1208 N ALEXANDRIA AVE 90029
Certificate Information: 1208 N ALEXANDRIA AVE 90029
- Application / Permit
- 19010-20000-06293
- Plan Check / Job No.
- B19VN22546
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 21' x 27'-6" TWO-STORY ACCESSORY DWELLING UNIT
- Permit Issued
- Issued on 5/8/2020
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/25/2021
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2019 | APPLICANT |
| Assigned to Plan Check Engineer | 1/30/2020 | SEAN SHAHMIRI |
| Corrections Issued | 2/5/2020 | SEAN SHAHMIRI |
| Green Plans Picked Up | 2/5/2020 | APPLICANT |
| Quality Review Completed | 2/18/2020 | OMID HEDAYAT |
| Building Plans Picked Up | 2/19/2020 | APPLICANT |
| Plan Check Approved | 3/12/2020 | SEAN SHAHMIRI |
| Issued | 5/8/2020 | LADBS |
| CofO in Progress | 2/9/2021 | RUBEN SALAS |
| CofO in Progress | 2/9/2021 | RUBEN SALAS |
| Permit Finaled | 2/25/2021 | DEROLD HAUFF |
| CofO Issued | 2/25/2021 | DEROLD HAUFF |
| Permit Finaled | 2/25/2021 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/26/2020 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 2/26/2020 | CELINA MORENO |
| Sewer availability | Cleared | 2/26/2020 | CELINA MORENO |
| Green Code | Cleared | 3/5/2020 | DAVID MATSON |
| Hydrant and Access approval | Cleared | 3/5/2020 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 3/9/2020 | MITESH PATEL |
| Roof/Waste drainage to street | Cleared | 3/9/2020 | EMIL KYUPELYAN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hsiao,, Stephanie; Lic. No.: C75937 | 6140 MONTEREY RD APT 427 LOS ANGELES, CA 90042 |
Inspector Information
| FREDDIE RIVERA, (213) 202-3437 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/3/2020 | Partial Inspection | ROBERT VORHIS |
| Underground Mechanical | 6/4/2020 | Partial Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 6/9/2020 | Partial Approval | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 6/22/2020 | Not Ready for Inspection | ROBERT VORHIS |
| Excavation/Setback/Form/Re-Bar | 6/25/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/7/2020 | Partial Approval | ROBERT VORHIS |
| Floor/Roof Diaphrgm/Shear Wall | 7/13/2020 | Partial Approval | ROBERT VORHIS |
| ELECTRICAL-Rough | 7/30/2020 | Approved | ROBERT VORHIS |
| HVAC-Rough | 7/30/2020 | Partial Approval | ROBERT VORHIS |
| HVAC-Rough | 8/10/2020 | Not Ready for Inspection | ROBERT VORHIS |
| PLUMBING-Rough | 8/10/2020 | Approved | ROBERT VORHIS |
| BUILDING-Rough-Frame | 8/12/2020 | Partial Inspection | RUBEN SALAS |
| Green Building Rough | 8/12/2020 | Partial Inspection | RUBEN SALAS |
| HVAC-Rough | 8/12/2020 | Partial Inspection | RUBEN SALAS |
| Verify Sprinkler Sign Off | 8/12/2020 | Partial Inspection | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2020 | Corrections Issued | RUBEN SALAS |
| HVAC-Rough | 8/13/2020 | Corrections Issued | RUBEN SALAS |
| BUILDING-Rough-Frame | 8/18/2020 | Partial Approval | RUBEN SALAS |
| HVAC-Rough | 8/18/2020 | Partial Approval | RUBEN SALAS |
| Insulation | 9/1/2020 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 9/1/2020 | Partial Approval | RUBEN SALAS |
| Drywall Nailing | 9/14/2020 | Approved | RUBEN SALAS |
| Green Building Rough | 9/14/2020 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 9/18/2020 | Approved | RUBEN SALAS |
| Shower Pan | 9/18/2020 | Approved | RUBEN SALAS |
| PLUMBING-Rough | 12/3/2020 | Partial Approval | SCOTT FINNILA |
| Sewer | 12/4/2020 | Partial Approval | SCOTT FINNILA |
| BUILDING-Rough-Frame | 1/13/2021 | Approved | RUBEN SALAS |
| Final | 1/13/2021 | Corrections Issued | RUBEN SALAS |
| Footing/Foundation/Slab | 1/13/2021 | Approved | RUBEN SALAS |
| Green Building Final | 1/13/2021 | Not Ready for Inspection | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 1/13/2021 | SGSOV Not Ready | RUBEN SALAS |
| Service/Power Release | 1/13/2021 | Not Ready for Inspection | RUBEN SALAS |
| Smoke Detectors | 1/13/2021 | Approved | RUBEN SALAS |
| Verify Sprinkler Sign Off | 1/13/2021 | Approved | RUBEN SALAS |
| Pre-Inspection | 1/15/2021 | Approved | RUBEN SALAS |
| Final | 2/9/2021 | OK to Issue CofO | RUBEN SALAS |
| Green Building Final | 2/9/2021 | Approved | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 2/9/2021 | SGSOV Approved | RUBEN SALAS |
| Service/Power Release | 2/9/2021 | Approved | RUBEN SALAS |