5146 N ROCKLAND AVE 90041
Certificate Information: 5146 N ROCKLAND AVE 90041
- Application / Permit
- 19010-20000-06461
- Plan Check / Job No.
- B19VN22720
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT (33'-0"X17'-0") PER LAMC 12.22 A.33(c)¹, (d)¹, and (g)
- Permit Issued
- Issued on 10/5/2020
- Issuing Office
- Current Status
- CofO Issued on 12/13/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/13/2020 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/21/2020 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/24/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 3/2/2020 | APPLICANT |
| Green Plans Picked Up | 3/2/2020 | APPLICANT |
| Plan Check Approved | 10/5/2020 | MOHAMMAD ESMAILI |
| Issued | 10/5/2020 | APPLICANT |
| CofO in Progress | 9/10/2021 | CRAIG VAUGHAN |
| No Progress | 9/10/2021 | CRAIG VAUGHAN |
| CofO in Progress | 12/6/2021 | CRAIG VAUGHAN |
| Permit Finaled | 12/13/2021 | DEROLD HAUFF |
| CofO Issued | 12/13/2021 | DEROLD HAUFF |
| Permit Finaled | 12/13/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Construction near power lines | Cleared | 5/7/2020 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 5/27/2020 | BRIAN MILLER |
| Grading Pre-Inspection | Cleared | 5/27/2020 | BRIAN MILLER |
| Address approval | Cleared | 6/12/2020 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/12/2020 | JEANIE LAM |
| Sewer availability | Cleared | 6/12/2020 | JEANIE LAM |
| Hydrant and Access approval | Cleared | 7/1/2020 | KURT CORRAL |
| Low Impact Development | Cleared | 7/13/2020 | ROBIN YAMADA |
| Roof/Waste drainage to street | Cleared | 8/17/2020 | JEANIE LAM |
| Green Code | Cleared | 8/19/2020 | DAVID MATSON |
Contact Information
| Contractor | Hillstar Construction Inc; Lic. No.: 972213-B | 22647 VENTURA BLVD #173 WOODLAND HILLS, CA 91367 |
| Engineer | De, Guzman, Nicolo Klaus Dumlao; Lic. No.: C76675 | 9506 ARBORGLEN DRIVE RANCHO CUCAMONGA, CA 91730 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/19/2020 | Not Ready for Inspection | CRAIG VAUGHAN |
| PLUMBING-Rough | 10/19/2020 | Partial Approval | CRAIG VAUGHAN |
| Excavation/Setback/Form/Re-Bar | 10/20/2020 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 11/12/2020 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 11/12/2020 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 11/12/2020 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 11/12/2020 | Partial Approval | CRAIG VAUGHAN |
| PLUMBING-Rough | 11/12/2020 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 11/12/2020 | Approved | CRAIG VAUGHAN |
| Wood Frame | 11/12/2020 | Approved | CRAIG VAUGHAN |
| Insulation | 11/16/2020 | Approved | HAMIK HARTOUNIAN |
| Interior/Exterior Lathing | 11/16/2020 | Approved | HAMIK HARTOUNIAN |
| Shower Pan | 11/16/2020 | Approved | HAMIK HARTOUNIAN |
| Drywall Nailing | 11/19/2020 | Approved | CRAIG VAUGHAN |
| Final | 1/4/2021 | Corrections Issued | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 1/4/2021 | Approved | CRAIG VAUGHAN |
| Green Building Final | 1/4/2021 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 1/4/2021 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 1/4/2021 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 1/4/2021 | Approved | CRAIG VAUGHAN |
| Final | 1/8/2021 | Not Ready for Inspection | COREY HUPP |
| Final | 1/19/2021 | Conditional Approval | CRAIG VAUGHAN |
| Gas Test | 1/19/2021 | Approved | CRAIG VAUGHAN |