434 N FLORES ST 90048
Certificate Information: 434 N FLORES ST 90048
- Application / Permit
- 19010-20000-06430
- Plan Check / Job No.
- B19VN22692
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW (74'-11"x 37'-6") 2-STORY SINGLE FAMILY DWELLING W/ ATTACHED 2- CAR GARAGE. NFPA-13D SPRINKLER THROUGHOUT. WORK PER ENGINEER.
- Permit Issued
- Issued on 7/10/2020
- Issuing Office
- Current Status
- CofO Issued on 8/4/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Green Plans Picked Up | 1/14/2020 | APPLICANT |
| Assigned to Plan Check Engineer | 1/16/2020 | TROY DEGUZMAN |
| Corrections Issued | 1/18/2020 | TROY DEGUZMAN |
| Quality Review Completed | 1/29/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 1/31/2020 | APPLICANT |
| Plan Check Approved | 2/13/2020 | TROY DEGUZMAN |
| Issued | 7/10/2020 | APPLICANT |
| CofO in Progress | 7/30/2021 | CHRIS CHRISTENSEN |
| Permit Finaled | 8/4/2021 | DEROLD HAUFF |
| Permit Finaled | 8/4/2021 | DEROLD HAUFF |
| CofO Issued | 8/4/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Low Impact Development | Cleared | 1/30/2020 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Sewer availability | Cleared | 1/30/2020 | APEKSHYA BAJRACHARYA |
| Hydrant and Access approval | Cleared | 1/31/2020 | GEORGE SUCHAND |
| Green Code | Cleared | 2/13/2020 | MICHAEL AYERS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Helou,, Dawn Renee; Lic. No.: C52361 | 22701 ERWIN ST WOODLAND HILLS, CA 91367 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 7/31/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/31/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Barrier | 7/31/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Subgrade | 7/31/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 8/6/2020 | Partial Approval | ARTHUR SARGSYAN |
| METHANE-Barrier | 8/6/2020 | Approved | ARTHUR SARGSYAN |
| METHANE-Subgrade | 8/6/2020 | Approved | ARTHUR SARGSYAN |
| PLUMBING-Rough | 8/17/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Wood Frame | 8/17/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Deputy Steel/Welding | 8/31/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 9/4/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Floor/Roof Diaphrgm/Shear Wall | 10/7/2020 | Partial Approval | CHRIS CHRISTENSEN |
| HVAC-Rough | 10/7/2020 | Approved | CHRIS CHRISTENSEN |
| ELECTRICAL-Rough | 10/19/2020 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Rough | 10/19/2020 | Approved | CHRIS CHRISTENSEN |
| Deputy Wood Construction | 11/4/2020 | No Access for Inspection | ELMER BLAND |
| BUILDING-Rough-Frame | 11/6/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Green Building Rough | 11/6/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| METHANE-Rough | 11/6/2020 | Approved | CHRIS CHRISTENSEN |
| Shower Pan | 11/6/2020 | Approved | CHRIS CHRISTENSEN |
| Verify Sprinkler Sign Off | 11/6/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 11/10/2020 | Partial Approval | CHRIS CHRISTENSEN |
| Special/Order Compliance | 11/25/2020 | Corrections Issued | CHRIS CHRISTENSEN |
| Insulation | 12/1/2020 | Conditional Approval | CHRIS CHRISTENSEN |
| Drywall Nailing | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Green Building Rough | 12/15/2020 | Approved | CHRIS CHRISTENSEN |
| Interior/Exterior Lathing | 12/15/2020 | Partial Approval | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 6/2/2021 | Approved | CHRIS CHRISTENSEN |
| HVAC-Final | 6/2/2021 | Approved | CHRIS CHRISTENSEN |
| PLUMBING-Final | 6/2/2021 | Approved | CHRIS CHRISTENSEN |
| Service/Power Release | 6/2/2021 | Approved | CHRIS CHRISTENSEN |
| BUILDING-Rough-Frame | 7/16/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 7/16/2021 | Corrections Issued | CHRIS CHRISTENSEN |
| Footing/Foundation/Slab | 7/16/2021 | Approved | CHRIS CHRISTENSEN |
| Green Building Final | 7/16/2021 | Approved | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 7/16/2021 | SGSOV Approved | CHRIS CHRISTENSEN |
| Smoke Detectors | 7/16/2021 | Approved | CHRIS CHRISTENSEN |
| Final | 7/29/2021 | OK to Issue CofO | CHRIS CHRISTENSEN |