6430 W DREXEL AVE 90048
Certificate Information: 6430 W DREXEL AVE 90048
- Application / Permit
- 19010-20000-06443
- Plan Check / Job No.
- B19VN22710
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- REMOVE ALL EXTERIOR AND INTERIOR WALLS OF AN EXISTING ONE STORY SINGLE FAMILY DWELLING EXCEPT FOR 15'-6" AND 8'-4" LF AT SOUTH SIDE AND BUILD A 33' x 55'-6" 2-STORY SINGLE FAMILY DWELLING. NFPA-13D FIRE SPRINKLERS THROUGHOUT REQUIRED, ALL WORK PER ENGINEERING
- Permit Issued
- Issued on 12/9/2020
- Issuing Office
- Current Status
- CofO Issued on 9/9/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 1/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | SEAN SHAHMIRI |
| Corrections Issued | 1/17/2020 | SEAN SHAHMIRI |
| Quality Review Completed | 1/28/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Applicant returned to address corrections | 5/29/2020 | SEAN SHAHMIRI |
| Plan Check Approved | 8/31/2020 | SEAN SHAHMIRI |
| Applicant returned to address corrections | 9/2/2020 | SEAN SHAHMIRI |
| Issued | 12/9/2020 | APPLICANT |
| CofO in Progress | 8/19/2022 | EVAN COOPER |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
| CofO Issued | 9/9/2022 | DANIEL ORRANTE |
| Permit Finaled | 9/9/2022 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 1/30/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 1/31/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 2/20/2020 | MICHAEL AYERS |
| ZI | Cleared | 2/20/2020 | VINCENT QUITORIANO |
| Miscellaneous | Cleared | 3/31/2020 | HERMINIGILDO AGUSTIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/5/2021 | Approved | EVAN COOPER |
| METHANE-Barrier | 5/5/2021 | Approved | EVAN COOPER |
| METHANE-Subgrade | 5/5/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 5/20/2021 | Partial Approval | EVAN COOPER |
| Wood Frame | 5/20/2021 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 6/4/2021 | Partial Approval | EVAN COOPER |
| Deputy Steel/Welding | 7/16/2021 | Conditional Approval | EVAN COOPER |
| ELECTRICAL-Rough | 7/19/2021 | Approved | KEVIN SARGSYAN |
| HVAC-Rough | 7/19/2021 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 7/28/2021 | Corrections Issued | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/4/2021 | Not Ready for Inspection | EVAN COOPER |
| HVAC-Rough | 8/4/2021 | Approved | EVAN COOPER |
| PLUMBING-Rough | 8/4/2021 | Approved | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2021 | Partial Approval | EVAN COOPER |
| Shower Pan | 8/13/2021 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2021 | Partial Approval | EVAN COOPER |
| Green Building Rough | 8/31/2021 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 8/31/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 9/14/2021 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 10/13/2021 | Conditional Approval | EVAN COOPER |
| Interior/Exterior Lathing | 10/21/2021 | Partial Approval | JOHNNY MIRANDA |
| Interior/Exterior Lathing | 10/27/2021 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 11/10/2021 | Partial Approval | EVAN COOPER |
| Drywall Nailing | 11/15/2021 | Partial Inspection | DEANDRE HOFFMAN |
| Pre-Inspection | 11/15/2021 | Partial Inspection | CLAYTON GRAHAM |
| Special/Order Compliance | 11/15/2021 | Partial Inspection | CLAYTON GRAHAM |
| Drywall Nailing | 11/22/2021 | Conditional Approval | EVAN COOPER |
| Green Building Rough | 11/22/2021 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 12/23/2021 | Approved | EVAN COOPER |
| Drywall Nailing | 12/23/2021 | Approved | EVAN COOPER |
| Green Building Rough | 12/23/2021 | Approved | EVAN COOPER |
| Insulation | 12/23/2021 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 12/23/2021 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 12/23/2021 | Approved | EVAN COOPER |
| HVAC-Final | 6/20/2022 | Corrections Issued | DAVID FEILER |
| ELECTRICAL-Final | 8/10/2022 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 8/10/2022 | Corrections Issued | EVAN COOPER |
| PLUMBING-Final | 8/10/2022 | Corrections Issued | EVAN COOPER |
| ELECTRICAL-Final | 8/18/2022 | Approved | EVAN COOPER |
| Final | 8/18/2022 | OK to Issue CofO | EVAN COOPER |
| Gas Test | 8/18/2022 | Approved | EVAN COOPER |
| Green Building Final | 8/18/2022 | Approved | EVAN COOPER |
| HVAC-Final | 8/18/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 8/18/2022 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/18/2022 | SGSOV Approved | EVAN COOPER |
| Service/Power Release | 8/18/2022 | Approved | EVAN COOPER |
| Smoke Detectors | 8/18/2022 | Approved | EVAN COOPER |