715 N ILIFF ST 90272
Certificate Information: 715 N ILIFF ST 90272
- Application / Permit
- 19010-20000-06480
- Plan Check / Job No.
- B19VN22730
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 72'-8" X 38'-0" FULLY SPRINKLERED TWO STORY SFD WITH ATTACHED TWO CAR GARAGE & OPEN TRELLIS.
- Permit Issued
- Issued on 4/10/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 5/17/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/9/2020 | ARTIN ZARUKIAN |
| Corrections Issued | 1/12/2020 | ARTIN ZARUKIAN |
| Quality Review Completed | 1/15/2020 | GUANG MIN TUNG |
| Building Plans Picked Up | 1/16/2020 | APPLICANT |
| Green Plans Picked Up | 1/17/2020 | APPLICANT |
| Plan Check Approved | 3/27/2020 | ARTIN ZARUKIAN |
| Issued | 4/10/2020 | LADBS |
| CofO in Progress | 5/17/2021 | VINCENT COTTON |
| Permit Finaled | 5/17/2021 | VINCENT COTTON |
| Permit Finaled | 5/17/2021 | VINCENT COTTON |
| CofO Issued | 5/17/2021 | VINCENT COTTON |
Permit Application Clearance Information
| Address approval | Cleared | 3/3/2020 | GUILLERMO PETRA |
| Eng Process Fee Ord 176,300 | Cleared | 3/3/2020 | GUILLERMO PETRA |
| Permit | Cleared | 3/3/2020 | GUILLERMO PETRA |
| Sewer availability | Cleared | 3/3/2020 | GUILLERMO PETRA |
| Hydrant and Access approval | Cleared | 3/4/2020 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/4/2020 | ORVAL HERNANDEZ-MARCIAL |
| Roof/Waste drainage to street | Cleared | 3/4/2020 | CELINA MORENO |
| Trees in Parkway | Cleared | 3/4/2020 | JOHN KIM |
| Green Code | Cleared | 3/5/2020 | MICHAEL AYERS |
| GPI Written Notices | Cleared | 3/27/2020 | ARTIN ZARUKIAN |
| Grading Pre-Inspection | Cleared | 3/27/2020 | ARTIN ZARUKIAN |
Contact Information
| Contractor | Lev Construction; Lic. No.: 1027463-B | 340 S CLOVERDALE AVE #404 LOS ANGELES, CA 90036 |
| Engineer | Wang,, Hongyu; Lic. No.: C72679 | 6270 MCLEOD DR STE 140 LAS VEGAS, NV 89120 |
Inspector Information
| TEMISTOCLES CAAL, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
| JESUS PINEDA, (213) 653-1908 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/15/2020 | Partial Approval | DANNY TOLENTINO |
| Excavation/Setback/Form/Re-Bar | 5/21/2020 | Partial Approval | DANNY TOLENTINO |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2020 | Partial Approval | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2020 | Approved | JOHN KIDWELL |
| Gas Test | 7/21/2020 | Approved | CARLOS MATAMOROS |
| HVAC-Rough | 7/21/2020 | Not Ready for Inspection | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 7/21/2020 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 7/21/2020 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/23/2020 | Not Ready for Inspection | ROBERT SHELLY |
| HVAC-Rough | 7/23/2020 | Approved | ROBERT SHELLY |
| BUILDING-Rough-Frame | 7/27/2020 | Corrections Issued | ROBERT SHELLY |
| ELECTRICAL-Rough | 7/27/2020 | Corrections Issued | ROBERT SHELLY |
| Green Building Rough | 7/27/2020 | Not Ready for Inspection | ROBERT SHELLY |
| Verify Sprinkler Sign Off | 7/27/2020 | Not Ready for Inspection | ROBERT SHELLY |
| BUILDING-Rough-Frame | 7/28/2020 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 7/28/2020 | Approved | JOHN KIDWELL |
| Green Building Rough | 7/28/2020 | Approved | JOHN KIDWELL |
| Verify Sprinkler Sign Off | 7/28/2020 | Approved | JOHN KIDWELL |
| Insulation | 8/3/2020 | Corrections Issued | ROBERT SHELLY |
| Shower Pan | 8/3/2020 | Corrections Issued | ROBERT SHELLY |
| Insulation | 8/4/2020 | Approved | ROBERT SHELLY |
| Shower Pan | 8/4/2020 | Approved | ROBERT SHELLY |
| Drywall Nailing | 8/12/2020 | Approved | ROBERT SHELLY |
| Interior/Exterior Lathing | 8/12/2020 | Approved | ROBERT SHELLY |
| ELECTRICAL-Final | 3/10/2021 | Approved | JOHN KIDWELL |
| Green Building Final | 3/10/2021 | Conditional Approval | JOHN KIDWELL |
| HVAC-Final | 3/10/2021 | Conditional Approval | JOHN KIDWELL |
| PLUMBING-Final | 3/10/2021 | Approved | JOHN KIDWELL |
| Final | 4/19/2021 | Not Ready for Inspection | JOHN KIDWELL |
| Footing/Foundation/Slab | 4/19/2021 | Approved | JOHN KIDWELL |
| Green Building Final | 4/19/2021 | Approved | JOHN KIDWELL |
| HVAC-Final | 4/19/2021 | Approved | JOHN KIDWELL |
| SGSOV-Seismic Gas S/O Valve | 4/19/2021 | SGSOV Approved | JOHN KIDWELL |
| Service/Power Release | 4/19/2021 | Approved | JOHN KIDWELL |
| Smoke Detectors | 4/19/2021 | Approved | JOHN KIDWELL |
| Final | 4/27/2021 | Conditional Approval | JOHN KIDWELL |