NEW 2-STORY SINGLE FAMILY DWELLING WITH ATTACHED GARAGE; EQUIPPED WITH NFPA 13'D FIRE SPRINKLERS THROUGHOUT
Permit Issued
Issued on 8/9/2023
Issuing Office
Valley
Current Status
Issued on 8/9/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/30/2019 APPLICANT
Assigned to Plan Check Engineer 2/6/2020 SELLA BENYAMIN
Corrections Issued 2/13/2020 SELLA BENYAMIN
Quality Review Completed 2/14/2020 STEVEN KIM
Building Plans Picked Up 2/18/2020 APPLICANT
Green Plans Picked Up 2/18/2020 APPLICANT
Plan Check Approved 10/19/2020 SELLA BENYAMIN
Issued 8/9/2023 APPLICANT

Permit Application Clearance Information

Low Impact Development Cleared 8/20/2020 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 8/24/2020 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 8/25/2020 ADRIAN CASTRO
Sewer availability Cleared 8/25/2020 ADRIAN CASTRO
Hydrant and Access approval Cleared 9/24/2020 KURT CORRAL
Green Code Cleared 10/1/2020 MICHAEL AYERS

Contact Information

Contractor Saran Group Development; Lic. No.: 1105674-B 4825 ARCOLA AVE      NORTH HOLLYWOOD, CA 91601

Inspector Information

GAREN HAYRAPETYAN, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI
ROBERTO PALACIOS-LOPEZ, (818) 374-1171 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 11/20/2023 Not Ready for Inspection KEVIN BERBERYAN
Pre-Inspection 11/20/2023 Partial Inspection KEVIN BERBERYAN
Excavation/Setback/Form/Re-Bar 12/8/2023 Not Ready for Inspection JENNIFER RABUCHIN
Footing/Foundation/Slab 12/8/2023 Not Ready for Inspection JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 12/15/2023 Partial Approval JENNIFER RABUCHIN
Footing/Foundation/Slab 12/15/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 12/15/2023 Partial Approval JENNIFER RABUCHIN
Excavation/Setback/Form/Re-Bar 1/9/2024 Not Ready for Inspection JOHN COLEMAN
Underground Mechanical 1/12/2024 Partial Approval CRAIG DAVIS
Excavation/Setback/Form/Re-Bar 1/24/2024 Approved JOHN COLEMAN
Underground Mechanical 1/24/2024 Approved JOHN COLEMAN
Deputy Reinf. Concrete 1/29/2024 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 1/30/2024 No Access for Inspection JOHN HAYES
Deputy Other (see comments) 2/2/2024 Conditional Approval DAVID MATSON
BUILDING-Rough-Frame 2/15/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 2/15/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 2/15/2024 Not Ready for Inspection MISAEL ESPARZA
Wood Frame 2/15/2024 Corrections Issued MISAEL ESPARZA
Wood Frame 2/20/2024 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/9/2024 Not Ready for Inspection MISAEL ESPARZA
Green Building Rough 4/9/2024 Not Ready for Inspection MISAEL ESPARZA
Verify Sprinkler Sign Off 4/9/2024 Not Ready for Inspection MISAEL ESPARZA
Floor/Roof Diaphrgm/Shear Wall 4/12/2024 Not Ready for Inspection THOMAS FINNILA
Wood Frame 4/12/2024 Not Ready for Inspection THOMAS FINNILA
BUILDING-Rough-Frame 5/14/2024 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Not Ready for Inspection JOSE AVILA
Floor/Roof Diaphrgm/Shear Wall 7/24/2024 Partial Approval JOSE AVILA
ELECTRICAL-Rough 9/18/2024 Approved JOSE AVILA
HVAC-Rough 9/18/2024 Corrections Issued JOSE AVILA
PLUMBING-Rough 9/18/2024 Corrections Issued JOSE AVILA
HVAC-Rough 10/9/2024 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 10/9/2024 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 10/16/2024 Approved JOSE AVILA
ELECTRICAL-Rough 10/16/2024 Approved JOSE AVILA
Green Building Rough 10/16/2024 Approved JOSE AVILA
HVAC-Rough 10/16/2024 Approved JOSE AVILA
Interior/Exterior Lathing 10/16/2024 Partial Approval JOSE AVILA
PLUMBING-Rough 10/16/2024 Approved JOSE AVILA
Verify Sprinkler Sign Off 10/16/2024 Approved JOSE AVILA
Insulation 10/28/2024 Conditional Approval MICHAEL CORTEZ
Drywall Nailing 11/18/2024 Approved JOSE AVILA
Shower Pan 11/18/2024 Approved JOSE AVILA
Interior/Exterior Lathing 11/26/2024 Approved ROBERTO PALACIOS-LOPEZ
Interior/Exterior Lathing 1/7/2025 Approved ROBERTO PALACIOS-LOPEZ
Service/Power Release 1/7/2025 Not Ready for Inspection ROBERTO PALACIOS-LOPEZ
ELECTRICAL-Final 2/21/2025 Not Ready for Inspection JOSE AVILA
Excavation/Setback/Form/Re-Bar 3/28/2025 Approved JOSE AVILA
ELECTRICAL-Final 6/10/2025 Corrections Issued JOSE AVILA
ELECTRICAL-Final 9/10/2025 Approved JOSE AVILA
HVAC-Final 9/10/2025 Approved JOSE AVILA
Service/Power Release 12/12/2025 Approved JUAN VALENZUELA
ELECTRICAL-Final 12/29/2025 Approved JAVIER RAMOS JR
Final 12/29/2025 Corrections Issued JAVIER RAMOS JR
Green Building Final 12/29/2025 Approved JAVIER RAMOS JR
PLUMBING-Final 12/29/2025 Approved JAVIER RAMOS JR
SGSOV-Seismic Gas S/O Valve 12/29/2025 SGSOV Approved JAVIER RAMOS JR
Smoke Detectors 12/29/2025 Approved JAVIER RAMOS JR