2529 S WESTWOOD BLVD 90064

Certificate Information: 2529 S WESTWOOD BLVD 90064

Application / Permit
19010-20000-06361
Plan Check / Job No.
B19VN22622
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW 24' X 29'-4" 2-STORY IRREGULAR SHAPE DETACHED ACCESSORY DWELLING UNIT WITH 18' X 19'ATTACHED CARPORT.
Permit Issued
Issued on 11/24/2020
Issuing Office
Current Status
CofO Issued on 8/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 SERGIO MUNIZ
Corrections Issued 2/7/2020 SERGIO MUNIZ
Green Plans Picked Up 2/7/2020 APPLICANT
Quality Review Completed 2/13/2020 OMID HEDAYAT
Building Plans Picked Up 2/21/2020 APPLICANT
Applicant returned to address corrections 5/29/2020 SERGIO MUNIZ
Plan Check Approved 7/15/2020 SERGIO MUNIZ
Issued 11/24/2020 APPLICANT
CofO in Progress 8/11/2023 JESUS PINEDA
Permit Finaled 8/15/2023 DANIEL ORRANTE
CofO Issued 8/15/2023 DANIEL ORRANTE
Permit Finaled 8/15/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 3/6/2020 JOHN LIN
Eng Process Fee Ord 176,300 Cleared 3/6/2020 JOHN LIN
Specific Plan Cleared 3/9/2020 FREDDY GARCIA
Hydrant and Access approval Cleared 4/1/2020 JOHN CONNEALLY
Green Code Cleared 4/17/2020 SERGIO MUNIZ
GPI Written Notices Cleared 5/29/2020 SERGIO MUNIZ
Grading Pre-Inspection Cleared 5/29/2020 SERGIO MUNIZ
Low Impact Development Cleared 6/18/2020 MARTIN FRAGOSO
Roof/Waste drainage to street Cleared 7/2/2020 CATHERINE ADROVER
Sewer availability Cleared 7/6/2020 CATHERINE ADROVER

Contact Information

Contractor Construction For Less; Lic. No.: 965043-B 23355 COLLINS STREET      WOODLAND HILLS, CA 91367
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 12/14/2020 Partial Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 1/4/2021 Not Ready for Inspection PIERRE VEGA
Underground Mechanical 1/4/2021 Partial Approval PIERRE VEGA
FLOOD-Elevation Certificate 1/7/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/7/2021 Corrections Issued OGANES TARAKHCHYAN
FLOOD-Elevation Certificate 1/12/2021 Not Ready for Inspection OGANES TARAKHCHYAN
Footing/Foundation/Slab 1/12/2021 Partial Approval OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 2/4/2021 Corrections Issued RICHARD ROBLES
Wood Frame 2/4/2021 Not Ready for Inspection RICHARD ROBLES
FLOOD-Elevation Certificate 2/9/2021 Approved RICHARD ROBLES
Footing/Foundation/Slab 2/9/2021 Approved RICHARD ROBLES
Floor/Roof Diaphrgm/Shear Wall 3/17/2021 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 3/26/2021 Partial Approval KEVIN SARGSYAN
Underground Mechanical 3/26/2021 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 4/1/2021 Partial Approval EVAN COOPER
Gas Test 4/1/2021 Not Ready for Inspection EVAN COOPER
PLUMBING-Rough 4/1/2021 Approved EVAN COOPER
Sewer 4/1/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 5/24/2021 Not Ready for Inspection WILLIAM MICHALAK
Green Building Rough 5/24/2021 Not Ready for Inspection WILLIAM MICHALAK
Interior/Exterior Lathing 5/24/2021 Conditional Approval WILLIAM MICHALAK
Rough-Elec/Plmb/HVAC 5/24/2021 Not Ready for Inspection WILLIAM MICHALAK
ELECTRICAL-Rough 6/1/2021 Corrections Issued EVAN COOPER
HVAC-Rough 6/1/2021 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 6/1/2021 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 6/17/2021 Conditional Approval DONALD GALLAGHER
ELECTRICAL-Rough 6/17/2021 Partial Approval DONALD GALLAGHER
FLOOD-Proofing Certificate 6/17/2021 Approved DONALD GALLAGHER
Green Building Rough 6/17/2021 Approved DONALD GALLAGHER
HVAC-Rough 6/17/2021 Partial Approval DONALD GALLAGHER
Verify Sprinkler Sign Off 6/17/2021 Conditional Approval DONALD GALLAGHER
Special/Order Compliance 6/22/2021 Corrections Issued OGANES TARAKHCHYAN
Insulation 6/30/2021 Partial Approval OGANES TARAKHCHYAN
Drywall Nailing 7/14/2021 Approved KEVIN SARGSYAN
Gas Test 10/6/2021 Partial Approval RYAN SALAZAR
Sewer 12/7/2021 Approved JOHNNY MIRANDA
Gas Test 12/15/2021 No Access for Inspection KRISTEN CAUSEY
Gas Test 1/12/2022 Corrections Issued KEVIN SARGSYAN
Service/Power Release 1/12/2022 Not Ready for Inspection KEVIN SARGSYAN
BUILDING-Rough-Frame 5/10/2022 No Access for Inspection JOHNNY MIRANDA
Final 5/10/2022 No Access for Inspection JOHNNY MIRANDA
Gas Test 5/10/2022 Approved JOHNNY MIRANDA
Green Building Final 5/10/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 5/10/2022 SGSOV Not Ready JOHNNY MIRANDA
Service/Power Release 5/10/2022 No Access for Inspection JOHNNY MIRANDA
Smoke Detectors 5/10/2022 No Access for Inspection JOHNNY MIRANDA
Verify Sprinkler Sign Off 5/10/2022 No Access for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 8/24/2022 Approved ANDREW NAVE
BUILDING-Rough-Frame 2/13/2023 Approved JOHNNY MIRANDA
Final 2/13/2023 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 2/13/2023 SGSOV Approved JOHNNY MIRANDA
Service/Power Release 2/13/2023 Approved JOHNNY MIRANDA
Smoke Detectors 2/13/2023 Approved JOHNNY MIRANDA
Verify Sprinkler Sign Off 2/13/2023 Approved JOHNNY MIRANDA
Final 3/14/2023 Corrections Issued JOHNNY MIRANDA
Final 8/10/2023 OK to Issue CofO JESUS PINEDA