Issued | 1/19/2020 | TROY DEGUZMAN |
| Quality Review Completed | 1/30/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 2/4/2020 | APPLICANT |
| Applicant returned to address corrections | 2/21/2020 | TROY DEGUZMAN |
| Applicant returned to address corrections | 2/28/2020 | TROY DEGUZMAN |
| Plan Check Approved | 3/3/2020 | TROY DEGUZMAN |
| Issued | 3/5/2020 | LADBS |
| CofO in Progress | 2/25/2025 | MISAEL ESPARZA |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
| CofO Issued | 3/13/2025 | RUBEN SALAS |
| Permit Finaled | 3/13/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/6/2020 | ADRIAN CASTRO |
| Eng Process Fee Ord 176,300 | Cleared | 2/6/2020 | ADRIAN CASTRO |
| Hydrant and Access approval | Cleared | 2/6/2020 | GEORGE SUCHAND |
| Sewer availability | Cleared | 2/6/2020 | ADRIAN CASTRO |
| GPI Written Notices | Cleared | 3/3/2020 | TROY DEGUZMAN |
| Grading Pre-Inspection | Cleared | 3/3/2020 | TROY DEGUZMAN |
| Green Code | Cleared | 3/3/2020 | AARON COSTA |
| Low Impact Development | Cleared | 3/3/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 3/3/2020 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 2/1/2021 | Corrections Issued | CHARLES POWELL |
| Underground Mechanical | 7/19/2021 | Corrections Issued | CHARLES POWELL |
| Underground Mechanical | 8/2/2021 | Partial Approval | CHARLES POWELL |
| Excavation/Setback/Form/Re-Bar | 8/16/2021 | Not Ready for Inspection | ARAM AVEDISIAN |
| Footing/Foundation/Slab | 8/19/2021 | Approved | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2021 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2021 | Partial Inspection | MISAEL ESPARZA |
| Structural Steel Frame | 9/22/2021 | Partial Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2021 | Partial Approval | MICHAEL PELHAM |
| HVAC-Rough | 1/12/2022 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 2/15/2022 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 2/22/2022 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 2/22/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 2/23/2022 | Corrections Issued | MISAEL ESPARZA |
| Green Building Rough | 2/23/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 2/23/2022 | Corrections Issued | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 2/23/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 3/21/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Rough | 3/21/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 3/21/2022 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 3/21/2022 | Approved | MISAEL ESPARZA |
| Verify Sprinkler Sign Off | 3/21/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/12/2022 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 7/25/2022 | Corrections Issued | MISAEL ESPARZA |
| Insulation | 7/25/2022 | Conditional Approval | MISAEL ESPARZA |
| Shower Pan | 9/16/2022 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 11/9/2022 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 12/9/2022 | Approved | MISAEL ESPARZA |
| Drywall Nailing | 12/9/2022 | Approved | MISAEL ESPARZA |
| Green Building Rough | 12/9/2022 | Approved | MISAEL ESPARZA |
| Insulation | 12/9/2022 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 7/30/2024 | Corrections Issued | MISAEL ESPARZA |
| HVAC-Final | 7/30/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 7/30/2024 | Approved | MISAEL ESPARZA |
| Smoke Detectors | 7/30/2024 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Final | 8/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 8/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 8/16/2024 | Approved | MISAEL ESPARZA |
| HVAC-Final | 8/16/2024 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Final | 8/16/2024 | Approved | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 8/16/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 8/16/2024 | Corrections Issued | MISAEL ESPARZA |
| Final | 11/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 11/12/2024 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 11/12/2024 | Approved | MISAEL ESPARZA |
| Final | 2/24/2025 | OK to Issue CofO | MISAEL ESPARZA |
| Service/Power Release | 2/24/2025 | Approved | MISAEL ESPARZA |