Pre-Inspection
|
11/5/2024
|
Approved
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
12/19/2024
|
Partial Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
12/20/2024
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
12/20/2024
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
12/20/2024
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/2/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Footing/Foundation/Slab
|
1/3/2025
|
Approved
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/6/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
1/6/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
1/6/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
1/6/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/7/2025
|
Approved
|
ROBERT DAVIS
|
|
Wall Anchors
|
1/7/2025
|
Partial Inspection
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/8/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/22/2025
|
Approved
|
ROBERT DAVIS
|
|
Green Building Rough
|
1/22/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
1/22/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
1/22/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
1/23/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
2/26/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
2/26/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
2/26/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
2/28/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
3/25/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
3/28/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
3/28/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
3/28/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Green Building Rough
|
4/3/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
4/3/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
4/3/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
4/7/2025
|
Approved
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
4/7/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
4/15/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
4/17/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Deputy Shotcrete
|
4/18/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Shotcrete
|
4/21/2025
|
Conditional Approval
|
JEFFREY DURAN
|
|
Green Building Rough
|
4/23/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Reinforced Concrete Frame
|
4/23/2025
|
Partial Approval
|
GREGORY POMISH
|
|
Verify Sprinkler Sign Off
|
4/23/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Deputy Shotcrete
|
4/24/2025
|
Conditional Approval
|
JOHN KITCKO
|
|
Reinforced Masonry Frame
|
4/24/2025
|
Not Ready for Inspection
|
DANNY RODRIGUEZ
|
|
Deputy Shotcrete
|
4/25/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Green Building Rough
|
4/28/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Reinforced Concrete Frame
|
4/28/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Verify Sprinkler Sign Off
|
4/28/2025
|
Not Ready for Inspection
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
5/5/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Masonry Wall/Backfill
|
5/22/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Deputy Reinf. Concrete
|
5/23/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Reinf. Concrete
|
5/28/2025
|
Conditional Approval
|
ROBERT DAVIS
|
|
Deputy Reinf. Concrete
|
6/5/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Green Building Rough
|
6/6/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Reinforced Concrete Frame
|
6/6/2025
|
No Access for Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
6/6/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
6/13/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Reinforced Concrete Frame
|
6/13/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
6/13/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Reinforced Masonry Frame
|
6/16/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Deputy Reinf. Concrete
|
6/25/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Reinf. Concrete
|
6/26/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Steel/Welding
|
7/7/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Special/Order Compliance
|
7/7/2025
|
Corrections Issued
|
BRIAN KELLY
|
|
Deputy Steel/Welding
|
7/14/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
7/14/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/14/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Deputy Shotcrete
|
7/21/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/24/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
7/25/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/25/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Deputy Steel/Welding
|
7/29/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
8/6/2025
|
Conditional Approval
|
DEANDRE HOFFMAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/6/2025
|
Partial Approval
|
DEANDRE HOFFMAN
|
|
Deputy Wood Construction
|
8/20/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/25/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
8/27/2025
|
Partial Inspection
|
ROBERT DAVIS
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/9/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
9/10/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Deputy Steel/Welding
|
9/25/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
10/2/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/2/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Deputy Steel/Welding
|
10/14/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
10/14/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/14/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/15/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Deputy Steel/Welding
|
10/16/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
10/16/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/17/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/20/2025
|
Partial Approval
|
ROBERT DAVIS
|
|
Insulation
|
10/21/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/22/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
10/24/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/27/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
10/28/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Drywall Nailing
|
10/28/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
10/28/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Insulation
|
10/28/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/30/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
10/31/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
10/31/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
10/31/2025
|
Corrections Issued
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
11/3/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/3/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/4/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Green Building Rough
|
11/4/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
11/4/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
11/4/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/5/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/6/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
11/7/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/7/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
11/12/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/12/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
11/14/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
11/18/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
11/18/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
11/18/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
11/19/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
11/20/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
11/20/2025
|
Corrections Issued
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
11/21/2025
|
No Access for Inspection
|
BRIAN KELLY
|
|
Insulation
|
11/21/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Drywall Nailing
|
11/24/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
11/24/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Insulation
|
11/24/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
11/25/2025
|
Conditional Approval
|
BRIAN KELLY
|
|
Drywall Nailing
|
11/25/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
11/25/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
11/26/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Special/Order Compliance
|
11/29/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Drywall Nailing
|
12/1/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
12/1/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Drywall Nailing
|
12/4/2025
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
12/4/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/5/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Drywall Nailing
|
12/8/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Green Building Rough
|
12/8/2025
|
Partial Inspection
|
GREGORY POMISH
|
|
Insulation
|
12/8/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Special/Order Compliance
|
12/8/2025
|
Partial Approval
|
SCOTT SOBEL
|
|
Verify Sprinkler Sign Off
|
12/9/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
12/9/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
12/10/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
12/11/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
12/11/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
12/12/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Drywall Nailing
|
12/16/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Green Building Rough
|
12/16/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Insulation
|
12/16/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Light Gage Steel Frame
|
12/19/2025
|
Partial Approval
|
BRIAN KELLY
|
|
Drywall Nailing
|
12/24/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
12/24/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
12/30/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
12/30/2025
|
Partial Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
12/31/2025
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
1/5/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Special/Order Compliance
|
1/5/2026
|
Partial Inspection
|
REGINA MENDEZ
|
|
Wood Frame
|
1/5/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
1/6/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
1/8/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Insulation
|
1/14/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Drywall Nailing
|
1/15/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
1/15/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Drywall Nailing
|
1/16/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Interior/Exterior Lathing
|
1/21/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Interior/Exterior Lathing
|
1/22/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Interior/Exterior Lathing
|
1/23/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
1/27/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Light Gage Steel Frame
|
1/27/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Insulation
|
1/28/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Drywall Nailing
|
2/3/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
2/3/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Interior/Exterior Lathing
|
2/4/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Drywall Nailing
|
2/9/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
2/9/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Drywall Nailing
|
2/12/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Green Building Rough
|
2/12/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Special/Order Compliance
|
2/12/2026
|
Partial Inspection
|
SEAN GRIFFITH
|
|
Drywall Nailing
|
2/13/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Drywall Nailing
|
2/17/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Green Building Rough
|
2/17/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
2/17/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
2/17/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
3/10/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
3/10/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Wood Frame
|
3/10/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Special/Order Compliance
|
3/19/2026
|
Partial Inspection
|
BRIAN KELLY
|
|
Light Gage Steel Frame
|
4/13/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Green Building Rough
|
4/16/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Light Gage Steel Frame
|
4/16/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Verify Sprinkler Sign Off
|
4/16/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Light Gage Steel Frame
|
4/20/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Light Gage Steel Frame
|
4/21/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Light Gage Steel Frame
|
4/24/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Special/Order Compliance
|
4/24/2026
|
Partial Inspection
|
SEAN GRIFFITH
|
|
Drywall Nailing
|
4/30/2026
|
Partial Approval
|
BRIAN KELLY
|
|
Green Building Rough
|
4/30/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
5/5/2026
|
Not Ready for Inspection
|
GREGORY POMISH
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/4/2026
|
Not Ready for Inspection
|
BRIAN KELLY
|
|
Deputy Wood Construction
|
6/5/2026
|
No Result Entered
|
BRIAN KELLY
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/5/2026
|
No Result Entered
|
BRIAN KELLY
|