2803 N GRIFFITH PARK BLVD 90027
Certificate Information: 2803 N GRIFFITH PARK BLVD 90027
- Application / Permit
- 19010-20000-06335
- Plan Check / Job No.
- B19VN22594
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW (35'-8"x 35'-10 1/4") DET ACCESSORY DWELLING UNIT WITH ATT 2-CAR GARAGE PER AB 494 AND SB 229. WORK PER ENGINEER.
- Permit Issued
- Issued on 4/29/2021
- Issuing Office
- Current Status
- Issued on 4/29/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/30/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 2/6/2020 | TROY DEGUZMAN |
| Green Plans Picked Up | 2/7/2020 | APPLICANT |
| Corrections Issued | 2/11/2020 | TROY DEGUZMAN |
| Quality Review Completed | 2/11/2020 | CHON CHIO KUO |
| Building Plans Picked Up | 2/14/2020 | APPLICANT |
| Applicant returned to address corrections | 1/15/2021 | TROY DEGUZMAN |
| Plan Check Approved | 4/22/2021 | TROY DEGUZMAN |
| Issued | 4/29/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/3/2020 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 12/4/2020 | CECILIO NAVARRO |
| Sewer availability | Cleared | 12/4/2020 | CECILIO NAVARRO |
| Grading Pre-Inspection | Cleared | 1/14/2021 | TROY DEGUZMAN |
| Low Impact Development | Cleared | 1/23/2021 | ORVAL HERNANDEZ-MARCI |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | ROSA SILVA |
| Hydrant and Access approval | Cleared | 2/4/2021 | JOHN CONNEALLY |
| Green Code | Cleared | 4/22/2021 | AARON COSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kardjian,, Vahe Matios; Lic. No.: C40821 | 1648 W GLENOAKS BLVD STE 102 GLENDALE, CA 91201 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 7/13/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Pre-Inspection | 7/13/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 7/15/2022 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Partial Inspection | JOSEPH MCGARRY |
| Reinforced Masonry Frame | 11/17/2022 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Corrections Issued | LILIANA PORTILLO |
| Deputy Wood Construction | 7/12/2023 | Partial Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2023 | Corrections Issued | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 8/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 8/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 8/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 8/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 8/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 8/27/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 8/27/2024 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 9/13/2024 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/13/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Rough | 9/13/2024 | Not Ready for Inspection | JEFFREY MEAD |
| HVAC-Rough | 9/13/2024 | Corrections Issued | JEFFREY MEAD |
| PLUMBING-Rough | 9/13/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 9/13/2024 | Not Ready for Inspection | JEFFREY MEAD |
| Wood Frame | 9/13/2024 | Not Ready for Inspection | JEFFREY MEAD |
| ELECTRICAL-Rough | 9/20/2024 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 9/20/2024 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 9/20/2024 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 9/20/2024 | Approved | ENRIQUE MIRELES |
| Insulation | 10/24/2024 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 6/24/2025 | Approved | ALEX COLIN |
| Green Building Rough | 6/24/2025 | Approved | ALEX COLIN |