(N) 21' x 27'-6" TWO-STORY ACCESSORY DWELLING UNIT
Permit Issued
Issued on 5/8/2020
Issuing Office
Valley
Current Status
CofO Issued on 2/25/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2019 APPLICANT
Assigned to Plan Check Engineer 1/30/2020 SEAN SHAHMIRI
Corrections Issued 2/5/2020 SEAN SHAHMIRI
Green Plans Picked Up 2/5/2020 APPLICANT
Quality Review Completed 2/18/2020 OMID HEDAYAT
Building Plans Picked Up 2/19/2020 APPLICANT
Plan Check Approved 3/12/2020 SEAN SHAHMIRI
Issued 5/8/2020 LADBS
CofO in Progress 2/9/2021 RUBEN SALAS
CofO in Progress 2/9/2021 RUBEN SALAS
Permit Finaled 2/25/2021 DEROLD HAUFF
CofO Issued 2/25/2021 DEROLD HAUFF
Permit Finaled 2/25/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/26/2020 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 2/26/2020 CELINA MORENO
Sewer availability Cleared 2/26/2020 CELINA MORENO
Green Code Cleared 3/5/2020 DAVID MATSON
Hydrant and Access approval Cleared 3/5/2020 JOHN CONNEALLY
Low Impact Development Cleared 3/9/2020 MITESH PATEL
Roof/Waste drainage to street Cleared 3/9/2020 EMIL KYUPELYAN

Contact Information

Contractor Owner-Builder       ,
Engineer Hsiao,, Stephanie; Lic. No.: C75937 6140 MONTEREY RD APT 427      LOS ANGELES, CA 90042

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/3/2020 Partial Inspection ROBERT VORHIS
Underground Mechanical 6/4/2020 Partial Approval ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 6/9/2020 Partial Approval ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 6/22/2020 Not Ready for Inspection ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 6/25/2020 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 7/7/2020 Partial Approval ROBERT VORHIS
Floor/Roof Diaphrgm/Shear Wall 7/13/2020 Partial Approval ROBERT VORHIS
ELECTRICAL-Rough 7/30/2020 Approved ROBERT VORHIS
HVAC-Rough 7/30/2020 Partial Approval ROBERT VORHIS
HVAC-Rough 8/10/2020 Not Ready for Inspection ROBERT VORHIS
PLUMBING-Rough 8/10/2020 Approved ROBERT VORHIS
BUILDING-Rough-Frame 8/12/2020 Partial Inspection RUBEN SALAS
Green Building Rough 8/12/2020 Partial Inspection RUBEN SALAS
HVAC-Rough 8/12/2020 Partial Inspection RUBEN SALAS
Verify Sprinkler Sign Off 8/12/2020 Partial Inspection RUBEN SALAS
Floor/Roof Diaphrgm/Shear Wall 8/13/2020 Corrections Issued RUBEN SALAS
HVAC-Rough 8/13/2020 Corrections Issued RUBEN SALAS
BUILDING-Rough-Frame 8/18/2020 Partial Approval RUBEN SALAS
HVAC-Rough 8/18/2020 Partial Approval RUBEN SALAS
Insulation 9/1/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 9/1/2020 Partial Approval RUBEN SALAS
Drywall Nailing 9/14/2020 Approved RUBEN SALAS
Green Building Rough 9/14/2020 Approved RUBEN SALAS
Interior/Exterior Lathing 9/18/2020 Approved RUBEN SALAS
Shower Pan 9/18/2020 Approved RUBEN SALAS
PLUMBING-Rough 12/3/2020 Partial Approval SCOTT FINNILA
Sewer 12/4/2020 Partial Approval SCOTT FINNILA
BUILDING-Rough-Frame 1/13/2021 Approved RUBEN SALAS
Final 1/13/2021 Corrections Issued RUBEN SALAS
Footing/Foundation/Slab 1/13/2021 Approved RUBEN SALAS
Green Building Final 1/13/2021 Not Ready for Inspection RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 1/13/2021 SGSOV Not Ready RUBEN SALAS
Service/Power Release 1/13/2021 Not Ready for Inspection RUBEN SALAS
Smoke Detectors 1/13/2021 Approved RUBEN SALAS
Verify Sprinkler Sign Off 1/13/2021 Approved RUBEN SALAS
Pre-Inspection 1/15/2021 Approved RUBEN SALAS
Final 2/9/2021 OK to Issue CofO RUBEN SALAS
Green Building Final 2/9/2021 Approved RUBEN SALAS
SGSOV-Seismic Gas S/O Valve 2/9/2021 SGSOV Approved RUBEN SALAS
Service/Power Release 2/9/2021 Approved RUBEN SALAS