4919 N RHODES AVE 91607

Certificate Information: 4919 N RHODES AVE 91607

Application / Permit
19010-20000-06427
Plan Check / Job No.
B19VN22688
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD W/ ATT GARAGE ( 65'-6" x 35'-0") fire sprinkler NFPA 13D
Permit Issued
Issued on 12/7/2020
Issuing Office
Current Status
CofO Issued on 8/28/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 MOHAMMAD ESMAILI
Corrections Issued 2/18/2020 MOHAMMAD ESMAILI
Quality Review Completed 2/27/2020 OMID HEDAYAT
Building Plans Picked Up 2/28/2020 APPLICANT
Green Plans Picked Up 2/28/2020 APPLICANT
Applicant returned to address corrections 5/13/2020 MOHAMMAD ESMAILI
Plan Check Approved 12/3/2020 MOHAMMAD ESMAILI
Issued 12/7/2020 APPLICANT
CofO in Progress 8/28/2021 MICHAEL PELHAM
Permit Finaled 8/28/2021 MICHAEL SMITH
CofO Issued 8/28/2021 MICHAEL SMITH
Permit Finaled 8/28/2021 MICHAEL SMITH

Permit Application Clearance Information

ZI Cleared 7/22/2020 OLGA AYALA
Low Impact Development Cleared 9/16/2020 ANDRES COVARRUBIAS
Address approval Cleared 9/25/2020 ADRIAN CASTRO
Green Code Cleared 9/25/2020 AARON COSTA
Roof/Waste drainage to street Cleared 9/25/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 10/5/2020 ADRIAN CASTRO
Sewer availability Cleared 10/5/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 10/30/2020 MATTHEW CRAIG
Trees in Parkway Cleared 11/12/2020 JOHN KIM

Contact Information

Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno S; Lic. No.: S3454 25531 PRADO DELAS BELLOTAS      CALABASAS, CA 91302

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 12/21/2020 Corrections Issued BRENDAN LOONEY
Sewer 12/22/2020 Approved DANIEL DREW
Footing/Foundation/Slab 12/24/2020 Corrections Issued BRENDAN LOONEY
Pre-Inspection 12/28/2020 Not Ready for Inspection DANIEL DREW
Excavation/Setback/Form/Re-Bar 12/29/2020 Approved BRENDAN LOONEY
Footing/Foundation/Slab 1/4/2021 Approved ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 1/8/2021 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 1/19/2021 Partial Approval BRENDAN LOONEY
Deputy Wood Construction 2/4/2021 Conditional Approval DANIEL ORRANTE
BUILDING-Rough-Frame 2/22/2021 Approved JOHN HAYES
ELECTRICAL-Rough 2/22/2021 Approved JOHN HAYES
Green Building Rough 2/22/2021 Approved JOHN HAYES
Verify Sprinkler Sign Off 2/22/2021 Approved JOHN HAYES
Interior/Exterior Lathing 2/25/2021 Partial Approval BRENDAN LOONEY
Drywall Nailing 3/15/2021 Approved DAVID MATSON
Interior/Exterior Lathing 3/15/2021 Approved DAVID MATSON
Shower Pan 3/15/2021 Approved DAVID MATSON
Final 8/2/2021 Corrections Issued CHRISTOPHE COCHRAN
Green Building Final 8/2/2021 Approved CHRISTOPHE COCHRAN
SGSOV-Seismic Gas S/O Valve 8/2/2021 SGSOV Approved CHRISTOPHE COCHRAN
Service/Power Release 8/2/2021 Approved CHRISTOPHE COCHRAN
Smoke Detectors 8/2/2021 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 8/5/2021 Approved CHRISTOPHE COCHRAN
Service/Power Release 8/5/2021 Approved CHRISTOPHE COCHRAN
Special/Order Compliance 8/7/2021 Corrections Issued MICHAEL PELHAM
Final 8/28/2021 Conditional Approval MICHAEL PELHAM