814 N SPAULDING AVE 90046

Certificate Information: 814 N SPAULDING AVE 90046

Application / Permit
19010-20000-06309
Plan Check / Job No.
B19VN22572
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 76'-3" X 30' IRREGULAR SHAPED TWO STORY SINGLE FAMILY DWELLING WITH 9'-6" X 28'-3" ROOF TOP DECK AND ATTACHED 2-CAR GARAGE ALL WORK PER ENGINEERING NFPA 13D FIRE SPRINKLER REQUIRED
Permit Issued
Issued on 2/10/2021
Issuing Office
Current Status
CofO Issued on 4/1/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/9/2020 SEWADA ZADOORIAN MILAGARDI
Green Plans Picked Up 1/14/2020 APPLICANT
Corrections Issued 1/15/2020 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 1/21/2020 OMID HEDAYAT
Building Plans Picked Up 1/28/2020 APPLICANT
Applicant returned to address corrections 4/15/2020 SEWADA ZADOORIAN MILAGARDI
Applicant returned to address corrections 5/13/2020 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 5/27/2020 SEWADA ZADOORAN MILAGARDI
Plan Check Approved 2/9/2021 SEWADA ZADOORAN MILAGARDI
Issued 2/10/2021 APPLICANT
CofO in Progress 3/17/2022 ARTHUR SARGSYAN
Permit Finaled 4/1/2022 DEROLD HAUFF
CofO Issued 4/1/2022 DEROLD HAUFF
Permit Finaled 4/1/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/19/2020 GUILLERMO PETRA
Permit Cleared 2/19/2020 GUILLERMO PETRA
Permit Cleared 2/19/2020 GUILLERMO PETRA
Sewer availability Cleared 2/19/2020 GUILLERMO PETRA
Hydrant and Access approval Cleared 2/20/2020 GEORGE SUCHAND
Green Code Cleared 3/3/2020 DAVID MATSON
Trees in Parkway Cleared 3/4/2020 ADRIAN SANCHEZ
Low Impact Development Cleared 3/5/2020 JORGE MEJIA LEMUS
Roof/Waste drainage to street Cleared 3/5/2020 JUAN ASHTON

Contact Information

Contractor Numa Brothers Construction Inc; Lic. No.: 859857-B 18375 VENTURA BLVD #270      TARZANA, CA 91356
Engineer Landers,, Jesse Eugene; Lic. No.: C83060 2101 BENECIA AVE      LOS ANGELES, CA 90025

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 2/17/2021 Approved CHRIS CHRISTENSEN
Underground Mechanical 2/26/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/4/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 3/12/2021 Partial Approval CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/3/2021 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 5/5/2021 Partial Approval CHRIS CHRISTENSEN
ELECTRICAL-Rough 5/12/2021 Approved CHRIS CHRISTENSEN
Floor/Roof Diaphrgm/Shear Wall 5/12/2021 Partial Approval CHRIS CHRISTENSEN
HVAC-Rough 5/12/2021 Approved CHRIS CHRISTENSEN
PLUMBING-Rough 5/12/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 5/19/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Wood Frame 5/19/2021 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 6/3/2021 Conditional Approval CHRIS CHRISTENSEN
Green Building Rough 6/3/2021 Conditional Approval CHRIS CHRISTENSEN
Shower Pan 6/3/2021 Not Ready for Inspection CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 6/3/2021 Conditional Approval CHRIS CHRISTENSEN
Insulation 6/14/2021 Approved CHRIS CHRISTENSEN
Shower Pan 6/14/2021 Approved CHRIS CHRISTENSEN
Drywall Nailing 7/1/2021 Approved CHRIS CHRISTENSEN
Green Building Rough 7/1/2021 Approved CHRIS CHRISTENSEN
Interior/Exterior Lathing 8/3/2021 Partial Approval CHRIS CHRISTENSEN
BUILDING-Rough-Frame 1/21/2022 Conditional Approval CHRIS CHRISTENSEN
ELECTRICAL-Final 1/21/2022 Approved CHRIS CHRISTENSEN
Final 1/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
Footing/Foundation/Slab 1/21/2022 Approved CHRIS CHRISTENSEN
Green Building Final 1/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
HVAC-Final 1/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 1/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 1/21/2022 SGSOV Not Ready CHRIS CHRISTENSEN
Service/Power Release 1/21/2022 Approved CHRIS CHRISTENSEN
Smoke Detectors 1/21/2022 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 1/21/2022 Not Ready for Inspection CHRIS CHRISTENSEN
PLUMBING-Final 1/27/2022 Not Ready for Inspection SHAVONNE ESPINOZA
HVAC-Final 1/28/2022 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 2/3/2022 Conditional Approval CHRIS CHRISTENSEN
Final 2/3/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 2/3/2022 Corrections Issued CHRIS CHRISTENSEN
HVAC-Final 2/3/2022 Approved CHRIS CHRISTENSEN
PLUMBING-Final 2/3/2022 Approved CHRIS CHRISTENSEN
SGSOV-Seismic Gas S/O Valve 2/3/2022 SGSOV Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 2/3/2022 Not Ready for Inspection CHRIS CHRISTENSEN
BUILDING-Rough-Frame 3/1/2022 Approved CHRIS CHRISTENSEN
Final 3/1/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 3/1/2022 Corrections Issued CHRIS CHRISTENSEN
Pool/Spa Cover 3/1/2022 Approved CHRIS CHRISTENSEN
Verify Sprinkler Sign Off 3/1/2022 Approved CHRIS CHRISTENSEN
Final 3/10/2022 Corrections Issued CHRIS CHRISTENSEN
Green Building Final 3/10/2022 Corrections Issued CHRIS CHRISTENSEN
Final 3/14/2022 OK to Issue CofO ARTHUR SARGSYAN
Green Building Final 3/14/2022 Approved ARTHUR SARGSYAN
ELECTRICAL-Final 3/17/2022 Partial Inspection CRAIG DAVIS